Earned Value (EV)
Budgeted cost of work actually performed to date. Computed as percent complete times the budget for that work, and used as the performance baseline in cost and schedule variance formulas.
Cost Variance (CV)
CV equals earned value minus actual cost. A negative result means the project has spent more than the value of work completed, indicating a cost overrun at the measurement date.
Schedule Variance (SV)
SV equals earned value minus planned value. A negative result means less work was completed than planned by that date; expressed in currency, it is a schedule proxy rather than time.
Cost Performance Index
CPI equals earned value divided by actual cost. A value below 1.0 means each unit of currency buys less work than planned; CPI is commonly used to forecast final cost.
Schedule Performance Index
SPI equals earned value divided by planned value. A value below 1.0 indicates work is proceeding slower than planned; SPI trends toward 1.0 as a project nears completion.
Estimate at Completion
Projected total cost of the project. Common forms: actual cost plus remaining budget, budget divided by CPI when current efficiency persists, or a fresh bottom-up estimate of remaining work.
Budget at Completion
The total approved budget for the scope of work in the project baseline. It anchors variance at completion and the to-complete performance index calculations.
To-Complete Performance Index
TCPI equals remaining budget divided by remaining funds. It states the cost efficiency required on all remaining work to meet a stated budget target.
Variance at Completion
VAC equals budget at completion minus estimate at completion. A negative value forecasts a final cost overrun relative to the approved baseline budget.
Critical Path
The longest-duration path through the network, which sets the shortest possible project duration. Activities on it have zero or negative total float.
Total Float
Amount of time an activity can be delayed without delaying the project finish. Calculated as late start minus early start, or late finish minus early finish.
Free Float
Time an activity can slip without delaying the early start of any successor. Free float is always less than or equal to total float for the same activity.
PERT Expected Duration
Weighted average of optimistic, most likely, and pessimistic estimates, using weights of one, four, and one divided by six. It approximates a beta-distributed activity duration.
Crashing
Adding resources or paying overtime to shorten duration of critical-path activities. Effective only on the critical path and chosen by lowest cost per unit of time saved.
Fast Tracking
Overlapping activities normally performed in sequence to compress schedule. It adds risk of rework and coordination errors and works best where activities have limited dependency.
Resource Leveling
Rescheduling activities to resolve resource over-allocation, often by delaying work beyond its float. It frequently extends project duration and can change the critical path.
Resource Smoothing
Adjusting activity timing within available float to flatten resource demand without changing the project finish date. Unlike leveling, it never delays the critical path.
Risk Transfer
Shifting financial consequence of a threat to a third party, as with insurance or fixed-price contracts. Transfer does not eliminate the risk itself, only ownership of its impact.
Risk Mitigation
Action taken to reduce probability or impact of a threat before it occurs. Differs from contingency planning, which prepares a response for after the risk event happens.
Secondary Risk
A new risk created as a direct result of implementing a risk response. It must be identified and assessed separately from the original threat.
Residual Risk
Risk that remains after planned responses have been applied. Accepted residual risk should be documented and monitored through the risk register.
Contingency Reserve
Budget or time set aside for known risks with identified responses. Held by the project manager and distinct from management reserve for unknown risks.
Management Reserve
Budget held outside the project baseline for unplanned scope or unknown risks. Release typically requires sponsor or senior management approval and changes the cost baseline.
Cost of Quality
Sum of conformance costs (prevention and appraisal) and non-conformance costs (internal and external failure). External failures such as warranty claims usually cost the most.
Scope Creep
Uncontrolled expansion of scope without corresponding adjustments to time, cost, or resources. Prevented by formal change control and a defined scope baseline.
Change Control Board
Formal group that reviews, approves, or rejects change requests affecting the project baseline. Its decisions are recorded and communicated to affected stakeholders.
Work Breakdown Structure
Hierarchical decomposition of total project scope into manageable work packages. The lowest level, the work package, supports estimating, scheduling, and assignment of accountability.
Responsibility Assignment Matrix
Chart linking work packages to team members. A RACI variant labels each person as responsible, accountable, consulted, or informed, with exactly one accountable owner per task.
Stakeholder Salience
Model ranking stakeholders by power, legitimacy, and urgency. Stakeholders holding all three attributes are definitive; those with one are latent and may need monitoring.
Configuration Management
Discipline controlling changes to deliverables and documents through identification, status accounting, and audits. Ensures the delivered product matches its approved specification.
Lessons Learned Register
Repository of knowledge gained during the project, recorded as work proceeds rather than only at closure. Used to improve current and future project performance.
Decision Tree Analysis
Technique comparing alternatives by expected monetary value, multiplying outcome value by probability and summing branches. Supports selection among risky options under uncertainty.