Sole-Source Supplier in Financial Distress Demands Exclusivity for Priority Allocation
You are the SQE for a sole-source supplier of a molded power-module housing. The supplier runs one plant, is at 92% of demonstrated capacity, and supplies 100% of your 480,000 units per year. A credit report shows a two-notch downgrade, and the supplier has disclosed that its resin distributor moved it to cash-on-delivery. Two of the last six shipments were late by 5 and 9 days, and your demand forecast rises 20% in two quarters. Your tooling is at the supplier's site under a purchase-order clause that is silent on ownership and on the right to move it. Qualifying a new molder, including tool transfer, PPAP, and customer approval, takes about 14 weeks; you hold 5 weeks of inventory. The supplier's owner has asked for a 12% price increase and a three-year exclusive agreement in exchange for "priority allocation." Your VP asks whether to sign.
1. How would you assess and prioritize this risk before any commercial decision?
Read the worked answer
Build a risk register with likelihood, impact, velocity, and detectability for each exposure:
- Supply continuity: 5 weeks of inventory against a 14-week qualification creates a potential 9-week gap if the supplier fails. Quantify revenue at risk per week and the cost of building buffer stock.
- Capacity: 92% utilization cannot absorb a 20% demand increase; the constraint may be press time, labor, or resin. Request a capacity study by work center and a constrained-capacity plan.
- Financial: a two-notch downgrade plus cash-on-delivery indicates a liquidity problem. Request recent financial statements, payment behavior, and a 13-week cash view if available; set up ongoing monitoring triggers.
- Single site and sub-tier: one plant, one resin distributor. Map the sub-tier, alternate resin approvals, and any single points of failure.
- Tooling and contractual: the purchase order is silent on tool ownership and right to move, which is a serious exposure. Obtain tooling records, title, and condition; clarify access rights.
- The offer itself: 'priority allocation' is unverifiable and an exclusive agreement increases lock-in. Treat it as a claim to be tested, not a benefit.
Rank by risk score and time to impact; the 9-week gap and tooling ambiguity are the top items.
2. Should the VP sign the three-year exclusive agreement and 12% increase? What counterproposal would you recommend?
Read the worked answer
Do not sign a three-year exclusive agreement. It converts a temporary dependency into a long-term lock-in and removes leverage just when the supplier is least stable. The 12% increase may be negotiable, but only against verified cost data and performance commitments.
Counterproposal:
- Short-term supply agreement (6 months) with capacity reservation at a specified volume, delivery performance commitments, and a right to audit capacity and financial status.
- Price: open-book review of resin and conversion costs; any increase tied to verified indices and offset by productivity or CoPQ recovery. Avoid a flat 12% with no floor or ceiling.
- Tooling amendment: confirm your ownership, right to access and move tooling, and obligation to return tooling and process documentation on request. This is non-negotiable.
- Allocation language: define allocation rules, notice periods, and penalties rather than accepting a vague promise.
- Dual-source commitment: begin qualifying a second molder now; do not make exclusivity a condition of support.
If the supplier refuses tooling rights, treat that as a red flag and escalate. The goal is continuity, not punishment, but the contract must protect the business if the supplier fails.
3. What 30/60/90-day operational actions would you take to reduce the exposure?
Read the worked answer
Days 1–30: build buffer inventory toward 8–10 weeks within cash constraints; secure tooling documentation and a written access agreement; request financial and capacity data; identify and RFQ two alternate molders; check alternate resin approvals; start weekly supply reviews with the supplier; brief your customer on the risk and mitigation plan.
Days 31–60: complete new-molder selection and tool-transfer plan; run trial molds and dimensional layout; begin PPAP for the new source; audit the supplier's resin sub-tier and cash-on-delivery impact; confirm allocation rules and delivery commitments; set financial monitoring triggers (credit score, payment behavior, days past due).
Days 61–90: complete PPAP and customer approval for the second source; ramp a 70/30 or 80/20 split to create redundancy without destabilizing the incumbent; validate buffer levels against the 20% demand increase; update the risk register and business continuity plan; review pricing with verified cost data.
Report progress to the VP monthly with a single risk dashboard. If the supplier's financial condition worsens, trigger the pre-agreed escalation: accelerate transfer, draw on buffer, and invoke tooling access rights.