CWS Welding study materials
CWS Welding study resources

Choosing a Process for 4,000 Feet of Fillet Weld

CWS Welding · Put your knowledge to work in context.

All case studies

Choosing a Process for 4,000 Feet of Fillet Weld

You must produce 4,000 linear feet of 1/4-in. fillet weld on A36. Theoretical deposited weight is 0.106 lb/ft; adding 10% for reinforcement and oversize, plan on 460 lb of deposited metal. Labor is $60/hr fully burdened, and either machine is already owned and idle, so there is no capital difference.

GMAW (0.035-in. solid): 3.5 lb/hr deposition, 40% operating factor, $1.60/lb filler at 98% efficiency, 25 cfh gas at $0.05/cf.

FCAW-G (0.045-in. E71T-1): 7.0 lb/hr deposition, 45% operating factor, $2.40/lb filler at 86% efficiency, 35 cfh gas at $0.05/cf.

1. Compute the cost per foot for each option and identify where the money actually goes.

Read the worked answer

GMAW

  • Arc hours: 460 / 3.5 = 131.4 h
  • Paid hours: 131.4 / 0.40 = 328.6 h → labor $19,714
  • Filler: (460 / 0.98) × $1.60 = $751
  • Gas: 25 cfh × 131.4 h = 3,285 cf × $0.05 = $164
  • Total ≈ $20,629 → $5.16/ft; labor is 95.6% of it

FCAW-G

  • Arc hours: 460 / 7.0 = 65.7 h
  • Paid hours: 65.7 / 0.45 = 146.0 h → labor $8,760
  • Filler: (460 / 0.86) × $2.40 = $1,284
  • Gas: 35 cfh × 65.7 h = 2,300 cf × $0.05 = $115
  • Total ≈ $10,159 → $2.54/ft; labor is 86%

Difference: about $10,470, or 51%. The filler price gap ($586 more for FCAW) is noise against a $10,954 labor gap.

2. Filler prices are volatile and your engineer calls the 45% operating factor optimistic. How far can the FCAW case deteriorate before the choice flips?

Read the worked answer

Test both variables.

Filler price: at $3.60/lb instead of $2.40, FCAW filler rises to $1,926 and total to $10,801 - still about $9,800 ahead. Filler is the wrong thing to worry about.

Operating factor: set FCAW's labor plus filler plus gas equal to GMAW's total. 60 × (65.7 / f) + 1,284 + 115 = 20,629 → 3,942 / f = 19,230 → f = 0.205

FCAW would have to fall to a 20.5% operating factor - less than half the assumed value - before GMAW wins. The margin is large, but the operating factor is the number most likely to be wrong, because flux-cored welding adds deslag and cleaning time. On short, tack-heavy, repositioning-heavy work, re-measure it with a stopwatch before you commit.

3. What factors outside the arithmetic could still change the decision?

Read the worked answer

Schedule and headcount. 146 paid hours is roughly 3.7 weeks for one welder; 329 hours is more than eight weeks on one man, so GMAW would need two arcs and two machines - that, not filler, is the real fixed cost.

Quality risk. Add expected rework to whichever process the shop has historically struggled with. At 5% of 146 hours, FCAW rework is about 7 hours (~$440) - immaterial, but it is only immaterial because the labor base is small.

Data credibility. The deposition rates came from a vendor sheet measured at 100% arc time. Verify them on your own floor with a stopwatch and a scale, using your wire and your positioner, before you quote $2.54/ft to a customer.