DC Land Surveyor Exam: Land Development and Construction Surveying

DC Land Surveyor Exam · Work through your exam, one topic at a time.

All guide sections

Land Development and Construction Surveying

Construction surveying questions test whether you can transfer design intent to the ground and verify it afterward. Expect cut and fill, slope stakes, control, as-builts, and DC regulatory overlays such as stormwater, erosion control, and right-of-way permits.

Control and stakeout

  • Establish horizontal and vertical control tied to record monuments and a known benchmark; protect control from construction traffic.
  • Set offsets and hubs, then check the stakeout independently. Machine control and GPS-guided grading still require verification against control.
  • As-built surveys compare constructed conditions with the approved plan and document deviations.

Grades, cut and fill, and volumes

  • Cut = existing elevation - design elevation; a negative result is fill. State the sign convention on the stake.
  • Slope stakes are set where the design slope intersects existing ground. For a 2:1 slope and 4.50 ft of cut, the catch point is 9.0 ft horizontally from the hinge.
  • Volumes use average end area or prismoidal methods; strip topsoil before computing earthwork.

DC context

  • Stormwater management and erosion and sediment control are reviewed by DOEE; right-of-way occupancy and lane closures require DDOT permits.
  • ADA accessibility, the Green Area Ratio, and the DC Building Code affect grades, walks, and site layout.
  • Survey monuments are protected by law; do not remove or disturb them without authorization.

Worked example

At station 10+00, 25 ft right of centerline, design elevation is 100.00 ft and existing ground is 104.50 ft. Cut = 100.00 - 104.50 = -4.50 ft, so it is a 4.50-ft cut. With a 2:1 slope, the catch point lies 2 × 4.50 = 9.0 ft farther out, at 34.0 ft right of centerline, at existing grade. The stake notes cut and offset so the grader can work from the hinge.

Traps that cost marks

  • Reversing the cut/fill sign.
  • Setting slope stakes without iterating on sloping or curved ground.
  • Ignoring topsoil stripping or compaction factors in volumes.
  • Staking from unchecked control or a benchmark of unknown datum.
  • Overlooking DOEE or DDOT permit requirements before construction.