DE Asbestos Abatement key terms
DE Asbestos Abatement · Get comfortable with the vocabulary.
- friable asbestos
- Related: non-friable asbestos, RACM
Asbestos material that can be crumbled, pulverized, or reduced to powder by hand pressure when dry. Friability drives how easily fibers become airborne and therefore how strictly the material must be handled.
- non-friable asbestos
- Related: friable asbestos, Category I non-friable ACM
Asbestos-containing material that resists being crumbled or powdered by hand pressure. Examples include asbestos cement siding, floor tile, and roofing felt, which release fibers mainly when cut, sanded, or broken.
- RACM
- Related: friable asbestos, Category I non-friable ACM, NESHAP
Regulated Asbestos-Containing Material. Under NESHAP, this covers friable ACM, Category I and II non-friable ACM that has become friable or will be sanded/ground/cut, and non-friable ACM with a high asbestos content that is damaged.
- Category I non-friable ACM
- Related: Category II non-friable ACM, RACM
Non-friable asbestos-containing material that contains more than 1 percent asbestos and includes packings, gaskets, resilient floor coverings, and asphalt roofing products. It becomes regulated when sanded, ground, cut, or damaged.
- Category II non-friable ACM
- Related: Category I non-friable ACM, RACM
Non-friable asbestos-containing material other than Category I, such as asbestos cement sheet, pipe, and shingle. It is regulated when it becomes friable or is expected to be crumbled or pulverized during demolition or renovation.
- asbestos-containing material (ACM)
- Related: PLM, bulk sampling, presumed ACM
Any material or product that contains more than 1 percent asbestos by weight, as determined by an accredited inspector using polarized light microscopy or an equivalent method. The 1 percent threshold is the regulatory trigger for most requirements.
- presumed ACM
- Related: suspect material, ACM, thorough inspection
Material that has not been sampled or analyzed but must be treated as asbestos-containing until proven otherwise. Renovation and demolition rules require presuming suspect materials are ACM if they are not inspected.
- suspect material
- Related: presumed ACM, thorough inspection, bulk sampling
A building material that, because of its type, use, or age, may contain asbestos. Inspectors must identify and sample all suspect materials before renovation or demolition disturbs them.
- thorough inspection
- Related: suspect material, accredited inspector, bulk sampling
A complete walk-through of a facility by an accredited inspector to locate and assess all suspect asbestos-containing materials, including concealed spaces, before renovation or demolition work begins.
- bulk sampling
- Related: PLM, ACM, accredited inspector
Collecting physical samples of suspect material for laboratory analysis to determine whether asbestos is present and in what percentage. Sampling must follow accepted procedures to avoid cross-contamination and represent the material accurately.
- PLM
- Related: bulk sampling, ACM, point counting
Polarized Light Microscopy. The standard laboratory method for identifying asbestos fibers in bulk samples by their optical properties. It reports fiber type and percentage, with gravimetric or point-counting methods used for low concentrations.
- point counting
- Related: PLM, ACM
A more precise PLM analysis in which the microscopist counts fibers at hundreds of grid points to estimate asbestos percentage. It is used when the initial estimate is near the 1 percent regulatory threshold.
- accredited inspector
- Related: thorough inspection, bulk sampling, asbestos abatement worker
A person who has completed an approved asbestos inspection course and passed the required exam, qualified to identify and assess ACM and collect bulk samples. Accreditation must be maintained through refresher training.
- asbestosis
- Related: mesothelioma, latency period, asbestos exposure
A progressive, irreversible lung disease caused by inhaling asbestos fibers. Scar tissue builds up in the lungs, reducing elasticity and gas exchange, and symptoms such as shortness of breath typically appear years after exposure.
- mesothelioma
- Related: asbestosis, latency period, lung cancer
A rare cancer of the thin membranes lining the chest, abdomen, or heart, strongly associated with asbestos exposure. It has a long latency, often decades, and can occur after relatively low cumulative exposures.
- lung cancer
- Related: asbestosis, mesothelioma, asbestos exposure
A malignant tumor of the lung associated with asbestos inhalation, with risk rising sharply in people who also smoke. It is one of the major causes of death attributed to occupational asbestos exposure.
- latency period
- Related: asbestosis, mesothelioma, asbestos exposure
The time between first asbestos exposure and the appearance of disease, commonly 10 to 40 years or more. Because of this delay, current illness often reflects exposures that occurred decades earlier.
- asbestos exposure
- Related: respiratory protection, latency period, asbestos fibers
Inhalation or ingestion of airborne asbestos fibers. Risk increases with the concentration of fibers in air, the duration and frequency of exposure, and the time since exposure began.
- asbestos fibers
- Related: asbestos exposure, friable asbestos
Microscopic, needle-like mineral strands that can remain suspended in air for long periods and penetrate deep into the lungs. Their size and durability make them difficult for the body to clear.
- respiratory protection
- Related: asbestos exposure, containment, negative air pressure
Personal protective equipment, such as a fitted half-face or full-face respirator with appropriate filters, worn to reduce inhalation of airborne fibers. It requires fit testing, medical clearance, and training to be effective.
- containment
- Related: negative air pressure, critical barrier, decontamination unit
A sealed enclosure, often of plastic sheeting and tape, built around the work area to prevent asbestos fibers from escaping. It includes critical barriers at openings and is maintained under negative pressure during abatement.
- negative air pressure
- Related: containment, HEPA filter, decontamination unit
A condition in which air pressure inside the containment is lower than outside, so air flows inward and fibers are kept from escaping. It is maintained with HEPA-filtered negative air machines and monitored with gauges.
- HEPA filter
- Related: negative air pressure, containment
High-Efficiency Particulate Air filter rated to capture at least 99.97 percent of particles 0.3 microns in diameter. It is required on vacuums and negative air machines used in abatement to trap asbestos fibers.
- critical barrier
- Related: containment, negative air pressure
A temporary seal, usually plastic sheeting and tape, placed over doors, windows, vents, and other openings to isolate the work area and prevent fiber migration. It is installed before abatement begins and removed last.
- decontamination unit
- Related: containment, negative air pressure, personal protective equipment
A three-stage enclosure with a clean room, shower, and dirty room that workers pass through when entering and leaving the containment. It prevents fibers from being carried out on clothing or skin.
- personal protective equipment (PPE)
- Related: respiratory protection, decontamination unit
Disposable coveralls, gloves, foot coverings, and respirators worn during abatement to protect the worker from fiber contact. PPE must be removed and disposed of properly before leaving the work area.
- asbestos abatement worker
- Related: abatement contractor, asbestos abatement supervisor, accredited inspector
A trained and accredited individual who removes, encapsulates, or encloses asbestos-containing material under supervision. Accreditation requires approved training and periodic refresher courses.
- asbestos abatement supervisor
- Related: asbestos abatement worker, abatement contractor
The person who directs abatement work and ensures compliance with work practices, safety requirements, and regulations on site. Supervisors must complete an approved course and maintain accreditation.
- abatement contractor
- Related: asbestos abatement worker, asbestos abatement supervisor
A business licensed or certified to perform asbestos removal and related work. It must meet state or local licensing requirements, carry insurance, and employ accredited workers and supervisors.
- NESHAP
- Related: RACM, demolition notification, waste shipment record
National Emission Standards for Hazardous Air Pollutants. The federal rules under the Clean Air Act that govern asbestos handling during demolition, renovation, and waste disposal, including notification and emission controls.
- demolition notification
- Related: renovation notification, NESHAP, RACM
A written notice submitted to the appropriate air quality agency before starting demolition or renovation that will disturb threshold amounts of asbestos. It identifies the site, owner, contractor, and amount of RACM.
- renovation notification
- Related: demolition notification, NESHAP
A required filing to the air quality agency before renovation work that will disturb regulated asbestos-containing material above the regulatory threshold. It must be submitted within the required time before work begins.
- waste shipment record
- Related: asbestos waste packaging, disposal site, NESHAP
A tracking document that accompanies asbestos waste from the generator through transport to the disposal site. It documents quantities, dates, and handlers and must be retained and reconciled after disposal.
- asbestos waste packaging
- Related: waste shipment record, disposal site, containment
Placing removed asbestos debris in sealed, leak-tight, labeled containers, usually heavy-duty bags or drums, before transport. Containers must be wetted and sealed to prevent fiber release during handling.
- disposal site
- Related: waste shipment record, asbestos waste packaging
A landfill or facility permitted to accept asbestos-containing waste material. Waste must be delivered to an approved site that follows required covering and handling practices.
- air monitoring
- Related: clearance, containment, asbestos fibers
Collecting and analyzing air samples to measure airborne fiber concentrations during and after abatement. It verifies that containment is working and that clearance levels are met before reoccupancy.
- clearance
- Related: air monitoring, containment
The final verification step after abatement in which air samples confirm fiber levels are below the required limit and the work area is visually clean. Reoccupancy is allowed only after clearance is achieved.
- encapsulation
- Related: enclosure, friable asbestos
Treating asbestos material with a sealant that penetrates or coats it to bind fibers and reduce release. It is an alternative to removal but does not eliminate the asbestos hazard.
- enclosure
- Related: encapsulation, containment
Building a permanent airtight barrier around asbestos-containing material so it is not disturbed. Unlike encapsulation, it does not alter the material itself but isolates it from the occupied space.
- asbestos-related work permit
- Related: demolition notification, abatement contractor, NESHAP
A permit issued by a state or local agency authorizing a specific asbestos abatement or renovation project. It typically requires submission of notification, project plans, and contractor credentials before work starts.