Drainage fixture unit (DFU)

A number that rates how much wastewater a fixture produces compared with a standard fixture, used to size drain pipes and vents so the system carries the expected load.

Related: Fixture branch, Vent stack, Building drain
Water supply fixture unit (WSFU)

A number that estimates the likely peak demand a fixture places on the water supply system, accounting for how often it is used, used to size supply piping.

Related: Fixture branch, Pressure-reducing valve
Trap seal

The measured depth of water held in a plumbing trap that blocks sewer gas from entering a building; it is lost through evaporation or siphonage if the trap is improperly vented.

Related: P-trap, Vent stack, Air admittance valve
P-trap

A U-shaped fitting beneath or near a fixture that holds water to seal out sewer gas while allowing wastewater to pass through to the drain.

Related: Trap seal, Fixture branch
Vent stack

A vertical pipe that lets air into the drainage system and releases sewer gas above the roof, protecting trap seals from siphonage and allowing drains to flow smoothly.

Related: Trap seal, Air admittance valve, Drainage fixture unit (DFU)
Air admittance valve (AAV)

A one-way valve installed on a vent line that admits air when a fixture drains and closes to keep sewer gas inside, often used where a full vent stack is impractical.

Related: Vent stack, Trap seal
Fixture branch

The pipe that connects one or more fixtures to a soil or waste stack, sized by the fixture units it serves and required to be vented.

Related: Drainage fixture unit (DFU), Soil stack
Soil stack

The main vertical pipe that carries wastewater and sewage from fixtures down to the building drain, extending upward to connect with the vent system.

Related: Fixture branch, Building drain, Vent stack
Building drain

The lowest horizontal piping of a drainage system that receives waste from stacks and branches and carries it to the building sewer.

Related: Building sewer, Soil stack
Building sewer

The pipe that carries sewage from the building drain to the public sewer or private disposal system, starting outside the building foundation.

Related: Building drain, Backwater valve
Backwater valve

A one-way valve installed on a drainage line that closes automatically to stop sewage from flowing backward into a building during a sewer backup.

Related: Building sewer, Cleanout
Cleanout

An accessible fitting with a removable cap that lets a plumber rod or snake a drain line to clear blockages.

Related: Building drain, Backwater valve
Water hammer

A banging or knocking noise and pressure surge caused when flowing water is stopped suddenly, often controlled with air chambers or arrestors.

Related: Water hammer arrestor, Pressure-reducing valve
Water hammer arrestor

A device containing a trapped air cushion that absorbs the pressure surge when a valve closes quickly, preventing banging and pipe damage.

Related: Water hammer
Pressure-reducing valve (PRV)

A device that lowers incoming water pressure to a safe level for the building's piping and fixtures, protecting them from excessive stress.

Related: Thermal expansion, Water hammer
Thermal expansion

The increase in water volume as it is heated in a closed system, which raises pressure and must be relieved by an expansion tank or relief valve.

Related: Temperature and pressure relief valve, Pressure-reducing valve
Temperature and pressure relief valve (T&P valve)

A safety valve on a water heater that opens to release water if temperature or pressure inside the tank becomes dangerously high.

Related: Thermal expansion, Backflow prevention device
Backflow prevention device

A valve or assembly that stops contaminated water from flowing backward into the potable water supply, protecting drinking water from pollution.

Related: Cross-connection, Air gap
Cross-connection

Any actual or potential link between the potable water supply and a source of contamination that could allow pollutants to enter drinking water.

Related: Backflow prevention device, Air gap
Air gap

The unobstructed vertical distance between a water supply outlet and the flood-level rim of a fixture, providing the strongest form of backflow protection.

Related: Cross-connection, Backflow prevention device
Flood-level rim

The edge of a fixture over which water would overflow onto the floor, used as the reference point for setting air gaps and fixture outlet heights.

Related: Air gap
Wet vent

A vent pipe that also serves as a drain for fixtures on a floor above, allowed only under specific code conditions and sizing limits.

Related: Vent stack, Fixture branch
Developed length

The total length of pipe measured along its centerline including all fittings and bends, used to determine drain slope and vent sizing.

Related: Slope (fall), Building drain
Slope (fall)

The downward pitch of a horizontal drain pipe, usually expressed in inches per foot, that lets wastewater flow by gravity without clogging.

Related: Developed length, Building drain
Water closet

The plumbing code term for a toilet; a fixture that receives human waste and discharges it through a trap into the drainage system.

Related: Trap seal, Drainage fixture unit (DFU)
Potable water

Water that is safe for drinking, cooking, and personal use because it meets health standards for contamination and quality.

Related: Cross-connection, Backflow prevention device
Permit

Official authorization from the local authority to perform plumbing work, required before installation so the work can be inspected and approved.

Related: Inspection, Certificate of occupancy
Rough-in

The stage of construction when pipes, drains, and vents are installed inside walls and floors before fixtures and finished surfaces are put in place.

Related: Inspection, Permit
Inspection

A required visit by a code official to examine plumbing work at set stages, such as rough-in and final, to confirm it meets code before it is covered or used.

Related: Rough-in, Permit
Certificate of occupancy

A document issued by the local authority confirming a building or space may legally be occupied, typically issued after final plumbing inspections pass.

Related: Inspection, Permit
Lockout/tagout

A safety procedure that isolates energy sources and applies locks and tags so equipment cannot be started while a worker is servicing it.

Related: Personal protective equipment (PPE), Confined space
Personal protective equipment (PPE)

Gear such as gloves, safety glasses, respirators, and boots worn to protect a worker from hazards on the job site.

Related: Lockout/tagout, Confined space
Confined space

An area with limited entry and exit that is not designed for continuous occupancy and may contain hazardous gases or low oxygen, requiring special safety procedures.

Related: Lockout/tagout, Personal protective equipment (PPE)
Material Safety Data Sheet (SDS)

A document that describes the hazards, safe handling, and emergency measures for a chemical product used on the job.

Related: Personal protective equipment (PPE)
Change order

A written agreement that modifies the scope, price, or schedule of a construction contract after work has begun.

Related: Bid, Punch list
Punch list

A list of incomplete or defective items identified near the end of a project that the contractor must correct before final payment and acceptance.

Related: Change order, Certificate of occupancy
Bid

A contractor's formal offer to perform specified work at a stated price, based on plans, specifications, and estimated labor and material costs.

Related: Change order, Retainage
Retainage

A percentage of each payment withheld by the owner until the project is substantially complete, protecting the owner against unfinished or defective work.

Related: Bid, Punch list
Lien

A legal claim against a property for unpaid work or materials, which a contractor or supplier can file to secure payment.