La Rioja PAU Tech & Engineering II (UR) flashcards
La Rioja PAU Tech & Engineering II (UR) · Build recall with a focused review session.
32 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Young's modulus
- Slope of the linear elastic part of the stress-strain curve, E = σ/ε. It measures stiffness: a higher E means less deformation for the same applied stress.
- Section modulus W
- Geometric property W = I/c, where I is the second moment of area and c the distance from the neutral axis to the extreme fibre. Maximum bending stress is σ = M/W.
- Euler buckling load
- Critical axial load of a slender column: P_cr = π²·E·I/L_e², with L_e the effective length set by end conditions. Valid only when slenderness exceeds the limit value.
- Thévenin equivalent circuit
- Any linear two-terminal network can be replaced by a voltage source V_th in series with R_th. V_th is the open-circuit voltage and R_th the resistance seen with all sources killed.
- Power factor correction
- Adding a parallel capacitor bank to raise cos φ from cos φ₁ to cos φ₂, with Q_C = P·(tan φ₁ − tan φ₂). It cuts line current and losses while active power stays the same.
- Betz limit
- Maximum theoretical power coefficient of a wind rotor, C_p = 16/27 ≈ 0.593. No turbine can extract more than 59.3 % of the kinetic energy of the wind stream.
- Carnot efficiency
- Upper limit on the efficiency of any heat engine between two reservoirs: η = 1 − T_c/T_h, using absolute temperatures. Real cycles always fall below this value.
- PID controller
- Control law u = K_p·e + K_i·∫e dt + K_d·de/dt. Proportional action speeds response, integral action removes steady-state error, derivative action damps and reduces overshoot.
- PLC scan cycle
- Repeating sequence of reading inputs, executing the user program and updating outputs. Scan time is the total duration; a watchdog timer faults the CPU if it is exceeded.
- First-angle projection
- ISO projection system where each view is placed on the side opposite the observer: top view below the front view and left-side view to its right. Standard in Europe.
- Hole basis fit
- Fits system where the hole tolerance is fixed at H and the shaft letter sets the type: a–h clearance, j–n transition, p–zc interference. Preferred in ISO design practice.
- Critical path method
- Scheduling technique where the longest chain of dependent tasks defines the minimum project duration; any delay on the critical path delays the whole project.
- Hall-Petch relation
- Yield stress increases as grain size decreases: σ_y = σ₀ + k·d^(−1/2). Finer grains mean more grain boundary area obstructing dislocation motion.
- Resilience and toughness
- Resilience is the elastic energy per volume, σ_y²/(2E). Toughness is the total area under the stress-strain curve to fracture, high when strength and ductility are both high.
- Grashof condition
- For a four-bar linkage, if s + l ≤ p + q (shortest plus longest link versus the other two), at least one link can rotate fully; otherwise it is a double-rocker.
- Grübler mobility formula
- Degrees of freedom of a planar mechanism: M = 3·(n − 1) − 2·j₁ − j₂, with n links, j₁ lower pairs and j₂ higher pairs. M = 1 means a single input drives it.
- Star versus delta connection
- In star, line voltage is √3 times phase voltage and line current equals phase current. In delta, line current is √3 times phase current. Balanced power is √3·V_L·I_L·cos φ.
- Buck and boost converters
- Switched DC-DC converters. Buck steps voltage down, V_o = D·V_i. Boost steps it up, V_o = V_i/(1 − D), where D is the duty cycle between 0 and 1.
- Rankine cycle
- Standard steam power cycle with pump, boiler, turbine and condenser. Efficiency rises with higher steam pressure and temperature and with lower condenser pressure.
- Energy payback time
- Time a generating installation needs to produce the energy consumed in its manufacture and installation. Shorter payback means a better sustainability profile for the technology.
- Routh-Hurwitz criterion
- Algebraic stability test: build the Routh array from the closed-loop characteristic polynomial. The number of sign changes in the first column equals the number of right-half-plane poles.
- Stepper motor step angle
- Angular advance per full step, typically 1.8° giving 200 steps per revolution. Position is set by counting pulses, so no feedback sensor is needed for basic positioning.
- ISO 129 dimensioning rules
- Dimensions state true size regardless of drawing scale, the unit is declared once in the title block, dimension lines are not crossed, and each feature is dimensioned only once.
- Ra surface roughness
- Arithmetic mean roughness expressed in micrometres. Lower Ra means a smoother, more expensive surface, so it is specified only where the function requires it.
- Bill of materials
- Itemized list of every component in a product or project, giving reference, description, material, quantity and often unit price. It links design, purchasing and budgeting.
- FMEA risk priority number
- Failure mode and effects analysis scores severity, occurrence and detection from 1 to 10; their product is the RPN, used to rank failure modes for corrective action.
- Ashby performance index
- Combination of material properties to maximize for a given design objective, e.g. E/ρ for a light stiff tie-rod or E^(1/2)/ρ for a light stiff bending beam.
- Maximum power transfer theorem
- A load receives maximum power when R_L equals the source's Thévenin resistance R_th, giving P_max = V_th²/(4·R_th). Efficiency at that point is only 50 %.
- Carnot and real plant efficiency
- Carnot sets the theoretical ceiling between two temperatures. Real fossil steam plants reach roughly 35–45 % because of irreversibilities and large condenser heat rejection.
- PID integral action
- The K_i term accumulates past error and drives steady-state error to zero, but it adds overshoot and phase lag, so excessive integral gain can destabilize the loop.
- Parametric CAD modelling
- Geometry is defined by dimensions and constraints stored as parameters. Changing a parameter regenerates the model and all derived drawings automatically.
- Project budget structure
- Material and labour give direct cost; add indirect costs as a percentage, then industrial profit, then VAT. The result is the total contract price of the project.