IPAF MEWP Operator study materials
IPAF MEWP Operator study resources

IPAF MEWP Operator cheat sheet

IPAF MEWP Operator · Keep the key ideas within reach.

Quick reference

Boom-type MEWPs (1B)

  • Category 1B covers boom-supported MEWPs where the platform extends beyond the chassis/wheelbase; the machine must not be driven with the boom elevated except where the manufacturer permits and the route is assessed.

  • Boom types: articulated (knuckle) booms reach over obstacles; telescopic (straight) booms give greater horizontal reach; trailer-mounted booms are towable but not self-propelled.

  • Rated capacity is platform load only and excludes the operator's tools unless stated; the load chart applies at the working radius shown on the platform placard, not at the boom angle.

  • Structural stability depends on outriggers or axle-lock/wheel-base widening; outrigger pads must bear on ground verified for load, and floats must be fully deployed before elevation.

  • Wind: observe the manufacturer's maximum rated wind speed; platform sail area rises with boom length and attachment of panels/signage, so added attachments require re-checking the rating.

  • Emergency lowering: know the manual descent procedure (auxiliary pump, cable release, or gravity valve) and confirm it is functional at the pre-use inspection.

  • Harness anchorage: a full-body harness with adjustable lanyard is attached to the designated anchor point inside the platform; the lanyard is kept short to prevent ejection over the guardrail.

  • Boom MEWPs are not designed to be used as cranes; never attach loads, ropes, or tag lines to the platform or boom except as permitted by the manufacturer.

Quick reference

Scissor-type MEWPs (3A)

  • Category 3A covers scissor lifts that can be driven with the platform elevated; travel is permitted only on firm, level ground within the manufacturer's rated slope and floor-loading limits.

  • Scissor platforms are rated for a distributed load across the deck; point loads on a single guardrail or deck plate can exceed local limits even when total load is within capacity.

  • Stability is governed by the base width and extension deck position: extension decks retract before travel, and outrigger-equipped models require all outriggers set and level before elevation.

  • Guardrails and gates are part of the fall-protection system; the entry gate must self-close and latch, and the platform must not be entered by climbing the scissor structure.

  • Pothole protection devices deploy automatically on elevation; if the device is damaged or blocked, the machine must be taken out of service until repaired.

  • Floor loading: point load per wheel or outrigger pad must be checked against the slab rating; spreader plates distribute load where the slab capacity is marginal.

  • Scissor lifts are not anchorage-rated for fall arrest in most designs; a harness, where required by site rules, is used with a short restraint lanyard to an approved anchor, not for arrest.

  • Tilt and overload interlocks prevent elevation or drive beyond limits; bypassing them or operating with a fault displayed is prohibited.

Quick reference

MEWP categories 3B and general classification

  • Category 3B covers scissor-type MEWPs restricted to travel with the platform in the lowered position; the machine must be driven only stowed, then elevated on station.

  • Classification logic: group 1 = cannot travel when elevated; group 3 = can travel when elevated; type A = push-around/vertical lift with no rotating structure; type B = boom or rotating structure extending beyond the chassis.

  • Category 1A = push-around vertical lifts; 1B = boom MEWPs that cannot travel elevated; 3A = scissor lifts that can travel elevated; 3B = scissor lifts that cannot travel elevated.

  • A MEWP is a mobile machine intended to move persons to working positions; it is not a crane, and lifting of persons by non-MEWP plant (forklifts, excavators) requires a specific risk assessment and is generally prohibited.

  • Selection rule: match the category to the task - reach over an obstacle needs a boom (B); large stable deck area on a flat slab favours a scissor (A); restricted travel with platform up requires group 3.

  • Ground conditions drive category choice: wheel loads, outrigger pressures, and slope limits differ between 3A and 3B machines even at similar platform heights.

  • Familiarisation: the employer must ensure the operator is familiar with the specific model before use, covering controls, load chart, emergency lowering, and restraints.

  • Daily pre-use inspection covers tyres, outriggers, guardrails, gates, decals, battery/fuel, hydraulic leaks, emergency stops, and the function of tilt and overload interlocks.

Quick reference

Mast climbing work platforms (MCWP)

  • An MCWP is a temporarily installed machine with a working platform that climbs a mast; it is not a MEWP and is covered by its own standard (EN 1495) rather than EN 280.

  • MCWP rated load is typically expressed as a uniformly distributed load over the platform length; concentrated loads and eccentric loading are limited by the manufacturer's data.

  • Mast ties to the structure are engineered at specified vertical intervals; the tie spacing and anchor design come from the manufacturer or a competent engineer, never improvised.

  • The base must be founded on a designed foundation or spreader arrangement; the mast is plumbed within the manufacturer's tolerance before climbing.

  • Climbing operation is controlled from the platform or a designated station; personnel must not be on the platform during climbing unless the manufacturer's procedure explicitly permits it.

  • Tie anchors into concrete must be checked for pull-out capacity; anchor testing or specified embedment is required where the structure's capacity is unverified.

  • Platform gates and end guards must be closed and the platform levelled before work; the platform is not used as a crane and must not be loaded beyond the rated UDL.

  • Erection, alteration, and dismantling are carried out by trained, competent persons under a documented method statement, with the completed installation handed over and recorded.

Quick reference

Construction hoists (CH)

  • A construction hoist (builder's hoist) is a temporary rack-and-pinion or rope-suspended lift for persons and/or materials on a construction site; it is covered by EN 12159 (persons/materials) and EN 12158 (materials only).

  • Personnel hoists require a car with gates, landing doors at every landing, and interlocks that prevent movement unless all gates and doors are closed and locked.

  • The rated load and number of persons are stated on a plate in the car; load must be evenly distributed and the passenger limit is absolute regardless of weight.

  • Landing doors must be self-closing and interlocked; the landing edge must have edge protection, and the gate must not be defeated to speed loading.

  • Mast ties to the building are designed at specified intervals; free-standing height above the top tie is limited by the manufacturer's data and must never be exceeded.

  • The hoistway or landing area beneath the hoist must be barriered against access; the area under the car is a no-go zone while the hoist is in motion.

  • Operators must hold the appropriate competence and be authorised; the car is not driven with the door open, and the emergency stop and alarm must be tested at each shift.

  • Overload detection, overspeed/braking tests, and the final inspection before first use are documented; periodic thorough examination by a competent person is required at statutory intervals.

Quick reference

Common operational controls and rescue

  • Pre-use checks: controls, emergency stop, horn/alarm, tilt and overload interlocks, guardrails, gates, anchors, tyres, outriggers, fluid levels, and decals must all be verified before the first lift.

  • Rescue plan: a means of lowering an incapacitated operator from the platform must be prepared before work starts; calling emergency services alone is not a rescue plan.

  • Emergency lowering methods differ by machine: auxiliary hydraulic pump, manual descent valve, or brake release - the operator must be trained on the specific model's method.

  • Exclusion zones: the area beneath and around the platform is barriered for the full working radius, including the sweep of a rotating boom.

  • Overhead hazards: check for power lines and observe the relevant approach distance; contact with an energised line requires the operator to stay in the platform until isolated.

  • Slope and ground: operate only within the rated slope; use spreader plates where point loads exceed slab capacity, and never operate near unshored excavations or openings.

  • Weather: stop when wind exceeds the rated maximum, when lightning is near, or when ice/snow compromises the deck and controls.

  • Handover and familiarisation: the operator is familiarised with the specific model, and the machine is not used if it has been modified or has a safety device out of service.

Quick reference

Platform loading, stability and fall protection

  • Load calculation: rated capacity minus operator mass minus tools, materials, and any attachments equals available payload; never exceed the plate figure in total.

  • Platform load is rated for a uniformly distributed load; concentrated loads on guardrails or deck edges can locally exceed the deck's design and must be spread.

  • Fall protection: where the manufacturer or site requires it, a full-body harness with a short restraint lanyard is anchored to the designated point; the lanyard prevents ejection over the guardrail.

  • Guardrails, mid-rails, toe boards, and gates are the primary fall-protection system; the platform must not be used with any of these missing or damaged.

  • Never climb on the guardrail, use ladders or boxes inside the platform, or stand on the mid-rail to gain height; use the correct machine for the reach required.

  • The platform must not be used as a crane; tag lines and ropes are attached only where the manufacturer permits and must not create a snagging or pull-off hazard.

  • Stability is reduced by wind, side loads, and uneven ground; check the rated wind speed and keep the platform clear of structures that could trap it.

  • Exiting at height: only where the manufacturer permits and a specific risk assessment, anchorage, and edge protection are in place for the transition.

Quick reference

Power sources, inspection and documentation

  • Battery machines: check state of charge, charging area ventilation, and that charging is done with the machine off and in a designated area; do not charge near ignition sources.

  • Diesel/LPG machines: check fuel level, no leaks, and that exhaust is not routed into an enclosed space; carbon monoxide can accumulate in enclosed or partially enclosed areas.

  • Pre-use inspection is recorded daily; the machine is tagged out of service if any safety device, guard, or structural item fails.

  • Thorough examination: MEWPs are subject to periodic thorough examination by a competent person at intervals not exceeding those set by the applicable regulations and the manufacturer.

  • Documentation to hold: operator training/familiarisation record, machine logbook, thorough examination report, and the manufacturer's manual on the machine.

  • Modifications: attachments, extra signage, or repairs that affect stability, capacity, or controls require manufacturer approval and re-rating before use.

  • Defects found during inspection must be reported and the machine isolated; operating a machine with a known defect is a breach regardless of task urgency.

  • Record keeping: keep inspection and examination records available at the point of use so the operator can confirm the machine's status before starting work.

Quick reference

Site-specific hazards and safe positioning

  • Position the machine so the platform is over the work area, not over unprotected edges, openings, or traffic routes; the base must be on ground verified for load.

  • Overhead power lines: observe the required approach distance for the line voltage; if contact occurs, stay in the platform and warn others away until the line is isolated.

  • Floor loading: check slab capacity against wheel and outrigger point loads; use spreader plates and, where required, an engineer's check before positioning.

  • Excavations and openings: keep the machine back from unshored edges by at least the distance required by the ground conditions; the base must not be undermined.

  • Traffic and pedestrians: barrier the working radius and use a signaller or traffic management where the machine moves near vehicles or pedestrians.

  • Wind: the platform acts as a sail; stop when the rated wind speed is reached, and account for wind funnelling between buildings and for sudden gusts.

  • Confined or enclosed spaces: check ventilation and exhaust routing for combustion-powered machines; battery machines are preferred indoors.

  • Emergency services access must be maintained; the machine must not block fire routes, hydrants, or escape routes while positioned.

Quick reference

Operator competence and responsibilities

  • The operator must be trained to the correct category, familiarised with the specific model, and authorised by the employer before operating.

  • The operator is responsible for the pre-use inspection, for not exceeding rated capacity, and for stopping work if conditions become unsafe.

  • The operator must follow the manufacturer's manual and the site's method statement; where they conflict on a safety point, the more restrictive applies.

  • Fitness: alcohol, drugs, and medication that impair alertness are incompatible with operating; fatigue and medical conditions must be declared.

  • The operator must not allow unauthorised persons to operate the machine and must secure it against use when left unattended.

  • Reporting: defects, near misses, and incidents are reported immediately; the machine is isolated until assessed.

  • Teamwork: the operator follows the signaller's directions where one is appointed and maintains communication with ground personnel.

  • Continuous improvement: lessons from incidents and near misses are fed back into the method statement and pre-use checks.

Quick reference

MEWP categories: 1B, 3A and 3B in practice

  • 1B = boom MEWP that cannot travel with the platform elevated; reposition stowed, then elevate. Driving elevated is prohibited unless the manufacturer's rating and route assessment allow it.

  • 3A = scissor MEWP that can travel with the platform elevated; travel is limited to firm, level ground within rated slope and floor-loading limits.

  • 3B = scissor MEWP that cannot travel elevated; drive stowed, then elevate on station.

  • Push-around vertical lifts (1A) are moved manually and elevated only when stationary on firm ground.

  • Selection: reach over an obstacle → boom (B); large stable deck on a flat slab → scissor (A); restricted travel with platform up → group 3.

  • The category marking is on the machine's data plate; never assume a machine can travel elevated without confirming the plate and manual.

  • When in doubt, treat the machine as group 1 (no travel elevated) and reposition stowed.

Quick reference

MCWP and construction hoist interfaces on site

  • MCWP and CH are both temporarily installed and require a documented erection/dismantling method statement by competent persons.

  • Both require designed ties or anchors to the structure at specified intervals, with the free-standing height limited by the manufacturer.

  • Landing and platform gates must be interlocked: the CH car cannot move unless doors are closed, and the MCWP platform must be level and gated before work.

  • Access to the MCWP platform and to CH landings must be protected with edge protection and self-closing gates.

  • The area beneath both must be barriered as a no-go zone during operation.

  • Both require a handover and recorded final inspection before first use, and periodic thorough examination thereafter.

  • Personnel must never ride on a materials-only hoist (EN 12158) or on an MCWP platform during climbing unless the procedure permits.

Quick reference

Rescue, emergency and incident response

  • A rescue plan for an incapacitated operator at height must be prepared before work starts and briefed to the team.

  • Emergency lowering methods differ by machine: auxiliary pump, manual descent valve, or brake release; the operator must know the specific model's method.

  • If the platform cannot be lowered, secure the scene, call emergency services, and keep the casualty supported and warm; do not attempt an improvised descent.

  • Suspension trauma: a person hanging in a harness after a fall must be rescued quickly and kept horizontal; time from suspension to rescue is critical.

  • Power line contact: stay in the platform, warn others away, and wait until the line is isolated; do not touch the machine and ground simultaneously.

  • After any incident or near miss, the machine is isolated, the scene preserved, and the event reported and investigated before return to service.

  • Emergency stops and alarms are tested at each shift; a machine with a failed emergency stop is out of service.

Quick reference

Ground conditions and structural loading

  • Point load per wheel or outrigger pad = (machine mass + payload) distributed over the contact points; check against slab or ground capacity.

  • Spreader plates increase the contact area and reduce pressure; the plate must be stiff enough to distribute load without punching the slab.

  • Outriggers must be fully deployed on firm ground with floats/pads; partial deployment or blocking on loose material is prohibited.

  • Slope limits are stated by the manufacturer; operate within them and never on ground that could collapse or is undermined by excavation.

  • Check for buried services, basements, and suspended slabs; a structural engineer's check is required where capacity is uncertain.

  • Drainage covers, trenches, and backfilled areas may not support the machine; verify before positioning.

  • Wind and side loads increase the effective load on the base; stop when the rated wind speed is reached.

Quick reference

Controls, interlocks and machine familiarisation

  • Controls are typically proportional with a dead-man/enable switch; releasing the enable switch stops all functions.

  • Tilt interlocks prevent elevation or drive beyond the rated slope; overload interlocks prevent lifting beyond rated capacity.

  • Pothole protection devices deploy on elevation on scissor lifts; a damaged or blocked device puts the machine out of service.

  • Emergency stop buttons are located on the platform and ground controls; both must function.

  • Ground controls allow lowering in an emergency and must be operable by a trained person; the platform controls are the normal operating position.

  • Familiarisation covers the specific model's controls, load chart, emergency lowering, restraints, and interlocks; it is recorded.

  • Never bypass or disable an interlock; a machine with a defeated safety device must be isolated and reported.

Quick reference

MEWP use near edges, openings and structures

  • Keep the platform clear of unprotected edges and openings; the base must be set back from unshored excavations by the distance required by ground conditions.

  • Do not trap the platform against a structure: entrapment between the platform and an overhead structure is a recognised fatal risk; keep clear and use a spotter where visibility is limited.

  • Maintain the required approach distance from overhead power lines for the line voltage; treat all lines as live until isolated.

  • Barrier the full working radius, including the sweep of a rotating boom and the area beneath the platform.

  • Where the platform must be exited at height, only the manufacturer's permitted method with a specific risk assessment, anchorage, and edge protection is used.

  • Check for fragile surfaces, skylights, and false ceilings that the platform or operator could fall through.

  • Maintain escape routes and emergency access; do not block fire routes or hydrants.

Quick reference

MEWP selection and task planning

  • Define the task: working height = platform height + operator reach (commonly ~2 m); confirm the machine's rated working height exceeds the task.

  • Reach over an obstacle → boom (B); large stable deck on a flat slab → scissor (A); restricted travel with platform up → group 3.

  • Check access route: door widths, floor loading, slope, and overhead obstructions along the route to the work area.

  • Confirm the machine's category from the data plate before planning travel with the platform elevated.

  • Consider power source: battery for indoor/confined spaces, diesel/LPG for outdoor with ventilation considerations.

  • Plan the rescue method and confirm the machine's emergency lowering function before starting.

  • Brief the team on the method statement, exclusion zones, and communication/signalling arrangements.

Quick reference

MCWP and CH: inspection and handover

  • Final inspection before first use is recorded and covers structure, ties, gates, interlocks, brakes, and emergency devices.

  • Periodic thorough examination by a competent person follows at statutory intervals and after alteration or repair.

  • Tie anchors are checked for capacity; anchor testing or specified embedment is required where the structure's capacity is unverified.

  • Landing doors and platform gates must self-close and interlock; defeating an interlock is prohibited.

  • The area beneath the MCWP and CH is barriered as a no-go zone during operation.

  • Handover documentation includes the method statement, inspection records, and the manufacturer's manual.

  • Defects are reported and the installation isolated until assessed and repaired.

Quick reference

Weather, environment and operational limits

  • Stop when wind exceeds the manufacturer's rated maximum; platform sail area rises with boom length and added attachments.

  • Account for wind funnelling between buildings and for sudden gusts; a calm ground reading does not guarantee calm at platform height.

  • Stop in lightning, ice, or snow that compromises the deck and controls; clear the deck before resuming.

  • Indoor use: battery machines are preferred; combustion machines require ventilation and exhaust routing to prevent carbon monoxide accumulation.

  • Heat and cold affect battery performance and hydraulic behaviour; follow the manufacturer's temperature limits.

  • Visibility: use a signaller where the operator's view is obstructed; maintain communication with ground personnel.

  • After severe weather, inspect the machine and its base before resuming work.

Quick reference

Documentation, records and legal duties

  • Hold the operator training/familiarisation record, machine logbook, thorough examination report, and the manufacturer's manual on the machine.

  • Pre-use inspection is recorded daily; the machine is tagged out of service if any safety item fails.

  • Thorough examination intervals follow the applicable regulations and the manufacturer; records are kept available at the point of use.

  • Modifications affecting stability, capacity, or controls require manufacturer approval and re-rating before use.

  • Employer duties include selection, training, familiarisation, supervision, and provision of a safe system of work.

  • Operator duties include pre-use inspection, respecting capacity, and stopping work when conditions become unsafe.

  • Report and investigate incidents and near misses; feed lessons back into the method statement and checks.

Quick reference

MEWP categories: 1B, 3A, 3B decision rules

  • 1B: boom MEWP that cannot travel with the platform elevated; reposition stowed, then elevate.

  • 3A: scissor MEWP that can travel with the platform elevated; travel limited to firm, level ground within rated slope and floor loading.

  • 3B: scissor MEWP that cannot travel elevated; drive stowed, then elevate on station.

  • 1A: push-around vertical lift; moved manually and elevated only when stationary on firm ground.

  • Group 1 = no travel elevated; group 3 = travel elevated; type A = no rotating structure extending beyond chassis; type B = boom or rotating structure.

  • Confirm the category from the data plate and manual before planning travel with the platform elevated.

  • When in doubt, treat the machine as group 1 and reposition stowed.

Quick reference

MEWP loading and platform capacity

  • Available payload = rated capacity − operator mass − tools/materials − attachments; never exceed the plate figure in total.

  • Rated capacity is a uniformly distributed load; concentrated loads on guardrails or deck edges must be spread.

  • The load chart applies at the working radius shown on the platform placard, not at the boom angle.

  • Attachments such as panels or signage increase sail area and may require re-checking the wind rating.

  • Never use the platform as a crane; tag lines and ropes only where the manufacturer permits.

  • Check the plate for the number of persons and the total load; the person limit is absolute regardless of weight.

  • Report and isolate the machine if the overload interlock activates; do not reset and continue without assessment.

Quick reference

Fall protection and restraints on MEWPs

  • Guardrails, mid-rails, toe boards, and gates are the primary fall-protection system; the platform must not be used with any missing or damaged.

  • Where required, a full-body harness with a short restraint lanyard is anchored to the designated point; the lanyard prevents ejection over the guardrail.

  • A restraint lanyard is not a fall-arrest system; it is kept short enough to prevent the operator leaving the platform.

  • Scissor lifts are generally not anchorage-rated for fall arrest; follow the manufacturer's and site's requirements.

  • Never climb on the guardrail or use ladders/boxes inside the platform to gain height.

  • Exit at height only where the manufacturer permits and a specific risk assessment, anchorage, and edge protection are in place.

  • Inspect harness, lanyard, and anchor before each use; damaged equipment is removed from service.

Quick reference

MEWP ground conditions and positioning

  • Verify ground capacity against wheel and outrigger point loads; use spreader plates where slab capacity is marginal.

  • Outriggers fully deployed on firm ground with floats/pads; partial deployment or blocking on loose material is prohibited.

  • Operate within the manufacturer's slope limits; never on ground that could collapse or is undermined by excavation.

  • Check for buried services, basements, and suspended slabs; an engineer's check is required where capacity is uncertain.

  • Keep the base set back from unshored excavations by the distance required by ground conditions.

  • Drainage covers, trenches, and backfilled areas may not support the machine; verify before positioning.

  • Barrier the full working radius, including the sweep of a rotating boom and the area beneath the platform.

Quick reference

MEWP emergency lowering and rescue

  • Know the specific model's emergency lowering method: auxiliary pump, manual descent valve, or brake release.

  • Test the emergency lowering function at the pre-use inspection where the manufacturer permits.

  • A rescue plan for an incapacitated operator at height must be prepared before work starts and briefed.

  • If the platform cannot be lowered, secure the scene, call emergency services, and keep the casualty supported; do not attempt an improvised descent.

  • Suspension trauma: rescue quickly and keep the casualty horizontal; time from suspension to rescue is critical.

  • Power line contact: stay in the platform, warn others away, and wait until the line is isolated.

  • After any incident, isolate the machine, preserve the scene, and report and investigate before return to service.

Quick reference

MEWP power sources and charging

  • Battery machines: check state of charge; charge with the machine off in a designated, ventilated area away from ignition sources.

  • Diesel/LPG machines: check fuel level and no leaks; exhaust must not route into an enclosed space because carbon monoxide can accumulate.

  • Battery machines are preferred indoors and in confined spaces.

  • Heat and cold affect battery performance and hydraulic behaviour; follow the manufacturer's temperature limits.

  • Check hydraulic hoses and fittings for leaks and chafing at the pre-use inspection.

  • Do not refuel or charge near open flame or while the machine is running, per the manufacturer's instructions.

  • A machine with a fuel or hydraulic leak is out of service until repaired.

Quick reference

MEWP inspection and defect reporting

  • Daily pre-use inspection covers tyres, outriggers, guardrails, gates, decals, battery/fuel, hydraulic leaks, emergency stops, and tilt/overload interlocks.

  • The inspection is recorded; the machine is tagged out of service if any safety item fails.

  • Thorough examination by a competent person follows at statutory intervals and after alteration or repair.

  • Defects are reported immediately and the machine isolated; operating with a known defect is a breach regardless of urgency.

  • Keep the logbook, thorough examination report, and manufacturer's manual on the machine.

  • Modifications affecting stability, capacity, or controls require manufacturer approval and re-rating before use.

  • After severe weather or an incident, inspect the machine and its base before resuming work.

Quick reference

MEWP operator competence and authorisation

  • The operator must be trained to the correct category, familiarised with the specific model, and authorised by the employer before operating.

  • Familiarisation covers the model's controls, load chart, emergency lowering, restraints, and interlocks, and is recorded.

  • The operator is responsible for the pre-use inspection, for not exceeding rated capacity, and for stopping work if conditions become unsafe.

  • Alcohol, drugs, and impairing medication are incompatible with operating; fatigue and medical conditions must be declared.

  • The operator must not allow unauthorised persons to operate the machine and must secure it against use when unattended.

  • Follow the manufacturer's manual and the site's method statement; where they conflict on a safety point, the more restrictive applies.

  • Report defects, near misses, and incidents immediately; the machine is isolated until assessed.

Quick reference

MCWP: erection, ties and climbing

  • An MCWP climbs a mast and is covered by EN 1495, not EN 280; it is not a MEWP.

  • Rated load is typically a uniformly distributed load over the platform length; concentrated and eccentric loads are limited by the manufacturer.

  • Mast ties to the structure are engineered at specified vertical intervals; tie spacing and anchor design come from the manufacturer or a competent engineer.

  • The base is founded on a designed foundation or spreader arrangement; the mast is plumbed within tolerance before climbing.

  • Climbing is controlled from the platform or a designated station; personnel must not be on the platform during climbing unless the procedure permits.

  • Tie anchors into concrete must be checked for pull-out capacity; anchor testing or specified embedment is required where capacity is unverified.

  • Erection, alteration, and dismantling are by trained, competent persons under a documented method statement, with a recorded handover.

Quick reference

Construction hoists: gates, interlocks and loading

  • Personnel hoists require a car with gates, landing doors at every landing, and interlocks preventing movement unless all gates and doors are closed and locked.

  • The rated load and number of persons are stated on a plate in the car; the passenger limit is absolute regardless of weight.

  • Landing doors must be self-closing and interlocked; the gate must not be defeated to speed loading.

  • Mast ties are designed at specified intervals; the free-standing height above the top tie is limited and must never be exceeded.

  • The area beneath the hoist is barriered as a no-go zone while the hoist is in motion.

  • The emergency stop and alarm are tested at each shift; the car is not driven with the door open.

  • Overload detection, overspeed/braking tests, and the final inspection before first use are documented; periodic thorough examination follows at statutory intervals.

Quick reference

MEWP selection: working height and reach

  • Working height = platform height + operator reach (commonly ~2 m); confirm the machine's rated working height exceeds the task.

  • Reach over an obstacle → boom (B); large stable deck on a flat slab → scissor (A); restricted travel with platform up → group 3.

  • Check the access route: door widths, floor loading, slope, and overhead obstructions along the route to the work area.

  • Confirm the machine's category from the data plate before planning travel with the platform elevated.

  • Consider power source: battery for indoor/confined spaces; diesel/LPG for outdoor with ventilation considerations.

  • Plan the rescue method and confirm the emergency lowering function before starting.

  • Brief the team on the method statement, exclusion zones, and communication/signalling arrangements.

Quick reference

MEWP hazards: entrapment, power lines and edges

  • Entrapment between the platform and an overhead structure is a recognised fatal risk; keep clear and use a spotter where visibility is limited.

  • Maintain the required approach distance from overhead power lines for the line voltage; treat all lines as live until isolated.

  • If contact occurs, stay in the platform, warn others away, and wait until the line is isolated.

  • Keep the platform clear of unprotected edges and openings; the base is set back from unshored excavations by the distance required by ground conditions.

  • Check for fragile surfaces, skylights, and false ceilings that the platform or operator could fall through.

  • Barrier the full working radius, including the sweep of a rotating boom and the area beneath the platform.

  • Maintain escape routes and emergency access; do not block fire routes or hydrants.