First 50 of 200 questions. Each one lists the choices, the correct answer, and an explanation. The checker at the top of this page saves progress in this browser when it is available.

Continue in the practice tool above to load more questions, 50 at a time.

Question 1Stakeholder identification and analysis

In stakeholder engagement practice, what distinguishes a 'stakeholder' from a merely interested party such as a casual reader of a news article about the project?

  1. A stakeholder is defined strictly as a person holding formal contractual authority over project deliverables.
  2. A stakeholder is anyone who has heard of the project, including incidental audiences reached by publicity.
  3. A stakeholder has an active stake: they can affect the project's outcomes or are affected by them, whereas a casual reader has neither capacity. Correct answer.
  4. A stakeholder is any individual the project manager has personally met during the engagement lifecycle.

Explanation

The defining test of a stakeholder is a two-way relationship: influence over the project or exposure to its effects. Incidental audiences have no stake to manage, so they fall outside the engagement baseline. Contractual authority is one narrow source of influence, not the definition.

Question 2Stakeholder identification and analysis

A programme manager is deciding how wide to cast the net when building the initial stakeholder register. Which approach best reflects good practice in stakeholder identification?

  1. Defer identification until the design is frozen, so only genuinely affected parties are captured.
  2. Start broad with a structured sweep, then filter and justify exclusions so the register stays defensible. Correct answer.
  3. Include every person named in any project document without filtering, to guarantee nothing is missed.
  4. List only the sponsor and the delivery team, because external parties rarely change project outcomes.

Explanation

Identification should be deliberately inclusive first and analytical second: a wide sweep surfaces candidates, and documented filtering keeps the register credible and auditable. Excluding groups early risks missing influence that emerges later. Deferring identification leaves the project blind during the phase of greatest uncertainty.

Question 3Stakeholder identification and analysis

Which technique is specifically designed to trace how stakeholders influence one another, rather than simply listing them?

  1. A critical path analysis of the delivery schedule.
  2. A cost-benefit analysis of the project's financial return.
  3. A lessons-learned review of a previous unrelated project.
  4. Stakeholder circle mapping, which places stakeholders in concentric rings by influence and direction of impact. Correct answer.

Explanation

Stakeholder circle mapping visualises influence and the direction of impact, revealing who affects whom and how close each party sits to the project. Financial, scheduling and historical techniques do not map stakeholder relationships. Choosing a mapping technique is what distinguishes analysis from a flat register.

Question 4Stakeholder identification and analysis

A project team uses Mendelow's power/interest grid. A regulator has high power to block approvals but low day-to-day interest in the project's internal workings. How should this stakeholder be classified?

  1. Keep informed: low power, high interest.
  2. Keep satisfied: high power, low interest. Correct answer.
  3. Manage closely: high power, high interest.
  4. Monitor: low power, low interest.

Explanation

Mendelow's grid pairs high power with low interest in the 'keep satisfied' quadrant, because such parties can obstruct but need not be overloaded with detail. The engagement aim is to maintain their comfort without demanding their active involvement. Misclassifying them as 'manage closely' wastes effort and can trigger unwanted scrutiny.

Question 5Stakeholder identification and analysis

What is the primary purpose of segmenting stakeholders into groups during analysis?

  1. To reduce the register to the smallest possible number of names.
  2. To decide which stakeholders can be lawfully excluded from consultation.
  3. To tailor the type and intensity of engagement to each group's needs and influence. Correct answer.
  4. To rank individuals for performance appraisal within the project team.

Explanation

Segmentation exists so engagement effort can be differentiated: different groups warrant different channels, frequency and depth. It is an analytical device for targeting effort, not a headcount reduction or appraisal tool. Legal consultation duties are set by regulation, not by segmentation choices.

Question 6Stakeholder identification and analysis

Which source is most useful for identifying stakeholders that a project team might otherwise overlook because they are geographically distant?

  1. Community liaison contacts and local government representatives in the affected area. Correct answer.
  2. The team's own social media accounts.
  3. The sponsor's personal calendar of meetings.
  4. The project's internal timesheet system.

Explanation

Distant or affected communities are typically surfaced through local liaison channels and elected local representatives who know the area. Internal administrative records reflect only parties already engaged. Relying on team social media introduces bias and misses organised local interests.

Question 7Stakeholder identification and analysis

During analysis, a team records for each stakeholder their 'interest' and their 'influence'. What does 'interest' most accurately capture in this context?

  1. The frequency with which the stakeholder contacts the project team.
  2. The stakeholder's formal rank within their own organisation.
  3. The degree to which the stakeholder cares about, and is affected by, the project's outcomes. Correct answer.
  4. The amount of budget the stakeholder controls.

Explanation

Interest describes stake and concern: how much the party is affected by, and cares about, what the project does. Rank, budget and contact frequency are separate attributes that may inform influence or engagement history but are not interest itself. Keeping the two dimensions distinct is essential to correct grid placement.

Question 8Stakeholder identification and analysis

A stakeholder analysis workshop produces a long list of names but no agreed view of who matters most. Which immediate action best improves the analysis?

  1. Postpone all engagement until the list is naturally shorter.
  2. Ask each team member to keep their own private ranking.
  3. Agree explicit criteria for influence and interest, then score stakeholders against them consistently. Correct answer.
  4. Delete names until the list fits on a single page.

Explanation

Prioritisation requires transparent, shared criteria so that scoring is consistent and defensible across the team. Truncating the list or keeping private rankings substitutes arbitrary choice for analysis. Postponing engagement while waiting for attrition leaves stakeholders unmanaged.

Question 9Stakeholder identification and analysis

A supplier has low power over the project and low interest in its outcomes, but must still receive statutory notices. Which handling is most appropriate?

  1. Monitor with minimal, compliance-driven communication. Correct answer.
  2. Keep satisfied with senior executive briefings.
  3. Manage closely with weekly co-design workshops.
  4. Treat as a champion and invite to steering meetings.

Explanation

Low power and low interest place the supplier in the monitor quadrant, where minimal but compliant communication suffices. Heavy engagement would consume effort disproportionate to the stake. Statutory notices are an obligation and do not by themselves raise the party's interest or power.

Question 10Stakeholder identification and analysis

A stakeholder who currently has low influence is expected to gain significant regulatory authority in six months. How should the analysis reflect this?

  1. Remove the stakeholder until the change actually happens, then re-add them.
  2. Keep the classification fixed, because analysis should reflect only the present position.
  3. Immediately classify the stakeholder as high power and engage as if the change had already occurred.
  4. Record the anticipated change in influence and schedule a review so the engagement approach can shift accordingly. Correct answer.

Explanation

Stakeholder analysis is a living process: anticipated shifts in influence should be recorded with a planned review point. Treating the grid as static ignores foreseeable change, while acting as if the future state already applies may distort current effort. Removing the party forfeits the chance to build the relationship before their power arrives.

Question 11Stakeholder identification and analysis

Which pairing of stakeholder attribute and engagement implication is most sound?

  1. High interest with low power suggests keeping the party informed and using them as a source of insight. Correct answer.
  2. High power with high interest suggests limiting contact to an annual newsletter.
  3. Low interest with low power suggests appointing them as the project's decision authority.
  4. High power with low interest suggests daily detailed progress reports to build enthusiasm.

Explanation

High-interest, low-power parties are valuable informants and advocates, so keeping them informed captures insight without granting them decision rights. Flooding a low-interest powerful party with detail risks irritation rather than enthusiasm. Decision authority and minimal contact are mismatched to the attributes described.

Question 12Stakeholder identification and analysis

Two stakeholders are both classified as high power and high interest, but one is a strong supporter and the other a vocal critic. What does good analysis recommend?

  1. Apply identical communication to both, since their grid position is the same.
  2. Transfer management of both to the communications team and stop tracking them.
  3. Manage both closely but differentiate tactics, leveraging the supporter and addressing the critic's concerns directly. Correct answer.
  4. Downgrade the critic to low priority to avoid negative attention.

Explanation

Grid position sets the intensity of engagement, while attitude sets the tactics within that intensity. Treating a supporter and a critic identically wastes the advocate's reach and leaves the critic's concerns unaddressed. Downgrading a powerful critic suppresses the risk rather than managing it.

Question 13Stakeholder identification and analysis

What is the main limitation of relying solely on a power/interest grid for stakeholder analysis?

  1. It is incompatible with maintaining a written stakeholder register.
  2. It reduces rich stakeholder situations to two dimensions and can obscure attitude, legitimacy and relationships. Correct answer.
  3. It requires expensive software that most projects cannot afford.
  4. It can only be applied to internal stakeholders.

Explanation

The grid is a simplification: two axes cannot capture attitude, urgency, legitimacy or the networks between stakeholders. Skilled analysts supplement it with other lenses such as attitude mapping or influence diagrams. Cost, internal-only scope and register incompatibility are not genuine limitations of the tool.

Question 14Stakeholder identification and analysis

A stakeholder map shows that a mid-level manager connects several otherwise separate stakeholder groups. Why does this matter for engagement planning?

  1. The manager's position proves they hold formal decision authority.
  2. The manager is a broker whose support or opposition can amplify messages across groups, so the relationship deserves attention. Correct answer.
  3. The manager should be removed from the map to simplify the picture.
  4. The manager's connectivity means they can be ignored, because others will relay information.

Explanation

Network position matters: brokers can accelerate or block the spread of information and sentiment across groups. Recognising them lets the project use them as a communication channel or manage them as a risk. Connectivity is not proof of formal authority, and ignoring a broker cedes influence to chance.

Question 15Stakeholder identification and analysis

Which statement best describes the relationship between stakeholder identification and stakeholder analysis?

  1. Identification and analysis are synonyms and are performed once at project start.
  2. Identification is optional once analysis has begun.
  3. Identification produces the candidate set; analysis judges significance, relationships and appropriate engagement. Correct answer.
  4. Analysis must be completed before any stakeholder can be identified.

Explanation

Identification answers 'who', while analysis answers 'how much and how'. They are iterative and interleaved rather than a single upfront event. Analysis cannot precede identification because there is nothing yet to analyse, and identification never stops being useful as new parties emerge.

Question 16Stakeholder identification and analysis

An engagement lead wants to validate the stakeholder register against reality before finalising the strategy. Which action provides the strongest validation?

  1. Cross-check the register with frontline staff and external contacts who deal with stakeholders directly. Correct answer.
  2. Assume the register is correct once it has been typed up neatly.
  3. Ask only the project sponsor to confirm the list is complete.
  4. Rely on the register from a similar project run five years ago.

Explanation

Frontline and external contacts hold ground-level knowledge of who actually matters and are well placed to spot omissions. A single senior view may replicate existing blind spots, and an old register may reflect a different context. Neat formatting is no evidence of accuracy.

Question 17Stakeholder identification and analysis

A project has a stakeholder with high interest but very low trust in the organisation. What does good analysis suggest about engagement design?

  1. Escalate immediately to legal action against the stakeholder.
  2. Prioritise transparency and early involvement to rebuild trust, while managing expectations carefully. Correct answer.
  3. Limit communication to formal notices to avoid further disagreement.
  4. Classify the stakeholder as low priority because trust is not an analytical dimension.

Explanation

Low trust combined with high interest is a significant risk that calls for openness and early involvement rather than withdrawal. Restricting communication tends to deepen suspicion and harden opposition. Trust is a recognised dimension of stakeholder attitude and belongs in the analysis.

Question 18Stakeholder identification and analysis

Which combination of techniques gives the most complete picture when analysing a complex stakeholder landscape?

  1. A single power/interest grid used in isolation.
  2. A power/interest grid combined with attitude mapping and a network or influence diagram. Correct answer.
  3. A financial risk register with no stakeholder dimension.
  4. A list of names sorted alphabetically.

Explanation

Different lenses reveal different things: the grid prioritises, attitude mapping reveals stance, and network diagrams expose relationships and brokers. Using them together compensates for each tool's blind spots. A single grid or an alphabetical list captures only part of the picture, and a purely financial register omits stakeholders entirely.

Question 19Stakeholder identification and analysis

A stakeholder's influence derives mainly from their ability to mobilise public opinion rather than from formal authority. How should the analysis treat this?

  1. Dismiss it, because only formal authority counts as power in stakeholder analysis.
  2. Reclassify the stakeholder as low power until they obtain an official role.
  3. Record it as a legitimate source of influence, since power can be informal as well as positional. Correct answer.
  4. Record it only if the stakeholder holds a formal title in a recognised institution.

Explanation

Power in stakeholder analysis includes informal and reputational sources such as the ability to shape public opinion. Ignoring informal power systematically underestimates risk. Formal authority is one source among several, and requiring an official title would exclude many genuinely influential parties.

Question 20Stakeholder identification and analysis

In Mendelow's grid, why is the 'keep informed' quadrant typically populated by parties with high interest but low power?

  1. They control the budget and must approve all expenditure.
  2. They have no stake in the project and can safely be ignored.
  3. They need sufficient information to remain comfortable, but cannot compel decisions, so effort focuses on communication rather than negotiation. Correct answer.
  4. They hold decision rights, so they must be consulted on every design choice.

Explanation

High-interest, low-power parties care deeply but cannot force outcomes, so the appropriate response is informative communication that maintains their comfort. They do not hold decision rights or budget control by virtue of this quadrant. Ignoring them would be wrong precisely because their interest is high.

Question 21Stakeholder identification and analysis

A project team discovers a stakeholder group that only emerges after a regulatory change mid-project. What is the most appropriate analytical response?

  1. Treat the group as low priority purely because it was not in the original plan.
  2. Add the group to the register but defer any assessment until project closure.
  3. Add the group to the register, assess its power, interest and attitude, and adjust the engagement plan accordingly. Correct answer.
  4. Ignore the group because the original analysis is already approved.

Explanation

Stakeholder analysis is continuous, and new parties must be assessed on their merits rather than on their absence from an earlier plan. Freezing an approved analysis ignores material change. Deferring assessment leaves a new risk unmanaged, and penalising late arrivals substitutes procedural loyalty for analysis.

Question 22Stakeholder identification and analysis

A stakeholder appears in the 'manage closely' quadrant but has consistently resisted every engagement attempt. What is the most rigorous analytical next step?

  1. Remove the stakeholder from the register so the quadrant looks cleaner.
  2. Re-examine the underlying drivers of resistance and test whether the classification or the engagement approach is wrong. Correct answer.
  3. Increase the volume of communication without changing its content or approach.
  4. Escalate to senior management to have the stakeholder overruled.

Explanation

Persistent resistance is diagnostic: it may signal a misread of the stakeholder's interests, a flawed engagement approach, or a genuine irreconcilable position. Investigating drivers preserves the analytical integrity of the map. Removing the party or simply escalating suppresses evidence, and more of the same communication rarely changes a resistant stance.

Question 23Stakeholder identification and analysis

Two departments both claim to be the project's single most important stakeholder, and each has high power and high interest. What does sound analysis recommend?

  1. Award priority to whichever department asserted the claim first.
  2. Assess each department's specific interests, decision rights and attitude separately rather than ranking them by assertion alone. Correct answer.
  3. Declare both low priority to avoid taking sides.
  4. Rank them by headcount as a proxy for importance.

Explanation

Competing claims should be resolved through evidence about decision rights, specific interests and stance, not through assertion or crude proxies. Headcount and order of claim are not measures of stakeholder significance. Declaring both low priority misclassifies two genuinely powerful parties.

Question 24Stakeholder identification and analysis

A team builds a stakeholder map that shows only one-way arrows from the project to each stakeholder. What important analytical dimension does this omit?

  1. The delivery schedule's critical path.
  2. The number of meetings held with each stakeholder.
  3. The project's budget baseline.
  4. The reciprocal influence stakeholders exert on the project and on each other. Correct answer.

Explanation

Stakeholder relationships are reciprocal: parties affect the project and one another, not merely receive its outputs. One-way arrows reduce a dynamic system to a broadcast list. Budget, schedule and meeting counts are separate management data and do not capture relational influence.

Question 25Stakeholder identification and analysis

A sponsor insists that only parties with formal contracts should appear in the stakeholder register. Which argument best explains why this position is analytically unsound?

  1. The position is unsound because contracts are legally unenforceable in most projects.
  2. Contract-only registers are unsound mainly because they take too long to compile.
  3. The position is unsound because the sponsor lacks authority over stakeholder matters.
  4. Influence and exposure arise from many non-contractual sources, so a contract-only register would omit regulators, communities and informal influencers. Correct answer.

Explanation

Stakeholder significance flows from influence and exposure, not from contractual status alone. A contract-only register would systematically exclude regulators, affected communities and informal opinion leaders who can materially affect outcomes. Compilation time, contract enforceability and the sponsor's authority are irrelevant to the analytical flaw.

Question 26Stakeholder identification and analysis

In stakeholder engagement practice, what is the primary purpose of building and maintaining a stakeholder register?

  1. To provide a structured, maintained record of identified stakeholders and relevant attributes Correct answer.
  2. To document the project schedule baseline for governance reviews
  3. To record payment terms agreed with each contracted supplier
  4. To replace the engagement plan once stakeholders have been confirmed

Explanation

The stakeholder register is the working record of who has been identified and what is known about them, such as their interests, influence, attitude and engagement needs. It is maintained and updated as the landscape changes, and it feeds rather than replaces the engagement plan.

Question 27Stakeholder identification and analysis

A team is starting stakeholder identification on a programme that affects several regions. Which approach best reduces the risk of missing affected parties at the outset?

  1. Limit identification to parties named in the business case
  2. Rely on the sponsor's personal contact list from previous work
  3. Combine several identification techniques and review the output with different groups Correct answer.
  4. Use a single technique consistently so results stay comparable

Explanation

Identification is more complete when multiple techniques are combined, because each technique surfaces different parties and biases. Reviewing the emerging list with varied groups helps expose blind spots before analysis begins.

Question 28Stakeholder identification and analysis

Which statement correctly distinguishes stakeholder identification from stakeholder analysis?

  1. Identification ranks stakeholders by priority; analysis produces the initial list of names
  2. Identification catalogues who the stakeholders are; analysis interprets their attributes and significance Correct answer.
  3. Identification happens once at initiation; analysis replaces it during delivery
  4. Identification and analysis are interchangeable terms for the same activity

Explanation

Identification is about discovering and recording who has an interest or stake. Analysis then examines those parties' attributes, such as power, interest, attitude and networks, so engagement can be prioritised and tailored.

Question 29Stakeholder identification and analysis

A stakeholder is described in the register as having a 'latent' interest. What does this most accurately mean for engagement planning?

  1. The stakeholder has no legitimate relationship with the initiative
  2. The stakeholder's stake exists but they are not yet actively engaged or aware of it Correct answer.
  3. The stakeholder has delegated all decisions to a representative body
  4. The stakeholder has formally objected to the initiative in writing

Explanation

Latent interest means a stake exists even though the party is not yet mobilised or conscious of it. Such stakeholders still need to be identified and considered, because dormant interest can become active and influential later.

Question 30Stakeholder identification and analysis

When recording stakeholder attitude on a simple scale, which set of categories is most commonly used in engagement practice?

  1. Supporter, neutral, critic Correct answer.
  2. Internal, external, contracted
  3. High, medium, low
  4. Supplier, customer, regulator, employee

Explanation

Attitude describes a stakeholder's disposition towards the initiative, typically ranging from supportive through neutral to resistant or critical. The other lists describe type or magnitude, not disposition.

Question 31Stakeholder identification and analysis

A team uses a power/interest grid during stakeholder analysis. Which pair of attributes does this grid combine?

  1. Attitude and legitimacy
  2. Power and interest Correct answer.
  3. Urgency and proximity
  4. Influence and proximity

Explanation

The widely used power/interest grid positions stakeholders according to their ability to affect the initiative and their concern in its outcomes. It is a simple prioritisation aid, not a complete analysis.

Question 32Stakeholder identification and analysis

Which of the following is a legitimate external stakeholder for a public-sector digital service programme?

  1. The programme's own assurance manager
  2. A residents' association affected by the service change Correct answer.
  3. A member of the programme's delivery team
  4. The internal finance business partner

Explanation

External stakeholders sit outside the performing organisation but are affected by, or can affect, the initiative. A residents' association is a clear example, whereas the other options are internal roles.

Question 33Stakeholder identification and analysis

Why should a stakeholder register be treated as a living document rather than a one-off deliverable?

  1. Because it forms part of the financial reporting pack
  2. Because regulators require it to be reissued every quarter
  3. Because the stakeholder landscape changes as the initiative progresses Correct answer.
  4. Because it must be signed off by every listed stakeholder

Explanation

New stakeholders emerge, attitudes shift and influence rises or falls as an initiative develops. The register must therefore be revisited and updated so that analysis and engagement remain relevant.

Question 34Stakeholder identification and analysis

A stakeholder map shows a regulator with high power and low interest. According to the logic of a power/interest grid, what engagement approach is most appropriate?

  1. Engage intensively and involve them in detailed design decisions
  2. Monitor with minimal effort and no communication
  3. Keep them satisfied with sufficient, accurate information Correct answer.
  4. Treat them as a passive recipient and share nothing until launch

Explanation

High-power, low-interest stakeholders can affect the initiative but are not deeply concerned day to day. The usual approach is to keep them satisfied by providing adequate, accurate information so that their latent power is not activated negatively.

Question 35Stakeholder identification and analysis

A community group has high interest in a construction project but very little formal power. Which engagement stance is most consistent with good practice?

  1. Keep them informed and provide channels for their concerns to be heard Correct answer.
  2. Ignore them until they escalate a formal complaint
  3. Restrict communication to statutory notices only
  4. Give them decision rights over the project schedule

Explanation

High-interest, low-power stakeholders are typically kept informed, with channels that allow concerns to surface before they become issues. Their interest makes them attentive and potentially influential through other routes.

Question 36Stakeholder identification and analysis

During analysis, a team finds that a stakeholder's influence comes from their expertise rather than their position. Why does this matter for engagement strategy?

  1. Only positional power should be recorded in the register
  2. Influence based on expertise can shape decisions and opinions, so it must be accounted for Correct answer.
  3. Expertise always indicates a supportive attitude
  4. Expert influence is irrelevant unless the person holds formal authority

Explanation

Influence is not limited to formal authority; expert credibility can sway decisions and shape others' views. Analysis must capture the source of influence so engagement can address it appropriately.

Question 37Stakeholder identification and analysis

A stakeholder's influence is expected to grow significantly after an upcoming election. How should the analysis reflect this?

  1. Record only their current influence and revisit the register after the election
  2. Treat them as low priority because their influence is not yet real
  3. Capture the anticipated change in influence and adjust the engagement approach in advance Correct answer.
  4. Remove them from the register until the election result is known

Explanation

Stakeholder analysis should be forward-looking where change is foreseeable. Anticipating a rise in influence lets the team build relationships and adapt engagement before the shift occurs.

Question 38Stakeholder identification and analysis

Which technique is most useful for revealing informal connections and communication paths between stakeholders?

  1. A risk register review
  2. A stakeholder network or sociogram map Correct answer.
  3. A lessons-learned log
  4. A cost-benefit analysis

Explanation

Network or sociogram mapping displays relationships and communication flows between stakeholders, exposing brokers and clusters. It complements attribute-based grids by showing how influence actually travels.

Question 39Stakeholder identification and analysis

A stakeholder has high power, high interest and a strongly opposed attitude. What does sound analysis suggest the team should do first?

  1. Exclude them from communications to limit their influence
  2. Reclassify them as low priority because they are opposed
  3. Wait until they raise objections through formal channels
  4. Engage them closely to understand their concerns and seek to address or manage them Correct answer.

Explanation

A powerful, interested opponent is a significant risk to the initiative. Close engagement to understand and address their concerns is the appropriate first response, rather than avoidance or exclusion.

Question 40Stakeholder identification and analysis

A team has produced a list of stakeholders but has not examined their relative importance. What is the most appropriate next step in the analysis?

  1. Delete stakeholders who cannot be contacted immediately
  2. Close the identification phase and begin delivery
  3. Publish the list to all stakeholders for comment
  4. Apply an analysis technique to assess and prioritise stakeholders by relevant attributes Correct answer.

Explanation

Identification produces the raw list; analysis is needed to assess attributes and relative significance. Applying a technique such as a power/interest grid turns the list into a basis for prioritised engagement.

Question 41Stakeholder identification and analysis

Which stakeholder attribute best captures how much a party can affect the initiative's outcomes?

  1. Influence Correct answer.
  2. Proximity
  3. Interest
  4. Attitude

Explanation

Influence (or power) describes a stakeholder's capacity to affect decisions, resources or outcomes. Interest concerns their concern in the initiative, attitude their disposition, and proximity their closeness to its effects.

Question 42Stakeholder identification and analysis

A project has many stakeholders, and the team cannot engage all of them intensively. What is the main purpose of prioritising stakeholders during analysis?

  1. To allocate finite engagement effort where it will have the greatest effect Correct answer.
  2. To ensure every stakeholder receives identical communication
  3. To satisfy a documentation requirement in the engagement plan
  4. To identify which stakeholders can be ignored permanently

Explanation

Prioritisation directs limited engagement resources towards stakeholders whose influence, interest or attitude most affects the initiative. It is about focusing effort, not excluding parties or treating everyone identically.

Question 43Stakeholder identification and analysis

A stakeholder's influence is high, but their interest is low and their attitude is neutral. Which engagement approach is most appropriate?

  1. Treat them as a critic and restrict information
  2. Ignore them entirely until they make contact
  3. Involve them in detailed working groups
  4. Keep them satisfied and monitor their position Correct answer.

Explanation

A powerful but uninterested neutral party needs sufficient information to remain satisfied, plus monitoring in case their interest or attitude shifts. Intensive involvement is unnecessary and ignoring them is risky.

Question 44Stakeholder identification and analysis

A team uses a stakeholder circle or influence/impact map rather than a simple grid. What does this technique add?

  1. A financial valuation of each stakeholder's contribution
  2. A guarantee that all stakeholders will support the initiative
  3. A replacement for the stakeholder register
  4. A visual depiction of proximity and degree of impact around the initiative Correct answer.

Explanation

Circle or influence/impact mapping places the initiative at the centre and shows stakeholders at varying distances according to their impact or closeness. It adds a spatial, proximity-based view that a two-axis grid does not provide.

Question 45Stakeholder identification and analysis

A stakeholder has a legitimate claim on the initiative but very little power and low interest. How should a team treat them in analysis?

  1. Exclude them because they cannot influence outcomes
  2. Record them and apply proportionate, minimal engagement while monitoring Correct answer.
  3. Engage them as intensively as high-power supporters
  4. Transfer their claim to a more powerful stakeholder

Explanation

Legitimacy gives a stakeholder a valid claim even when their power and interest are low. Proportionate engagement and monitoring respect that claim without diverting disproportionate effort from higher-priority parties.

Question 46Stakeholder identification and analysis

A stakeholder with high power and high interest is also a member of a group whose interests conflict with another powerful stakeholder. What does sound analysis recommend?

  1. Analyse the conflict explicitly and plan engagement that addresses both positions Correct answer.
  2. Engage only the stakeholder who supports the initiative
  3. Delay all engagement until the conflict disappears
  4. Assume the two powerful stakeholders will resolve it without project involvement

Explanation

Conflicting interests between powerful stakeholders are a material risk that analysis should surface explicitly. Planned engagement that acknowledges both positions helps manage the conflict rather than letting it escalate unmanaged.

Question 47Stakeholder identification and analysis

A team relies solely on a power/interest grid and concludes that a low-power, low-interest group needs no attention. What is the main weakness of this conclusion?

  1. Low-interest groups never have any relationship with the initiative
  2. The grid cannot be applied to groups, only to individuals
  3. Low power and low interest may be temporary, and the group may still hold a legitimate claim Correct answer.
  4. The grid always overstates the importance of low-power groups

Explanation

A single grid captures a snapshot and can mask change, legitimacy and indirect influence. A low-power, low-interest group may gain relevance or hold a valid claim that warrants monitoring and proportionate engagement.

Question 48Stakeholder identification and analysis

Two analysts classify the same stakeholder differently: one places them as high influence, the other as low. What is the most rigorous way to resolve this?

  1. Average the two ratings to produce a compromise score
  2. Accept the more senior analyst's rating without discussion
  3. Remove the stakeholder from the analysis to avoid disagreement
  4. Discuss the evidence and criteria used for the rating to reach a shared, defensible view Correct answer.

Explanation

Divergent ratings usually reflect different evidence or unclear criteria. Examining the basis for each judgement and agreeing explicit criteria produces a more defensible and shared analysis than averaging or deferring to seniority.

Question 49Stakeholder identification and analysis

A stakeholder's influence is high but derived from their ability to block decisions through a veto. How should analysis treat this compared with influence derived from persuasion?

  1. Both should be treated identically because influence is influence
  2. Persuasion-based influence is always more significant than veto power
  3. Veto-based influence warrants particular attention because it can stop the initiative outright Correct answer.
  4. Veto power should be disregarded because it is negative influence

Explanation

Influence varies in nature as well as degree, and a veto can halt the initiative regardless of support elsewhere. Analysis should recognise this distinctive capacity and shape engagement accordingly.

Question 50Stakeholder identification and analysis

A team maps a stakeholder who acts as a broker between two otherwise disconnected groups. Why is this structural position significant in analysis?

  1. It means the broker has formal authority over both groups
  2. It means both groups share identical interests
  3. It means the broker should be excluded from the register
  4. It means the broker can control or filter information flows between the groups Correct answer.

Explanation

A broker sits between groups and can shape what information passes between them, giving them structural influence beyond their formal position. Recognising this helps the team engage the broker deliberately rather than bypassing them.