EPI Data Centre Associate study materials
EPI Data Centre Associate study resources

EPI Data Centre Associate flashcards

EPI Data Centre Associate · Build recall with a focused review session.

32 cards. Read the term and the definition here. The deck at the top of this page is optional.

PUE definition
Power usage effectiveness equals total facility energy divided by IT equipment energy over the same period. A value of 1.0 is theoretical perfection; typical well-run facilities sit between 1.2 and 1.6.
Tier III concurrency
Tier III requires concurrent maintainability: any capacity component or distribution path can be serviced or replaced without shutting down the IT load, though a fault may still cause an outage.
Tier IV fault tolerance
Tier IV adds fault tolerance to concurrent maintainability, meaning a single worst-case failure of any component or path causes no impact on the IT load.
2N redundancy
Two complete independent capacity sets, each capable of carrying the full IT load alone. Failure or maintenance of one set leaves the other fully operational.
Hot aisle containment
Physical enclosure of the hot exhaust aisle so heated air returns directly to the cooling units, preventing mixing with cold supply air and improving cooling efficiency.
ASHRAE recommended envelope
The recommended operating range for IT equipment inlet air: roughly 18 to 27 degrees Celsius dry-bulb with humidity controlled to limit electrostatic discharge and corrosion.
DCiE formula
Data centre infrastructure efficiency is the reciprocal of PUE, calculated as IT equipment energy divided by total facility energy and expressed as a percentage.
UPS efficiency losses
Double-conversion UPS systems typically lose 3 to 6 percent of input power as heat. Eco or line-interactive modes reduce losses but may reduce ride-through and power quality.
ANSI/TIA-942
A telecommunications infrastructure standard for data centres that defines spaces, cabling, redundancy and availability, and assigns Rated-1 to Rated-4 ratings through assessment.
ISO/IEC 22237 series
An international series specifying data centre facility and infrastructure requirements, covering design, build, and operation with availability and efficiency classifications.
EN 50600 series
European standards for data centres covering building construction, power distribution, environmental control, cabling, and operation, with defined availability and protection classes.
ISO/IEC 27001
The international standard for an information security management system. Certification requires an accredited auditor to assess controls, risk treatment, and continual improvement.
Clean agent suppression
Fire suppression using gaseous agents such as FM-200, Novec 1230, or inert gases that extinguish fire without leaving residue, safe for occupied IT spaces at design concentrations.
PCI DSS physical security
Requires cardholder data environments to restrict physical access, log entry and exit, retain audit logs at least 12 months with 3 months immediately available, and review logs.
CCTV retention period
Common data centre practice and many audit frameworks require video surveillance recordings to be retained for a defined period, often a minimum of 90 days.
Certification versus compliance
Certification is third-party attestation against a standard; compliance means meeting a standard's requirements and may be self-declared or verified without formal certificate.
Method of procedure
A MOP is a written, approved, step-by-step script for a specific non-routine task, including prerequisites, sequence, verification steps, and a rollback plan.
Change management record
Documentation of a change including request, risk assessment, approval, implementation and rollback plans, schedule, and post-implementation review confirming success.
Generator load test
Periodic verification that standby generators can carry rated load. Monthly exercise runs plus annual load-bank testing confirm capacity, fuel consumption, and cooling performance.
UPS battery end of life
VRLA batteries are typically replaced when measured capacity falls below 80 percent of rated capacity or impedance trends indicate degradation, often at 3 to 5 years.
Two-person rule
A control requiring two authorized individuals to be present for critical operations or access to sensitive areas, reducing insider risk and enabling independent verification.
P1 incident definition
The highest severity level: a total outage, major customer impact, or loss of redundancy with no compensating control, requiring immediate escalation and response.
Infrared thermography
A non-contact inspection method that detects abnormal heat in electrical connections and panels, revealing loose terminations or overloaded circuits before failure occurs.
Environmental alarm thresholds
Configured limits for temperature, humidity, water detection, and smoke that trigger alerts to operations staff before conditions breach equipment operating envelopes.
Recovery time objective
RTO is the maximum acceptable time to restore a service after disruption. It drives DR architecture choices such as hot standby, warm standby, or backup restore.
Recovery point objective
RPO is the maximum acceptable amount of data loss measured in time. It determines replication frequency, backup intervals, and whether synchronous replication is needed.
Risk treatment options
Four standard responses to identified risk: avoid the activity, mitigate with controls, transfer via insurance or contract, or accept and document the residual risk.
Risk register contents
A log recording each risk with identifier, description, likelihood, impact, inherent score, controls, residual score, owner, and review date for governance tracking.
Availability percentage math
99.9 percent allows about 8.76 hours downtime per year; 99.99 percent about 52.6 minutes; 99.999 percent about 5.26 minutes, calculated against total annual minutes.
Business impact analysis
A structured assessment identifying critical business processes, their dependencies, and the financial and operational consequences of disruption, producing RTO and RPO targets.
DR test cadence
Common governance expectation: tabletop exercises annually, functional component tests at least annually, and full failover tests every one to two years or per business requirement.
Vendor SLA components
A service level agreement should define availability percentage, measurement window and method, exclusions, reporting obligations, remedies or credits, and review frequency.