The Widening In Progress Band

EXIN Kanban Foundation · Put your knowledge to work in context.

All case studies

The Widening In Progress Band

HelpDeskCo handles 900 tickets per week with 22 agents. The board has Backlog, In Progress, Waiting on Customer and Resolved. There are no WIP limits. Average WIP is 140 tickets and throughput is 28 tickets per day; average lead time is five days. The service manager reports 85% SLA attainment and rising customer complaints. Ten percent of tickets are marked 'urgent' by account managers and jump to the top of every agent's queue; standard tickets often wait two days before first response. A new cumulative flow diagram shows the 'In Progress' band widening steadily while 'Resolved' stays flat. Agents also handle a monthly release checklist that takes three days and is never shown on the board. The manager proposes a single WIP limit of 160 for In Progress and a weekly prioritisation meeting.

1. A cumulative flow diagram shows the 'In Progress' band widening steadily while 'Resolved' stays flat. What does this most likely indicate, and what should the manager investigate before changing WIP limits?

Read the worked answer

A widening In Progress band with a flat Resolved band means work is entering and accumulating in process faster than it is being completed. Before changing limits, the manager should investigate where the accumulation is: aging of in-progress tickets, time in Waiting on Customer, rework, handoffs, and the effect of urgent tickets jumping the queue. The diagram alone does not prove agents are slow; it may show hidden work such as the monthly release checklist, blocked tickets or multitasking. The proposal of a single WIP limit of 160 is not a real improvement because it sets the limit at the current average WIP, ratifying the problem rather than reducing it. A better first step is to visualise the workflow by work type and state, add explicit policies for ready, blocked and done, measure queue time and touch time, and then set a limit below current WIP and observe the effect. Use the cumulative flow diagram together with a control chart of cycle time and an aging chart. A weekly prioritisation meeting may help, but it will not fix flow if work is not pulled.

2. How should the team define classes of service and policies for urgent versus standard tickets?

Read the worked answer

Start from customer and service impact, not from who asks. Define a small set of classes, for example expedite, fixed-date, standard and intangible, each with explicit entry criteria and a policy. Expedite should be reserved for genuine service outages, security incidents or contractual breaches, with a named authoriser and a cap, such as one or two expedite items in the system at a time, counted in WIP. Urgent cannot be 10% of all tickets and still be an exception; if account managers can mark tickets urgent without a trade-off, the class loses meaning and standard work starves. Fixed-date tickets need a date and a policy for when to start. Standard tickets are pulled in order, with an SLA for first response and resolution that reflects the class. Publish the policies and review them at a service delivery review. Also measure expedite frequency and the impact on standard lead time. If expedite demand is genuinely high, address capacity or intake rather than let every urgent ticket bypass the queue.

3. The monthly release checklist takes three days but is never shown on the board. Why does this matter, and how should it be handled?

Read the worked answer

It matters because the checklist consumes real capacity that is invisible to the board and to the WIP limits. If agents do three days of release work while their ticket WIP stays unchanged, actual WIP is higher than measured, lead time is understated, and the team will be blamed for low throughput caused by hidden work. Hidden work also undermines improvement because the cumulative flow diagram and control chart cannot explain the delay. The fix is to make the checklist a visible work item type on the board, with its own policy, estimate and place in the workflow, and to include it in WIP accounting. If it is a recurring batch, plan it as a cadence item with reserved capacity, or break it into smaller routine checks that flow with releases. Do not treat it as overhead exempt from limits. Review whether the checklist can be reduced or automated. The test is whether a new agent can see all the work that consumes the team's time, not just customer tickets.