EXIN LSSA Six Sigma Green Belt · Put your knowledge to work in context.

This independent study page provides practice for EXIN LSSA Six Sigma Green Belt. Its editorial learning areas include Define; Measure; Analyze; Improve and Control. The questions develop subject knowledge and application through worked reasoning, distinctions between competing answers, and practical scenarios. Study the relevant guide before attempting a mixed set, then explain the evidence or calculation that supports each answer. Topics on this exam: Define, Measure, Analyze, and Improve and Control. The EXIN LSSA Six Sigma Green Belt case studies are 4 cases and about 2,845 words.

1

A Warehouse Charter That Blames the Process and Misses the Customer

Northline Distribution's main warehouse ships about 9,000 orders per month. The VP of Operations chartered a project to reduce late shipments from 14% to 3% within six months. The charter lists the team as the warehouse supervisor, a picking lead, and a Black Belt; it excludes IT, carrier management, and customer service. The problem statement says warehouse picks are slow and inaccurate and the goal says improve on-time shipping.

745 words, about 4 min
2

A Supplier Conclusion Confounded by Reactor, Season, and Temperature

A specialty chemical reactor produces a batch yield averaging 82%. The team compared two raw-material suppliers: 14 batches from supplier A averaged 84.1% and 12 from supplier B averaged 80.6%; a two-sample t-test gave p = 0.03. The team concluded supplier A is superior and proposed switching. A reviewer notices that supplier A batches were run mostly in Reactor 2 during summer, while supplier B batches were run in Reactor 1 during winter.

656 words, about 3 min
3

A Pilot Improvement That Regressed After Rollout

A printed-circuit-board assembly line reduced solder defects from 4,200 ppm to 900 ppm during a three-week pilot using a new stencil aperture design and a revised reflow profile. After rollout to all three shifts, defects rose to 3,100 ppm within six weeks. There is no control plan; the stencil is cleaned when operators remember; the reflow recipe is stored on a local PC and was edited twice by a technician; new operators received a five-minute verbal briefing. An X-bar-R chart was set up using pilot data with control limits calculated from the pilot, but the chart is reviewed only when a customer complains.

679 words, about 3 min
4

Rebaselining Picking Errors in a Distribution Center

The regional distribution center ships about 9,200 order lines a week across three shifts, with four pickers per shift. Packing reports a 1.8% picking error rate, up from 0.9% six months ago, and customer complaints have risen from 22 to 41 a month. The error log is kept by packing staff and records only defects caught before shipment; it has free-text entries such as 'wrong item', 'short', 'damaged' and 'missing', with no picker ID or shift. Pick lists are paper, and pickers batch 12 orders at a time across four aisles.

765 words, about 4 min