This domain ties the roof to the permit, the drawing, and the worker. Florida roofing work requires permits and inspections, and products must have Florida Product Approval. In the High-Velocity Hurricane Zone (HVHZ), Miami-Dade and Broward counties, additional product approval rules apply. Wind-uplift design uses zone diagrams: corners and edges have higher uplift than field areas, so fastener patterns change near edges.
Plan reading requires scale, symbols, and details. Know how to read a roof plan, slope arrows, drainage, expansion joints, and flashing details. A section cut shows layers; a detail shows how materials terminate.
Safety is heavily tested. OSHA construction fall protection generally triggers at 6 feet. Guardrails, personal fall-arrest systems, and safe ladder practices are required. Extension ladders must extend at least 3 feet above the landing. Roofers also face heat illness, nail-gun injuries, and electrical hazards from overhead lines.
Trap: assuming HVHZ rules apply statewide or that a product approval from another state is enough.
Worked example: Plan scale is 1/4 inch = 1 foot. A roof detail measuring 3 inches on the drawing represents 12 feet in the field, because 3 / 0.25 = 12.