GA General Contractor study materials
GA General Contractor study resources

GA General Contractor study plan

GA General Contractor · Give each week a clear focus.

8 weeks · About 7 hours per week

Week 1

Project Management, Supervision, and Contract Administration

  • Diagram the project delivery methods (design-bid-build, design-build, CM at risk) and match each to its typical risk allocation and contract type

  • Sequence the change-order workflow from field discovery through pricing, negotiation, written approval, and cost/schedule incorporation

  • Write out the lifecycle of a submittal and an RFI, including who originates, reviews, and closes each, and the schedule impact of a late return

  • Distinguish substantial completion, beneficial occupancy, final completion, and warranty start, and list the punch-list steps between them

Your checkpoint

A 2-page contract administration playbook containing one flowchart per process (change order, submittal, RFI, payment application) plus a 20-term glossary written in your own words

Week 2

Project Management, Supervision, and Contract Administration & Safety, Building Codes, and Georgia Regulatory Requirements

  • Build a schedule logic diagram for a small commercial project showing critical path, float, and two activity sequences that would compress the schedule

  • Reconstruct the monthly pay-application and retainage process, including lien-waiver types exchanged at each step

  • Sort the OSHA Focus Four hazards into a table of recognition cues, required controls, and the training or documentation each demands

  • Outline Georgia's contractor licensing categories, the state licensing board's role, and how licensing, permitting, and local inspections intersect on a job

Your checkpoint

A 30-question self-written quiz covering Domain 1 and Domain 12 with an answer key; score at least 80% on a closed-book attempt

Week 3

Safety, Building Codes, and Georgia Regulatory Requirements & Carpentry, Wood Framing, and Rough Framing

  • Assemble the permit-to-inspection sequence for a typical commercial build, naming the inspection gate at each phase of work

  • Summarize Georgia mechanics' lien notice and filing requirements from the statute's plain language, listing each party's deadline relative to the others

  • Draw the fall-protection, excavation, and scaffold control requirements that most often appear on a site safety plan

  • Map wood framing members from foundation to ridge, naming the load path and the purpose of each connector in the chain

  • Calculate stud, joist, rafter, and sheathing quantities from a simple given floor plan using standard spacing

Your checkpoint

A one-page site safety and inspection checklist plus a worked framing takeoff sheet with quantities shown for studs, joists, and sheathing

Week 4

Carpentry, Wood Framing, and Rough Framing & Concrete and Reinforcing

  • Explain how framing spacing, blocking, and sheathing orientation control wall and floor stiffness, and identify the three most common field errors in each

  • Describe the fire-blocking and draft-stopping locations required in concealed wood construction

  • Sequence formwork, reinforcement placement, and concrete placement for a slab-on-grade and an elevated slab, naming the hold points inspected at each

  • Match concrete mix parameters (water-cement ratio, air content, slump, admixture) to exposure conditions and finishing needs

  • Locate reinforcing steel requirements: cover by exposure, lap splice basics, and where chairs and supports are mandatory

Your checkpoint

A one-page framing and concrete inspection card listing hold points, tolerances, and the test or observation required at each, plus a 10-question concrete mix design drill

Week 5

Concrete and Reinforcing & Sitework, Earthwork, and Site Utilities

  • Describe curing and protection methods by season and state the consequence of early loading or premature form removal

  • Walk through a concrete cylinder sampling and testing program: who samples, how often, and what happens when results fall short

  • Sequence a sitework package from clearing and grubbing through rough grading, utility installation, and finish grading

  • Match soil classification and compaction testing methods to the fill and subgrade conditions they are appropriate for

  • Trace a storm and sanitary utility run: pipe bedding, slope, testing, and backfill requirements in order

Your checkpoint

A sitework and concrete quality-control matrix (activity, inspection or test, responsible party, acceptance criterion) covering at least 12 line items

Week 6

Sitework, Earthwork, and Site Utilities & Finishes (Drywall, Flooring, Painting, and Coatings)

  • Explain how grading, drainage slope, and subsurface drainage keep water away from the structure, and identify the design elements that most often fail in the field

  • Compare drywall finishing levels and match each level to the space and finish it serves

  • Sequence gypsum board installation from framing inspection through taping, finishing, and priming, naming the defects checked at each stage

  • Classify flooring systems (hard, resilient, carpet, tile) by substrate preparation, moisture testing, and installation tolerance

  • Translate a coating spec into surface preparation, primer, and coat schedule requirements, and explain how environmental conditions govern application

Your checkpoint

A finishes sequence-and-inspection timeline for one room type, plus a substrate moisture-testing summary sheet for three flooring systems

Week 7

Masonry & Structural Steel and Metals & Roofing and Waterproofing

  • Detail masonry wall components - flashing, weep holes, movement joints, anchors - and where each must appear in a cavity wall section

  • Describe mortar and grout proportioning, and the field conditions that govern masonry placement temperature and protection

  • Trace structural steel from shop drawing approval through fabrication, erection, bolting/welding, and inspection, naming the inspection at each step

  • Identify the fireproofing, connection, and tolerance items most frequently cited on steel inspections

  • Compare low-slope roof systems by membrane type, insulation attachment, and flashing detail, and list the correct application sequence for each

Your checkpoint

Three drawn wall/section sketches (cavity wall, steel connection, roof edge flashing) each annotated with at least six required components and their installation order

Week 8

Thermal and Moisture Protection & Doors, Windows, and Glazing & Specialties, Equipment, and Furnishings & Project Management, Supervision, and Contract Administration

  • Sequence the waterproofing, insulation, and air-barrier layers of a building envelope and identify the continuity points where each system most often fails

  • Explain door and window installation from rough opening through flashing, shimming, and sealant, and state the tests used to verify performance

  • Match specialty and equipment items to the coordination tasks they create for structure, power, and rough-in

  • Re-run missed questions from every earlier week's deliverable and convert each into a one-line rule you can recall without notes

  • Complete a timed 60-question mixed-domain practice set under exam pacing

Your checkpoint

A single-page 'final week' recall sheet of your top 25 self-identified weak points with the correct rule beside each, plus a timed practice score of 75% or better

Milestones

Week 2: Close the book on Domain 1: without notes, draw the change-order workflow and name every party who touches it, then pass your own 30-question quiz at 80%

Week 4: Complete the two heaviest domains (1 and 12) and wood framing: score 80%+ on a self-written 40-question set drawn only from those three domains

Week 6: All 12 domains have at least one revisitable one-page summary; sitework, concrete, and finishes inspection matrices are complete and internally consistent

Week 8: Timed mixed-domain practice at 75% or better, and the 25-item weak-point recall sheet is written and re-tested twice with no repeated misses