HK Grade B Electrical Worker Exam study plan
HK Grade B Electrical Worker Exam · Give each week a clear focus.
8 weeks · About 6 hours per week
Wiring Systems, Cables, Conductors and Installation Methods & Electrical Safety, Statutory Requirements and Codes of Practice
Classify the common Hong Kong wiring systems (surface conduit, concealed conduit, trunking, cable tray, MICC, armoured, flexible cord) and state where each is permitted or restricted under the Wiring Regulations (BS 7671 as applied in HK) and the Electricity Ordinance (Cap. 406) and its subsidiary regulations
Calculate current-carrying capacity for a given cable size, installation method (enclosed in conduit in thermally insulating wall, clipped direct, on tray, buried), ambient temperature and grouping, applying correction factors Ca, Cg, Ci and Ci
Determine the minimum cross-sectional area of earthing and protective conductors from the phase conductor size using the tabulated rule and verify with the adiabatic equation for a stated fault current and disconnection time
Distinguish the statutory duties of the registered electrical worker (Grade B) from the contractor's duties under the Electricity (Wiring) Regulations, including who may design, install, inspect, test and certify
Produce a one-page decision flowchart from load current to final selected cable size, showing every correction factor applied in order
Your checkpoint
A worked cable-sizing calculation for three different circuits (lighting, socket outlet ring, fixed 3-phase motor) showing tabulated values, correction factors, voltage drop check and selected CPC size, plus the completed flowchart.
Wiring Systems, Cables, Conductors and Installation Methods & Supply Systems, Earthing and Protective Conductors
Select wiring enclosures and support methods for a given environment (corrosive, damp, high-temperature, exposed to mechanical damage) and justify the choice against the relevant code requirements
Explain the TN-S, TN-C-S and TT supply arrangements as found in Hong Kong installations and identify the earthing arrangement from a described supply intake
Size main protective bonding conductors for water, gas and structural metalwork and state the locations where bonding is mandatory versus supplementary
Describe the requirements for earthing the consumer's installation, including earth electrode resistance expectations for TT systems and the role of the residual current device
Calculate voltage drop for a single-phase and a three-phase circuit and confirm compliance with the 3% lighting and 5% other-uses limits used in design
Your checkpoint
An earthing and bonding schedule for a small commercial unit: supply arrangement identified, main earthing conductor and bonding conductor sizes stated with justification, and voltage drop verified for the two longest circuits.
Final Circuits, Demand Assessment and Installation Design & Protective Devices, Switchgear and Controlgear
Design final circuits for lighting, socket outlets (ring and radial), immersion heater, cooker and air-conditioner loads, choosing protective device type and rating to protect the cable and the load
Assess maximum demand for a dwelling and a small shop using diversity allowances, and produce a load schedule with connected load, diversity factor and design current
Select MCB, MCCB, RCBO and fuse types by tripping characteristic and explain discrimination between upstream and downstream devices
State the requirements for RCD protection (30 mA for socket outlets and locations with increased shock risk), and explain the difference between RCD, RCBO and isolated RCBO arrangements
Verify that protective conductor disconnection times are met for a 220 V single-phase and 380 V three-phase final circuit using the relevant maximum earth fault loop impedance values
Your checkpoint
A complete design package for a two-bedroom flat: load schedule with diversity, final circuit schedule (circuit number, cable, protective device, RCD provision, Zs limit, calculated Zs) and a discrimination note.
Inspection, Testing, Certification and Fault Diagnosis & Electrical Safety, Statutory Requirements and Codes of Practice
Sequence the inspection and testing process: visual inspection, continuity of protective and bonding conductors, ring final circuit continuity, insulation resistance, polarity, earth electrode resistance, earth fault loop impedance, RCD operation and functional testing
State the test instrument, expected reading and pass criterion for each of the tests above on a 220 V single-phase installation
Interpret insulation resistance results and explain why a reading below 1 megohm requires investigation before energisation
Identify the certificates and reports required under the Electricity (Wiring) Regulations and explain the role of the Work Completion Certificate and periodic inspection
Diagnose five typical faults (open circuit CPC, reversed polarity, high Zs, nuisance RCD tripping, borrowed neutral) from given test readings and state the remedy
Your checkpoint
A completed test record sheet for a simulated installation with all readings entered, pass/fail judgement for each, and a written fault report for two deliberately failing circuits.
Electrical Science and Principles (circuit theory, AC/DC, magnetism, power factor) & Electrical Equipment, Motors, Transformers and Control Systems
Solve DC and single-phase AC series-parallel circuits for current, voltage, impedance, phase angle and power, including power factor correction by capacitor
Explain the operation of a three-phase induction motor, including slip, synchronous speed, star-delta starting and direct-on-line starting, and select a starter for a given load
Describe the protective functions for motors: overload relay, short-circuit protection, phase failure and undervoltage, and set an overload relay from nameplate full-load current
Explain transformer principles, turns ratio, losses and the reason for isolating transformers in special locations
Read and explain a simple motor control circuit with start, stop, emergency stop, contactor and interlock, and trace the circuit to identify why the motor will not start
Your checkpoint
A calculation and explanation sheet covering one power-factor correction problem, one motor starting selection with justification, and a labelled control circuit diagram with a fault-finding table for three failure symptoms.
Special Installations and Locations (bathrooms, construction sites, hazardous areas) & Protective Devices, Switchgear and Controlgear
Apply the zone rules for bathrooms (zones 0, 1, 2 and outside zones) and state permitted equipment IP ratings and the supplementary bonding requirements
State the requirements for construction site installations: reduced voltage for hand-held tools, RCD protection, isolation and the inspection regime for temporary supplies
Classify a hazardous area by zone and gas group and select equipment by explosion protection concept (flameproof, increased safety, intrinsic safety) appropriate to the zone
Specify protection and isolation requirements for swimming pools, saunas and agricultural locations where water and livestock increase risk
Explain the role of emergency lighting, fire alarm supply and escape route circuits in special locations and the requirement for independent isolation
Your checkpoint
A zone diagram for a bathroom drawn from a described layout, with each item of equipment placed in its zone, IP rating and supply protection stated, plus a one-page specification for a temporary construction site supply.
Electrical Safety, Statutory Requirements and Codes of Practice & Inspection, Testing, Certification and Fault Diagnosis & Final Circuits, Demand Assessment and Installation Design
Consolidate the statutory framework: Electricity Ordinance, Electricity (Wiring) Regulations, Electricity (Registration) Regulations and the Code of Practice for the Electricity (Wiring) Regulations, and state which document governs which activity
Re-derive the key design checks (cable capacity, voltage drop, disconnection time, RCD selection) from memory using the tabulated data
Work through timed mixed calculation sets combining demand assessment, cable sizing and earth fault loop impedance
Review inspection and testing procedures and practise writing a defect report in the style expected by an examiner
Identify your three weakest topics from practice results and build a targeted revision list for week 8
Your checkpoint
A timed 60-question mock paper completed under exam conditions with a scored review sheet, plus a written defect report for one simulated installation and a prioritised weak-topic list.
Electrical Safety, Statutory Requirements and Codes of Practice & Supply Systems, Earthing and Protective Conductors & Inspection, Testing, Certification and Fault Diagnosis
Review the full syllabus against a checklist and confirm every domain has been covered at least once with worked examples
Re-test the weak topics identified in week 7 and confirm improvement with a second timed mock
Practise explaining statutory and earthing answers aloud in short structured form (requirement, reference, application) to build exam recall
Rehearse the calculation set that most often loses marks: correction factors, voltage drop, Zs and RCD disconnection time
Finalise an exam-day plan covering time allocation per section and the order in which to attempt questions
Your checkpoint
Final mock score above your week 7 score, a completed syllabus checklist signed off, and a one-page exam-day strategy sheet.
Milestones
Week 2: Can size a cable end to end with correction factors and voltage drop, and correctly identify the supply earthing arrangement and bonding sizes for a described intake, without notes.
Week 4: Can list the inspection and testing sequence in order, state the instrument and pass criterion for each test, and correctly diagnose at least four of five given fault scenarios.
Week 6: Can place bathroom equipment into the correct zone with IP rating and protection, and state the construction site reduced-voltage and RCD requirements from memory.
Week 7: Timed mock completed with a score recorded and a written weak-topic list of no more than five items.
Week 8: Second timed mock score improved over week 7, syllabus checklist complete, and all weak topics re-tested with correct answers.