Mistake 1

Treating the loadshifting machine's rated capacity as the safe working load for every attachment and configuration, and quoting the bare rated figure when asked for the permitted load.

Candidates memorise the headline capacity plate figure and do not connect it to derating for attachment weight, boom/jib length, radius or outrigger spread, so they answer with the maximum number rather than the configuration-specific limit.

What to do instead

Practise reading a capacity/rating chart as a worked exercise: subtract attachment and rigging weight, then read the value at the actual radius and configuration. In answers, state the limiting condition (radius, boom angle, outrigger set) alongside the number, and say explicitly that the plate rating is not the permitted load in every setup.

Mistake 2

Describing the pre-use inspection as a visual walk-around only, omitting function checks of limits, alarms, interlocks and brakes before the shift starts.

Candidates conflate the daily pre-start check with a quick look for damage, because inspection checklists are often memorised as a list of components rather than a sequence of tests.

What to do instead

Learn the check as three stages: static visual (structure, wire ropes, tyres/tracks, leaks, guards), then fluid/level checks, then functional tests (travel, hoist, slew, limit switches, emergency stop, horn/alarm, brakes) with the machine unloaded. In exam answers, name at least two functional tests and state that defects are logged and the machine is tagged out until cleared.

Mistake 3

Planning a lift or travel route without a documented risk assessment, and answering scenario questions by jumping straight to the manoeuvre.

Under time pressure candidates treat planning questions as operational questions and describe the lift itself, missing the marks allocated to hazard identification, exclusion zones and permit/authorisation steps.

What to do instead

Use a fixed planning skeleton for every scenario: task and load details, site survey (ground bearing, slope, overhead lines, blind spots, pedestrians), hazard controls, communication method, emergency plan, authorisation. Write the plan first, then the manoeuvre, so the answer visibly covers planning before action.

Mistake 4

Rigging loads without verifying the sling angle effect, i.e. quoting the sling's vertical rated capacity when the legs are at an angle, or ignoring the added load from a multi-leg arrangement.

Sling tags show a single rating and candidates do not apply the angle factor or account for unequal leg loading, so the tension in each leg is underestimated.

What to do instead

Work through angle-factor examples until the pattern is automatic: leg tension rises as the included angle widens, and one leg can take most of the load if the centre of gravity is off-centre. In answers, state the included angle, the assumed load share per leg, and the derated sling capacity used.

Mistake 5

Ignoring ground conditions and outrigger/wheel loading when positioning the machine, assuming a hard-looking surface is adequate.

Candidates focus on the machine and the load and treat the ground as a given, forgetting that point loading under outriggers or pads can exceed the bearing capacity of asphalt, backfill or suspended slabs.

What to do instead

Build a habit of stating the ground check explicitly: identify the surface, check for voids, drains, backfill and slope, and specify spreader pads sized to the outrigger load. In scenario answers, mention verifying bearing capacity or obtaining confirmation before setting up, and re-checking after rain or excavation nearby.

Mistake 6

Answering signalling and communication questions with only 'use hand signals', without naming the designated signaller, the agreed code, or the rule that anyone can stop the operation.

Candidates reduce communication to a single phrase and miss the surrounding controls: one authorised signaller, radio channel discipline, blind-lift relays, and the emergency stop authority of any worker.

What to do instead

Memorise the communication hierarchy: agreed method before starting, one designated signaller (plus relay for blind lifts), standard signals, radio check and backup signal, and the universal stop signal available to anyone. In answers, name the method, the person, and the stop rule.

Mistake 7

Treating loadshifting operations near overhead power lines as safe based on visual distance, without stating the required exclusion distance or the procedure for de-energising/isolating.

Candidates underestimate how far electricity can arc and do not know that the control is a defined safe distance plus formal isolation, not a judgement call by the operator.

What to do instead

Learn the control sequence: identify and mark the line, determine the applicable safe clearance for the voltage, contact the utility for isolation or diversion if the clearance cannot be kept, use a spotter, and never rely on the machine's insulation. In answers, give the sequence and state that work stops if clearance cannot be assured.

Mistake 8

Skipping or misapplying the load chart when the machine is on a slope or in travel mode, and answering travel questions with the lifting capacity figure.

Candidates learn one set of ratings and do not distinguish lifting capacity, travel/transport capacity, and stability limits on gradients, so they quote the wrong table for the situation.

What to do instead

Separate the modes explicitly in revision: stationary lifting on outriggers, pick-and-carry, and travel unladen or with load. For each, note the governing limit (structural, stability, gradient, ground) and practise selecting the correct chart. In answers, name the mode before quoting any capacity.

Mistake 9

Describing an emergency or incident response as 'stop and report', without the immediate actions that prevent escalation: secure the load, isolate power, account for people, and preserve the scene.

Candidates compress emergency procedures into a closing sentence and lose marks for sequence, because they have not rehearsed the priority order under stress.

What to do instead

Learn a fixed emergency sequence: make safe (stop controls, lower/secure load, isolate energy), check for casualties and raise the alarm, account for personnel in the exclusion zone, then report and preserve evidence. Practise applying it to two or three scenarios (load drop, contact with a line, tip-over) so the order is automatic.

Mistake 10

Answering legislation and responsibility questions by describing what the operator does, rather than naming the duties of the employer, competent person and operator separately.

Candidates blur the roles and give a generic 'everyone must be safe' answer, missing that the exam tests who is responsible for what under the relevant safety legislation and codes.

What to do instead

Build a role matrix: employer duties (safe plant, training, supervision, risk assessment), competent person (inspection, thorough examination, planning), operator (pre-use checks, following the plan, stopping unsafe work). In answers, attribute each duty to the correct role and cite the principle rather than a vague shared responsibility.