HK SWP / Gondola Operator (CIC) study materials
HK SWP / Gondola Operator (CIC) study resources

HK SWP / Gondola Operator (CIC) cheat sheet

HK SWP / Gondola Operator (CIC) · Keep the key ideas within reach.

Quick reference

Statutory framework and safety responsibilities

  • Factories and Industrial Undertakings (Suspended Working Platforms) Regulation: applies to construction and industrial undertakings; requires SWP to be of good mechanical construction, sound material, adequate strength; properly maintained; examined by competent examiner before first use and at intervals not exceeding 6 months; and after substantial alteration or repair.

  • Construction Sites (Safety) Regulations: reg 38 requires SWP to be suspended from adequate anchorage; reg 39 requires competent person to inspect before use and at least once every 7 days; reg 40 requires report of examination in approved form.

  • Under F&IU(SWP) Reg, the contractor must ensure SWP is not used unless there is a valid certificate of examination (Form SWP1) and a report of inspection (Form SWP2) where required; certificate must be kept on site.

  • Competent examiner (CE) for SWP must be a person appointed by the contractor and registered with Labour Department; CE conducts statutory examinations every 6 months and after major alteration; competent person (CP) conducts weekly inspections.

  • Operator duties: use SWP only if trained and authorized; carry out pre-use checks; not exceed rated load; report defects; use fall protection; follow permit-to-work and safe system.

  • Contractor duties: provide safe SWP, ensure erection/dismantling by competent workers under supervision, maintain records, ensure CE examination and CP inspection, provide fall protection and rescue plan.

  • Labour Department Code of Practice for Suspended Working Platforms (SWP) gives practical guidance on design, erection, inspection, operation and maintenance; compliance is not mandatory but can be used as evidence.

  • Factories and Industrial Undertakings Ordinance (F&IUO) general duties: employer must ensure safety of employees; employee must take care of self and others; breaches can lead to prosecution and fines/imprisonment.

  • Construction Sites (Safety) Regulations reg 4: contractor must ensure all plant and equipment on site are safe and without risk to health; reg 5: employees must use safety equipment provided.

Quick reference

SWP types, configurations and terminology

  • Gondola / temporary suspended working platform (SWP): a suspended platform suspended by wire ropes from an overhead structure, used for work at height; typically has a cradle, hoist, safety device, and suspension ropes.

  • Single-point suspension: platform suspended from one suspension point; requires secondary safety rope and fall arrest; limited to light duty and specific configurations; stability depends on tie-back or counterweight.

  • Dual-point suspension: platform suspended from two independent suspension points; most common for facade work; each suspension point has its own suspension rope and safety rope.

  • Roof rig: the supporting structure on the roof consisting of beams, counterweights, outriggers, and tie-backs; must be structurally adequate and designed by engineer; counterweights must be securely fixed and marked with weight.

  • Parapet clamp: a device clamped to a parapet wall to provide anchorage for suspension ropes; must be designed for the load and inspected; not to be used on weak or fragile parapets.

  • Counterweight: weights used to counterbalance the roof rig; must be of adequate mass, fixed to prevent displacement, and never removed or substituted without authorisation; calculate required weight based on rig design.

  • Outrigger: a beam extending from the roof structure to support the suspension rope at a distance from the parapet; must be designed to take the load and be tied back to prevent overturning.

  • Tie-back: a rope or rod anchoring the roof rig to a structural element to prevent it from moving or overturning; must be independent of the suspension rope and designed for the load.

  • Cradle: the platform (basket) where workers stand; must have guardrails, toe boards, and floor; load rating plate must be displayed.

  • Suspension wire rope: the main rope supporting the platform; safety rope: independent rope for fall arrest, attached to a separate anchorage; fall arrest system: harness, lanyard, and safety rope.

Quick reference

Pre-use inspection and daily checks

  • Daily pre-use check by operator: check suspension ropes for broken wires, corrosion, kinks, wear, and correct termination; check safety ropes for damage and correct attachment; check rig for counterweights, tie-backs, and clamps.

  • Wire rope rejection criteria: if broken wires exceed limits (e.g., 6 randomly broken wires in one lay length for 6x19 rope; 10 for 6x37), or diameter reduction >10%, or severe corrosion, or kinks, the rope must be replaced.

  • Check hoist and brake: test hoist operation up and down; test brake by stopping and holding load; ensure no slippage; test emergency stop; check limiters (upper/lower) function.

  • Electrical: check power supply cable, RCD (trip test), control pendant, emergency stop, and isolator; ensure no exposed wires; check earth connection.

  • Platform: check guardrails (top rail, mid rail), toe boards, floor condition, nameplate with rated load and number of persons; ensure no unauthorized modifications.

  • Anchorage: verify roof rig is secure, counterweights are in place and fixed, tie-backs are tight, parapet clamps are tight; check structural adequacy of supporting structure.

  • Record: daily pre-use checklist must be completed and signed; defects must be reported and equipment tagged out; do not use defective SWP.

Quick reference

Erection, alteration, dismantling and commissioning

  • Erection/dismantling must be carried out by competent workers under supervision of a competent person, following manufacturer's instructions and design drawings; use fall protection and exclusion zone.

  • Roof rig installation: ensure supporting structure (roof slab, beams) can take the loads; use spreader beams if needed; counterweights must be fixed and marked; tie-backs to structural elements; outriggers secured.

  • Anchorage and tie-back: each suspension point must have independent safety rope anchorage; tie-backs must be designed by engineer and installed to prevent overturning; never use scaffolding or temporary structures as anchorage without engineer approval.

  • Testing and commissioning before first use: static and dynamic tests as per manufacturer; check hoist, brake, safety device (overspeed, slack rope), limiters, electrical systems; verify load rating; record results.

  • Statutory examination by competent examiner (CE) before first use and after substantial alteration; CE issues certificate (Form SWP1) and report; equipment cannot be used until certificate is issued.

  • After alteration (e.g., change of suspension height, change of rig configuration), re-examination by CE is required; also re-testing and re-commissioning.

  • Commissioning includes: load test at rated load and 125% static test (if required), function test of safety devices, and verification of stability.

Quick reference

Safe operation and load control

  • Rated load: never exceed the rated load (kg) or number of persons marked on nameplate; distribute load evenly; avoid concentrated loads; do not use as storage.

  • Load distribution: keep load within platform boundaries; secure tools and materials; do not lean over guardrails; do not use ladders or steps on platform to gain extra height.

  • Stability: ensure platform is level; do not move platform with workers on board unless designed for travel; avoid swinging; use guide ropes if provided.

  • Wind and weather limits: stop operation when wind speed exceeds manufacturer's limit (often 10 m/s or 20 knots) or when weather affects safety (heavy rain, typhoon); secure platform and rig before typhoon.

  • Keep clear of obstructions: maintain safe distance from power lines (minimum 3 m for low voltage, more for high voltage); avoid contact with building projections; use guide ropes to control.

  • Travelling and parking: when travelling, keep platform balanced; park platform at designated safe location, isolate power, and secure against unauthorized use.

  • Communication and signalling: use clear communication (radio or hand signals) between operator and roof person; one signalman; emergency stop signal must be known.

  • Exclusion zones below: barricade area below SWP to prevent falling objects; use toe boards and tool lanyards; never allow persons below unless protected.

Quick reference

Fall protection and rescue

  • Independent safety rope: each person must attach to a separate safety rope (not the suspension rope) using a fall arrest lanyard and harness; safety rope anchored independently to a structural anchorage.

  • Harness inspection and fitting: check harness for cuts, fraying, broken stitches, corrosion; fit snugly, adjust all straps, ensure leg straps and chest strap are secure; attach lanyard to designated D-ring.

  • Anchorage points: must be capable of withstanding 10 kN (or as per design) per person; independent of suspension rope; never attach to guardrails or hoist.

  • Self-rescue and assisted rescue: operator should be trained in self-rescue (e.g., using rescue kit); assisted rescue by trained personnel; rescue plan must be in place before work.

  • Emergency lowering: if hoist fails, use emergency lowering device (manual descent) as per manufacturer; ensure trained and practiced.

  • Suspension trauma awareness: after a fall, person may be suspended in harness; suspension trauma can occur within 10-20 minutes; rescue quickly, keep legs moving, use relief straps if available.

Quick reference

Electrical, mechanical and control systems

  • Power supply: use dedicated supply with RCD (30 mA) protection; check RCD trip test before use; ensure cables are protected from damage; use industrial plugs and sockets.

  • Isolation: isolate power before maintenance; use lockout/tagout; ensure emergency stop and isolator are clearly marked and accessible.

  • Control pendant: check for damage, function of all buttons, emergency stop; pendant cable must be protected; do not use if damaged.

  • Hoist motor and brake: test hoist and brake daily; brake must hold rated load; check for wear; if brake slips, stop use and report.

  • Overspeed and slack-rope devices: safety device must be tested (e.g., by lifting platform slightly and checking slack rope device); overspeed device must function; do not bypass.

  • Tilt and overload limiters: if fitted, test function; do not exceed rated load; tilt limiter stops platform if excessive tilt.

  • Alarms and interlocks: check alarms (e.g., overload alarm) and interlocks (e.g., gate interlock) function; never disable.

Quick reference

Incident, defect and emergency response

  • Reporting defects and near misses: report immediately to supervisor; record in logbook; near misses must be reported and investigated; defective equipment tagged out.

  • Dealing with power failure: stop work, secure platform, use emergency lowering if needed; do not attempt to repair unless trained; inform supervisor.

  • Jammed platform: do not force; use manual lowering or rescue; call for assistance; keep calm; use communication.

  • Rope damage: if suspension rope damaged, stop use immediately; do not attempt to continue; evacuate platform safely; report.

  • Fire: use fire extinguisher if safe; evacuate; raise alarm; follow site emergency plan.

  • Typhoon and rainstorm procedures: secure SWP and rig before typhoon signal No. 8 or black rainstorm; lower platform to safe position, tie down, isolate power; after typhoon, inspect before use.

  • Evacuation: know evacuation route; use rescue equipment; do not jump; wait for rescue.

  • Statutory notification: report serious accidents to Labour Department and other authorities as required; preserve scene.

Quick reference

Maintenance, record keeping and documentation

  • Log books: keep daily inspection log, maintenance log, and defect log; records must be kept on site and available for inspection.

  • Inspection and examination certificates: keep CE certificate (Form SWP1) and CP inspection report (Form SWP2) on site; valid for 6 months for CE, 7 days for CP.

  • Maintenance schedule: follow manufacturer's maintenance schedule; routine maintenance (e.g., lubrication, brake adjustment) by competent person; major maintenance by specialist.

  • Competent examiner certificates: CE must be registered; certificate must state SWP is safe to use; keep records for at least 2 years (or as required).

  • Records retention: keep records of inspection, maintenance, repair, and examination for at least 2 years; available for inspection by authorities.

  • Tagging out of defective equipment: use lockout/tagout; tag with 'DO NOT USE' and report; do not remove tag until repaired and re-examined.