HK SWP / Gondola Operator (CIC): Erection, alteration, dismantling and commissioning

HK SWP / Gondola Operator (CIC) · Work through your exam, one topic at a time.

All guide sections

Erection, alteration, dismantling and commissioning

Domain 4 covers the highest-risk phase: putting the rig up, changing it, taking it down, and proving it is fit before first use.

Erection

  • Erection, alteration and dismantling are done by trained riggers under the supervision of a competent person, following the manufacturer's instructions and the rigging plan.
  • Supporting structure: confirm the roof slab, beam or parapet can carry the outrigger reactions. Unusual or heavy rigs need an engineer's check; spreader beams distribute point loads.
  • Anchors and tie-backs: anchor to structural elements or approved cast-in anchors - never to parapets, handrails, pipes, ductwork or air-conditioning units.
  • Counterweights: the calculated mass, purpose-made, fixed so they cannot be displaced, and marked.
  • Ropes: correct diameter and length, correct reeving, terminations to specification, ropes free of twists; safety ropes anchored separately.

Alteration

Any change to overhang, back-span, counterweight, anchor position, rope length or platform configuration changes the loads. It requires re-inspection and, before use, re-examination and re-testing. A certificate issued for the old configuration does not cover the new one.

Commissioning before first use

  • Function test of hoists, brakes, emergency stop, limiters and alarms.
  • Load test to the specified proof load (commonly 1.25 times the rated load, per the Code or manufacturer).
  • Examination by a competent examiner and issue of the certificate.
  • Only then are persons carried.

Dismantling

Lower the platform to a safe level, isolate and lock off the power, slacken and remove ropes in a controlled way, and dismantle the rig with the same supervision. Secure the roof edge and prevent falls throughout.

Worked example

A team extends an outrigger overhang by 500 mm to clear a new fin. The counterweight no longer balances the increased moment, roof reactions rise, and the suspension rope may rub the fin. The rig must be recalculated, re-rigged, inspected, examined and load-tested before use - extending the beam and reusing the old certificate is a serious breach.

Traps

  • Anchoring tie-backs to the parapet.
  • Using loose weights as counterweights.
  • Commissioning by function test only, with no load test.
  • Reusing a certificate after alteration.
  • Letting the platform carry persons during setting-up.