IAI CP1 study materials
IAI CP1 study resources

IAI CP1 cheat sheet

IAI CP1 · Keep the key ideas within reach.

Quick reference

Actuarial Practice / Core Technical Application (CP1)

  • Present value: PV = sum over t of CF_t * v^t, where v = 1/(1+i); for continuous discounting v^t = exp(-delta*t) with delta = ln(1+i).

  • Level annuity-immediate a_n = (1 - v^n)/i; annuity-due a-double-dot_n = (1 - v^n)/d with d = i/(1+i); increasing annuity (Ia)_n = (a-double-dot_n - n*v^n)/i.

  • Net present value decision rule: accept a project when NPV > 0 at the risk-adjusted discount rate; between mutually exclusive projects choose the higher NPV, not the higher IRR.

  • IRR is the rate r solving NPV(r) = 0; it is unreliable when cash flows change sign more than once (multiple roots) or when comparing projects of different scale or duration.

  • Equation of value: accumulate or discount all cash flows to a common date and set inflows equal to outflows; the solution rate is the yield. Use linear interpolation only as an approximation between two bracketing rates.

  • Expected present value of a life contingent benefit: EPV = sum over t of (benefit_t) * v^t * (probability of payment at t), with probabilities taken from the appropriate decrement table.

  • Premium principle: equivalence principle sets the premium so that EPV of premiums equals EPV of benefits plus expenses, i.e. EPV(premiums) - EPV(benefits) - EPV(expenses) = 0.

  • Reserve (net premium reserve) at duration t: prospective reserve = EPV(future benefits) - EPV(future net premiums); it equals the retrospective accumulated value of past premiums less past claims costs.

  • Profit signature: model cash flows per policy in force at outset, multiply by the expected in-force probability each year, then discount at the risk discount rate to obtain the NPV of the contract.

Quick reference

Actuarial Practice / Core Technical Application (CP1)

  • Thiele's differential equation for a policy with state-dependent reserve V: dV/dt = delta*V + P - b - (S - V)*mu, where b is the benefit outflow rate and S the sum at risk on death.

  • Survival model: mu_x is the force of mortality; tPx = exp(-integral from 0 to t of mu_{x+s} ds); the probability of death in year t is (tPx)*q_{x+t}.

  • Under the uniform distribution of deaths assumption, force of mortality in year of age x is mu_{x+t} = q_x / (1 - tq_x), and l_{x+t} = l_x(1 - t*q_x).

  • Constant force of mortality mu over a year gives q = 1 - exp(-mu) and tP = exp(-mu*t); this assumption is convenient for fractional ages in multi-decrement work.

  • Multiple decrement: independent rates q' relate to dependent rates q by q^(j) = integral over the year of tP^(tau) * mu^(j)_{x+t} dt; with constant forces, q^(j) = (mu^(j)/mu^(tau))*(1 - exp(-mu^(tau))).

  • Select mortality: rates depend on duration since underwriting, so q_[x]+t < q_{x+t} for early durations; select period is typically shown before the ultimate table is entered.

  • Expected cash flow in a unit-linked contract separates the non-unit reserve (expenses less charges) from the unit fund; the unit reserve equals the bid value of units allocated to the policyholder.

  • Asset-liability matching: immunise by matching present value, duration and convexity of assets and liabilities; Redington immunisation requires PV(A) = PV(L), duration(A) = duration(L) and convexity(A) >= convexity(L).

  • Risk classification decision rule: a factor is worth using when the reduction in adverse selection cost exceeds the cost of underwriting and the regulatory or fairness constraints on its use.

Quick reference

Actuarial Practice / Core Technical Application (CP1)

  • Capital requirement logic: required capital covers the risk that assets fall short of liabilities at a chosen confidence level over a chosen horizon; SCR-type measures use a 1-in-200 annual shock, economic capital uses the firm's own target.

  • Free surplus = assets - liabilities - required capital; distributable earnings change each year by investment return plus releases less new capital and tax.

  • Profit test output: NPV at the risk discount rate, the internal rate of return of the profit signature, and the break-even year when cumulative discounted profit first becomes positive.

  • Risk discount rate reflects the shareholders' required return; raising it reduces NPV and can change the ranking of products, so it must be set consistently with the risks being modelled.

  • Sensitivity analysis varies one assumption at a time (mortality, lapse, expenses, interest) and reports the change in NPV; scenario testing varies several assumptions together, and stochastic modelling generates a distribution of outcomes.

  • Experience analysis compares actual against expected claims, lapses and expenses; the ratio actual/expected (A/E ratio) drives the assumption review, with credibility weighting for small volumes.

  • Profit emergence is front-loaded by acquisition expenses and reserves; new business strain equals the capital needed to write the business and is recovered as the block runs off.

  • Embedded value = net assets plus value of in-force business, where value of in-force is the present value of future shareholder profits after allowing for required capital and the cost of holding it.

  • Reinsurance decision: quota share cedes a fixed proportion of premium and claims and reduces new business strain; excess of loss cedes claims above an attachment point and protects against large individual losses.

Quick reference

Actuarial Practice / Core Technical Application (CP1)

  • Professional judgement must be documented: state the assumptions chosen, the evidence and rationale, and the sensitivity of results to those assumptions, so another actuary could review the work.

  • When communicating results, lead with the decision-relevant conclusion, quantify uncertainty, and separate facts from judgement; avoid unexplained technical jargon for non-actuarial audiences.

  • Peer review and independent checking are expected controls; a model should be validated against simple hand calculations and its output reconciled to accounting or experience data.

  • Conflicts of interest must be disclosed and managed; where the actuary's own remuneration depends on the result, independent oversight or review is required.

  • Data quality: check completeness, accuracy, consistency and relevance; document any adjustments for missing or unreliable data and consider the effect on the results.

  • Model risk controls include version control, documented change logs, input and output checks, and periodic recalculation of a sample of policies by an independent method.

  • Regulatory reporting usually requires a best-estimate basis for reserves plus a prudential margin, and a separate demonstration that the firm holds adequate capital against adverse experience.

  • Ethical decision rule: if a course of action would not bear public explanation to clients, regulators and peers, it should not be adopted even where it is technically permitted.

Quick reference

Actuarial Practice / Core Technical Application (CP1)

  • Option pricing: for a non-dividend share, the Black-Scholes call value is SN(d1) - Kexp(-rT)N(d2), with d1 = (ln(S/K) + (r + 0.5sigma^2)T)/(sigmasqrt(T)) and d2 = d1 - sigmasqrt(T).

  • Put-call parity: C - P = S - K*exp(-rT); it holds for European options and provides a no-arbitrage check on any pricing model output.

  • Risk-neutral valuation: the price equals the discounted expectation of the payoff under the risk-neutral measure, so expected returns on the underlying equal the risk-free rate.

  • Binomial model: p = (exp(r*dt) - d)/(u - d) is the risk-neutral up-probability; price by backward induction, discounting each expected value one step at the risk-free rate.

  • Greeks: delta = dV/dS, gamma = d2V/dS2, vega = dV/dsigma, theta = dV/dt and rho = dV/dr; delta-hedging removes first-order price risk but leaves gamma and vega exposure.

  • Interest rate models: Vasicek and Hull-White are mean-reverting short-rate models with analytic bond prices; the Black model prices caps and swaptions using a lognormal forward rate.

  • Forward and futures prices: F = S*exp((r - q)T) for an asset with continuous yield q; for a futures contract, daily settlement changes the value but not the initial no-arbitrage price.

  • Duration and convexity: modified duration D = -(1/P)dP/dr, and the price change is approximately -Dchange in r + 0.5convexity(change in r)^2.

  • Stochastic models for equity returns: geometric Brownian motion gives lognormal prices with expected value S0exp(mut) and variance S0^2exp(2mut)(exp(sigma^2*t) - 1).