Fixed-Bid Rebuild With a Moving Scope

WP-C · Put your knowledge to work in context.

All case studies

Fixed-Bid Rebuild With a Moving Scope

A 14-person digital agency has a $180,000 fixed-bid contract to rebuild a membership association's website in six months. The signed scope covers a CMS migration, a member directory, and "up to three rounds of design revisions per template." In week 11, the client's new COO asks for a gated online community, single sign-on with the association management system, and a French-Canadian version. No change order has been raised. Design is still not signed off after four rounds, and the agency has consumed 30% of the budget and 45% of the schedule. The client's executive sponsor expects launch before the annual conference in four months and has begun copying the agency's CEO on emails. The delivery lead wants to absorb the work to protect the relationship; the finance director wants to stop work.

1. Would you absorb the new work or issue a change order? Justify the decision.

Read the worked answer

Issue a change order; do not absorb. Absorbing converts a scope problem into a margin, quality, and team-retention problem, and it teaches the client that late requests are free. The new COO's community, SSO, and French-Canadian version are new scope, not clarification of the signed scope, and the design has already exceeded the three-revision limit. Quantify the impact in days, dollars, and schedule before the conversation: community build, AMS integration, translation and locale QA, plus the design overrun.

Present three options rather than a single demand: (A) full added scope with a revised price and date; (B) a phase-one launch that covers the conference with community and SSO deferred; (C) added scope funded by descoping something the client values less. Escalate to the executive sponsor with a one-page impact statement. The finance director's stop-work position is a legitimate lever, but using it as a threat damages the relationship more than a transparent change order. Protect the relationship through options, documentation, and predictability, not through unpaid work.

2. How would you structure the change-control conversation with the COO and executive sponsor?

Read the worked answer

Prepare a scope baseline, a decision log, and an impact summary before the meeting. Show what was signed, what has been delivered, what has changed, and what the change costs in money and time. Separate relationship language from commercial language: affirm the goal of a successful conference launch, then ask the client to prioritize among community, SSO, French-Canadian, and the original scope. Do not negotiate line items in the room without a written follow-up.

Set a design sign-off gate with a firm date and explain the schedule consequence of missing it. Define "one round" as consolidated feedback from a named approver, not sequential comments from multiple stakeholders. Record decisions in a revised statement of work and require written approval before work starts. The reasoning is that ambiguity is the real cost driver: the agency cannot price or schedule requests that are verbally requested and informally absorbed. A structured conversation also protects the client's sponsor from surprise.

3. What would you recommend for the conference launch date?

Read the worked answer

Work backwards from the conference and test the date against the critical path, not against optimism. Identify the must-have launch scope: content migration, member directory, accessibility and QA, analytics, and redirects. Put community, SSO, and French-Canadian into a post-launch phase or a separate workstream, and state clearly which conference needs each item serves.

Offer a phased launch with a stable date and a reduced scope rather than compressing QA and accessibility. If the sponsor insists on the full scope by the conference, present the cost of acceleration: additional staff, parallel translation, and a higher defect risk, priced explicitly. Do not silently absorb schedule risk. The reasoning is that the launch date is a constraint, but scope, quality, and cost are also constraints; the professional move is to make the trade-off explicit and let the sponsor choose.