A 1.2 m × 0.9 m patch on a vertical wall of a 1970s water-retaining structure is 75 mm deep after unsound concrete removal. The wall is 400 mm thick and the patch is 1.5 m above the floor. Ambient temperature is 35°C, relative humidity 18%, and wind is 25 km/h; the surface is in direct sun. The specified repair mortar has a 25-minute working life and a 28-day compressive strength of 50 MPa. The contractor proposes to mix one full batch, hand-apply with a trowel, strike off flush, and cure with a spray-applied curing compound the next morning. The owner requires a 10-year service life and no visible cracking. The substrate will be prepared to saturated-surface-dry before placement. The wall must return to service after 48 hours.

1. Identify the risks in the contractor's plan and explain which are most likely to cause premature failure.

Read the worked answer

The plan has three high-risk elements. First, hot, dry, windy, sun-exposed conditions cause rapid evaporation and plastic shrinkage; a 25-minute working life means the mortar may stiffen before it is consolidated, leading to voids and poor bond. Second, hand-applying 75 mm on a vertical surface in one pass risks sagging, entrapped air, and incomplete filling; one full batch cannot be placed within the working life. Third, curing the next morning is too late; early moisture loss can crack the surface before curing begins, and a curing compound may interfere with bond if a coating is later applied. The most likely failure is cracking and edge debonding, not low 28-day strength.

2. Recommend a placement sequence and curing method.

Read the worked answer

Shade the wall and pre-cool the substrate if possible; place during cooler hours. Pre-wet to saturated-surface-dry with no standing water. Use small batches that can be placed within the working life. For 75 mm vertical depth, use formwork and pour in lifts, or apply a thixotropic repair mortar in lifts with mechanical compaction; do not hand-trowel a single 75 mm lift. Press material against the substrate to eliminate voids. Finish flush and immediately cover with wet burlap and plastic, or use a moist curing system; keep it continuously moist for at least 7 days. Monitor temperature and do not let the patch dry in sun or wind. If a coating is specified, confirm curing-compound compatibility.

3. What inspection and testing would you require before and after placement?

Read the worked answer

Before placement, verify substrate soundness, roughness, saturated-surface-dry condition, temperature, and bond performance on a mockup. During placement, record batches, working time, lift thickness, consolidation, and curing start time. After placement, tap all patches for voids; inspect for cracks, shrinkage, and edge debonding; measure profile and thickness; and run tensile bond tests by ASTM C1583 at the specified age, with failure in the substrate preferred. Because the wall returns to service in 48 hours, require strength verification at that age, not only 28-day data. Document with photographs and a signed checklist. If cracks appear, map them and determine whether they are plastic shrinkage or structural before accepting.