LOLER examination interval
Lifting equipment must receive a thorough examination before first use, after erection, after exceptional circumstances, and at intervals not exceeding six months.
PUWER 1998 scope
Work equipment must be suitable, maintained, inspected, and used only by competent persons; this applies to cranes regardless of ownership or hire.
Competent person definition
A person with the competence, training, and experience to carry out the specific task, such as thorough examination, as distinct from the appointed person who plans lifts.
RIDDOR reporting
Dangerous occurrences such as crane collapse or uncontrolled release of a load must be reported to the enforcing authority under the Reporting of Injuries, Diseases and Dangerous Occurrences Regulations.
Self-erect crane definition
A tower crane designed for rapid erection without a separate mobile crane, typically using a folding mast and jib and its own climbing or jacking mechanism.
Moment limiter function
A safety device that measures load moment and cuts out hoisting or derricking when rated capacity is exceeded, protecting the crane from overload.
Two-blocking
Contact between the hook block and the jib or trolley, prevented by the upper hoist limit switch; causes include operator error or limit switch failure.
Slew lock purpose
A device that prevents rotation of the upper structure; applied during erection, dismantling, climbing, and in certain out-of-service conditions per the manufacturer.
Ground bearing pressure
The pressure imposed by the crane's base or outriggers on the ground, which must be less than the soil's bearing capacity with an adequate factor of safety.
Zone of influence
The area around the crane, including buried services, drains, basements, and voids, that could be affected by the crane's loads and must be surveyed before siting.
Out-of-service condition
The defined configuration for a crane not in use, such as slew lock or free-to-slew, with the jib positioned to minimise wind area per the manufacturer.
Over-sail hazard
The risk of the jib or load passing over adjacent property, structures, or public areas outside the site boundary, requiring assessment and control.
Climbing frame
The crane's own mechanism used to jack the mast and insert new sections; climbing is a reduced-stability operation with strict wind and exclusion controls.
Erection method statement
A written, site-specific document describing the sequence, personnel, equipment, and controls for erecting or dismantling the crane, supervised by a competent person.
Post-erection examination
A thorough examination by a competent person required after erection or climbing and before the crane is returned to service.
Dismantling risk
Dismantling is statistically the higher-risk phase; it requires the same planning, supervision, and exclusion controls as erection, often in more constrained conditions.
Load moment formula
Load moment equals load multiplied by radius, including hook block and sling effects; the rated capacity must not be exceeded at any radius.
Gross load calculation
Gross load equals the net load plus lifting accessories plus hook block; lifting calculations must always use gross load, not the net weight.
Rated capacity curve
The relationship showing that rated capacity decreases as radius increases, specific to jib length, counterweight, and base configuration.
Wind load proportionality
Wind load on the load and jib increases with exposed area and with the square of wind speed; the chart's in-service wind limit must be respected.
Sling leg tension
For a two-leg sling, tension per leg equals half the load divided by the cosine of the angle from vertical; flatter angles increase leg tension.
SWL versus WLL
Safe working load and working load limit denote the maximum rated load for an accessory; the assembly rating is limited by its weakest component.
Tag line use
A rope attached to the load to control rotation and swing during lifting, keeping personnel clear of the load's path.
Hook safety latch
A spring-loaded device on the hook that prevents the sling or load from slipping off; it must be present and functional before use.
Designated signaller
The single person appointed to direct the lift by hand or radio signals; only this person gives signals, except anyone may give an emergency stop.
Emergency stop signal
A signal that any person may give at any time; the operator must stop immediately on receiving it or on loss of communication.
Radio communication test
Before a lift, the dedicated radio channel must be tested and a backup hand-signal method agreed in case communication fails.
Wire rope rejection criteria
Reject wire rope for excessive broken wires per lay length, corrosion, kinks, bird-caging, or damaged end terminations, per manufacturer criteria.
Brake test requirement
Hoist and slew brakes must be verified to hold the rated load, tested before each shift where practicable and after any adjustment.
Limit switch function test
Upper and lower hoist, trolley, and slew limit switches must be tested and operating correctly; the operator must never rely on stopping the load manually.
In-service wind limit
The maximum wind speed at which the crane may lift, specified by the manufacturer; lifting must stop and the crane put out-of-service when reached.
Emergency load lowering
A procedure to lower a suspended load safely if power fails, using the crane's emergency lowering system, briefed to the operator before operations.