Five Facilities Incidents Before a Noon Cut-Off

ie-df-recruit-aptitude · Put your knowledge to work in context.

All case studies

Five Facilities Incidents Before a Noon Cut-Off

You are the facilities coordinator for a 12-floor office building. It is 08:10 on Monday. You have one maintenance technician available until 12:00, a £500 discretionary budget, and no other technician until Tuesday. The overnight log contains five items. (1) Water is dripping from a ceiling tile above the floor-9 server room; a bucket is catching it and the stain has grown since Friday. (2) The floor-3 kitchen has no hot water; about 40 staff use it and the staff council has complained. (3) A lift contractor is in reception waiting to service lift 2; the permit needs your signature and the work takes three hours. (4) A meeting room on floor 6 has a flickering light; the room is booked for a 14:00 client presentation. (5) A cleaner reports a burning smell near a printer on floor 5 but cannot say which printer; the fire panel shows normal. Your manager is unreachable until 11:00.

1. Rank the five items for action in the next four hours and justify your top three.

Read the worked answer

Ranking for the next four hours:

  1. Burning smell, floor 5. Life safety outranks property and comfort. It is unconfirmed, but a burning smell with a normal panel can be a smouldering printer or wiring; it must be investigated now, not logged for later.
  2. Water above the floor-9 server room. Active water over critical equipment is a business-continuity and electrical risk. The bucket is a stopgap; the source must be found and the server room protected.
  3. Lift contractor permit. The contractor is idle and the job takes three hours; if not started by about 09:00 it will not finish before your technician leaves at 12:00. Sign the permit after a two-minute check of the method statement and isolation.
  4. Flickering light, floor 6: schedule before 14:00 because a client presentation is time-bound, but it is not an emergency.
  5. Hot water, floor 3: important for staff welfare, but no safety risk; provide a temporary notice and a kettle, and book the plumber.

The order changes only if the smell investigation finds smoke or flame; then evacuate and call the fire service, and the other items stop.

2. What should you do about the unconfirmed burning smell, given you cannot see it and the fire panel shows normal?

Read the worked answer

Treat it as real until disproved. Go to floor 5 with the technician, ask the cleaner to point to the area, and check each printer for heat, smell, discoloured casing or a paper jam. Power down suspect equipment at the socket, not just the standby button. Use a thermal camera if available; smell alone is a poor locator. Check the ceiling void and nearby sockets, because the cleaner may be smelling wiring rather than a printer.

If the smell is traceable to a printer and stops when it is isolated, log it, tag the printer out of service and arrange repair. If there is any smoke, crackling, or the smell persists with all equipment off, evacuate the floor, call the fire service and tell reception. A normal panel is not evidence of absence: it only means no detector has operated yet.

3. Allocate the technician and the £500 budget for the morning. State what is deferred and what risk you accept.

Read the worked answer

Technician plan: 08:15-08:45 floor 5 with you; 08:45-09:30 server room: find the leak source, protect the rack, move the bucket, isolate nearby power if safe, and call the roofing contractor. 09:30 sign the lift permit and let the contractor start; the technician is not needed for the three-hour service. 11:00-11:20 fit the floor-6 light. Hot water is deferred.

Budget: up to £300 for an emergency roofer or leak kit, about £30 for the light fitting, and a small amount for temporary kettles/notice on floor 3. Keep at least £100 unallocated for the server room.

Accepted risk: floor-3 staff have no hot water until Tuesday; the stain may spread if the roofer cannot attend. Deferred risk must be recorded and handed to the afternoon coordinator, not just forgotten.