Health, Safety and Environmental Legislation and Site Rules

  • Employer duties under health and safety law are commonly framed as: provide safe plant and systems of work, safe handling and storage, information/instruction/training/supervision, safe premises with safe access and egress, and a safe working environment with adequate welfare.

  • A risk assessment is legally required to be 'suitable and sufficient' - it must identify hazards, evaluate risk, and record significant findings where five or more employees are employed.

  • Employees have a duty to take reasonable care of themselves and others, cooperate with the employer on safety matters, and report defects or hazards they cannot themselves remedy.

  • The hierarchy of control is: eliminate, substitute, engineering controls, administrative controls, then PPE - PPE is the last line of defence, not the first.

  • Environmental permitting for quarry operations typically covers dust, noise, water discharge, and waste; breaches are enforced by the regulator, not just internal discipline.

  • Site rules are enforceable instructions; breaching a site rule is a disciplinary matter and can also be a criminal offence where it breaches a legal duty.

  • Near-miss and dangerous-occurrence reporting is a legal duty in many jurisdictions, not optional - record the event even where no injury resulted.

  • A 'competent person' means someone with sufficient training, experience, knowledge and other qualities to properly undertake the task - not simply a senior employee.

Quick reference

Risk Assessment, Hazard Identification and Safe Systems of Work

  • Risk = likelihood × severity. Reducing either factor reduces the risk score; eliminating the hazard removes it entirely.

  • The five steps of risk assessment: identify hazards, decide who might be harmed and how, evaluate risks and decide controls, record and implement, review and update.

  • A safe system of work is a formal procedure documenting the sequence of work, the hazards, the controls, and who is responsible - it must be communicated and understood before work starts.

  • Residual risk is the risk remaining after controls are applied; it must be tolerable, not necessarily zero.

  • Dynamic risk assessment is a mental or short written reassessment made when conditions change on site - it supplements, but does not replace, the written assessment.

  • Hierarchy of control applies in order: the most effective controls remove the hazard at source; the least effective rely on behaviour or PPE.

  • A hazard is a source of potential harm; a risk is the chance, high or low, that harm will occur together with its severity.

  • Review triggers for a risk assessment include: change of process, change of plant, an incident or near miss, new personnel, and a set review date.

Quick reference

Plant and Machinery: Pre-Start Checks, Operation and Isolation

  • Pre-start checks typically cover: fluid levels, tyre condition and pressure, guards and covers in place, lights and alarms, seat belt, fire extinguisher, brakes, steering, and the presence of any leaks or damage.

  • Defects found at pre-start must be recorded and reported; plant must be tagged out of service if the defect affects safe operation.

  • Isolation for maintenance follows lock-out/tag-out: isolate the energy source, lock it, tag it, prove dead (test), and only then work on the plant.

  • Stored energy (hydraulic pressure, gravity, compressed air, springs) must be released or restrained before work begins - isolation alone does not remove stored energy.

  • Guards must never be removed or defeated while the plant is running; interlock switches must not be bypassed.

  • Only trained and authorised operators may operate plant; the operator is responsible for the daily pre-start check and for reporting faults.

  • Before starting plant, the operator checks the area for people, confirms the horn and alarms work, and ensures nobody is in the machine's sweep path.

  • When parking plant, lower attachments to the ground, apply the parking brake, remove the key, and chock where required.

Quick reference

Mobile Plant Operation and Site Traffic Management

  • A traffic management plan defines haul routes, one-way systems, speed limits, pedestrian walkways, crossing points, and reversing areas.

  • The hierarchy for reversing is: avoid reversing where possible, then use a trained banksman, then rely on reversing aids and alarms - never reversing aids alone.

  • A banksman must remain in clear view of the driver and use agreed signals; if the driver loses sight of the banksman, the driver stops immediately.

  • Segregation of pedestrians and plant is the primary control - physical barriers and marked walkways are preferred over painted lines alone.

  • Blind spots on large mobile plant are significant; operators must use mirrors, cameras and spotters, and pedestrians must never assume they have been seen.

  • Speed limits, load limits and stability limits on site are set for the plant and conditions; exceeding them is a common cause of overturning and loss-of-control incidents.

  • Haul roads require maintenance - potholes, rutting, spillage and dust all increase the risk of loss of control and must be reported.

  • Loading and unloading areas must be level, clear of overhead lines, and controlled so that only one machine operates in the loading zone at a time.

Quick reference

Excavations, Stockpiles, Tips and Ground Stability

  • An excavation must be supported, battered back to a safe angle, or otherwise made safe; unsupported vertical faces in loose material are a collapse hazard.

  • Spoil and materials must be kept back from the edge of an excavation - a common rule is a distance at least equal to the depth of the excavation, and never less than the site standard.

  • Excavations deeper than a set depth (commonly 1.2 m in many jurisdictions) require shoring, benching or a documented safe system, and access must be by ladder.

  • Before digging, use service plans and a cable avoidance tool, plus hand-dig trial holes near marked services - never rely on drawings alone.

  • Stockpiles and tips must be stable; over-steepening, undercutting the toe, or loading the crest can cause run-off or collapse.

  • Water ingress, vibration, and adjacent loading all reduce the stability of excavations and tips; monitor and reassess after rain or blasting.

  • The angle of repose is the steepest angle at which loose material remains stable - exceed it and the slope fails.

  • Edge protection, barriers and warning signs must be provided around excavations and the crests of tips and stockpiles.

Quick reference

Blasting, Explosives and Drilling Operations

  • Blast exclusion zones must be cleared and guarded before firing; the shot firer confirms all personnel are accounted for and gives the warning signal.

  • Warning signals are standardised: a series of audible signals before firing, a distinct signal at firing, and an all-clear after the area is confirmed safe.

  • Explosives must be stored in licensed magazines, kept secure, and issued only to authorised persons with records of issue and return.

  • Misfires must be treated as live; the area is kept clear, the shot firer is informed, and the misfire is dealt with only by a competent person following the site procedure.

  • Drilling operations require dust suppression (water or extraction), hearing protection, and control of the risk from rotating parts and compressed air.

  • Before drilling, confirm the hole pattern and check for misfires or remnants from previous blasts - drilling into a misfire can initiate it.

  • Vibration and flyrock are controlled by blast design: burden, spacing, stemming, charge weight and delay sequence all affect the outcome.

  • After the blast, the area is inspected for misfires, unsafe ground and damaged services before the all-clear is given and work resumes.

Quick reference

Crushing, Screening, Conveying and Processing Plant

  • The primary hazards of crushers and screens are entanglement, crushing, and ejection of material - guards and interlocked access doors are the key controls.

  • Conveyors present nip points at head and tail pulleys, and the belt itself can trap or drag a person; nip guards and pull-cords are essential controls.

  • Before clearing a blockage or working on a conveyor, isolate and lock off, prove dead, and release stored energy - never clear a blockage while the plant is running.

  • Pull-cords (emergency stop cords) along conveyors must be tested and must stop the belt when pulled; they are not a substitute for isolation during maintenance.

  • Dust and noise are the main occupational health hazards in processing plant; water sprays, enclosures and extraction control dust, and hearing protection controls noise.

  • Start-up and shutdown sequences must follow the site procedure; conveyors are started in the correct order so that material is not left on a stopped belt.

  • Walkways, handrails and stairs around plant must be kept clear of spillage and tripping hazards; spillage is a slip and fire risk.

  • Access to crushers and screens is only via interlocked doors - bypassing an interlock is a serious safety breach.

Quick reference

Emergency Procedures, First Aid and Incident Reporting

  • Emergency procedures must cover fire, explosion, major injury, entrapment, and environmental release, and must identify the alarm, the assembly point, and the responsible person.

  • The first action on discovering a fire is to raise the alarm and evacuate by the nearest safe route; fighting the fire is only attempted if trained and if it is safe to do so.

  • First aid arrangements must reflect the site's hazards and workforce; first aiders, kits and, where required, a first aid room must be provided and their locations known.

  • DR ABC (danger, response, airway, breathing, circulation) is the primary survey sequence for a casualty.

  • Incident reporting must be prompt and factual: record what happened, when, where, who was involved, the injuries, and the immediate actions taken.

  • Reportable incidents typically include fatalities, specified injuries, over-seven-day injuries, dangerous occurrences and certain occupational diseases - check the jurisdiction's list.

  • Preserve the scene after a serious incident so that the investigation can establish cause; do not move equipment unless it is necessary to save life or prevent further harm.

  • The purpose of investigation is to find root causes and prevent recurrence - not to apportion blame.

Quick reference

Environmental Controls: Dust, Noise, Water and Waste

  • Dust controls include water sprays, dust suppression on haul roads, enclosures, extraction and reduced drop heights when loading.

  • Noise controls follow the hierarchy: reduce at source, enclose, isolate, then administrative controls and hearing protection; noise is measured in decibels (dB(A)).

  • Silica dust from cutting and crushing is a serious health hazard; control it with water or extraction and do not rely on respiratory protection alone.

  • Water management includes settlement lagoons, silt traps, and bunding around fuel and chemical storage to prevent pollution of watercourses.

  • Spill response uses the 'contain, absorb, dispose' approach - stop the source, contain with absorbent or bunding, and dispose of contaminated material correctly.

  • Waste must be segregated (for example, general, hazardous, and recyclable), stored in labelled containers, and disposed of through licensed carriers.

  • Dust, noise and water discharges are often regulated by permit conditions with set limits; monitoring records must be kept.

  • Runoff from stockpiles and tips can carry suspended solids; settlement before discharge is a standard control.

Quick reference

Communication, Teamwork and Supervisory Responsibilities

  • Supervisors are responsible for ensuring that the safe system of work is followed, that personnel are competent, and that hazards are reported and controlled.

  • Toolbox talks are short, task-specific briefings delivered before work; they must be understood, and understanding should be confirmed by questioning.

  • Effective communication uses clear, agreed signals and terminology; where language barriers exist, use interpreters, pictograms or demonstrations.

  • A supervisor must stop work where there is an imminent risk to safety - the authority to stop work is a core supervisory responsibility.

  • Handover between shifts must cover plant status, isolation status, ongoing hazards, and any open defects.

  • Teamwork depends on clear roles and responsibilities; everyone must know who is in charge and what to do in an emergency.

  • Reporting lines must be clear: defects, near misses and hazards are reported to the supervisor, who escalates as required.

  • A supervisor should verify competence and authorisation before allowing anyone to operate plant or carry out a task.