IIW IWI-S study plan
IIW IWI-S · Give each week a clear focus.
8 weeks · About 7 hours per week
Inspection and testing (NDT and destructive testing) & Welding processes and equipment
Map every NDT method (RT, UT, MT, PT, VT, ET) to the discontinuity types it detects and its typical applications in welded fabrication
Explain the physical principle, penetration behaviour and detection limits of each NDT method in writing without notes
Compare welding processes (SMAW, GMAW, GTAW, SAW, FCAW, resistance, laser) by heat input, deposition rate, positional capability and typical defects
Identify the equipment set-up variables (polarity, current density, shielding gas, wire feed) that shift a process into a defect-prone window
Classify common weld discontinuities (porosity, lack of fusion, undercut, slag, cracks) by origin and most suitable detection method
Your checkpoint
A one-page NDT-method-to-discontinuity matrix plus a 400-word comparison of five welding processes scored on defect risk
Inspection and testing (NDT and destructive testing) & Welding inspection practice and reporting
Interpret radiographs and ultrasonic indications conceptually: image quality indicators, sensitivity, dead zones, probe angle selection
Write acceptance/rejection decisions for five worked indication scenarios against a stated acceptance criterion
Draft inspection reports that record technique, standard reference, equipment, calibration status, results and disposition
Distinguish between inspection, testing and examination terminology as used in quality and reporting documents
Practise describing an indication objectively without prematurely naming the defect
Your checkpoint
Five completed mock inspection reports with accept/reject dispositions and a justification paragraph each
Inspection and testing (NDT and destructive testing) & Welding inspection practice and reporting
Explain destructive tests (tensile, bend, impact, hardness, macro/micro) and what each proves about procedure qualification
Link test-piece failure modes back to welding parameter causes
Calculate and interpret hardness traverse results against common acceptance limits
Describe how welding procedure qualification test results feed into the written procedure
Produce a defect-cause-test-evidence chain for three failure cases
Your checkpoint
A destructive-test interpretation sheet covering six test types with acceptance criteria and three worked failure-case chains
Materials and their behaviour during welding & Welding processes and equipment
Classify steels by composition and structure and predict their weldability and cracking susceptibility
Explain the carbon equivalent concept and use it to justify preheat decisions
Describe hydrogen-assisted cracking mechanisms and the controls (preheat, low-hydrogen consumables, heat input, post-heat)
Explain how welding thermal cycles alter microstructure in the heat-affected zone of ferritic and stainless steels
Match filler metal selection to parent metal and service condition for five material pairs
Your checkpoint
A material weldability dossier: five material groups with CE reasoning, preheat/interpass recommendations and HAZ risks
Construction and design & Fabrication, welding applications and applied welding technology
Read a welded joint design and identify where stress concentration and restraint will drive defect risk
Apply heat input and interpass control calculations to a multi-run procedure
Describe distortion mechanisms and select corrective and preventive techniques for three joint configurations
Explain weld symbol interpretation and how design intent transfers to the fabrication drawing
Sequence a fabrication from fit-up to final inspection, naming the hold points
Your checkpoint
A fabrication sequence with hold points and a distortion-control plan for one multi-run butt and fillet assembly
Quality management, QA/QC and documentation & Fabrication, welding applications and applied welding technology
Distinguish quality control from quality assurance and place each activity in the fabrication workflow
Trace the document set: contract review, WPS, PQR, welder qualification, ITP, NCR, final dossier
Write a non-conformance report with root cause, containment and corrective action
Explain traceability of consumables and material certificates through the production chain
Describe how an inspection and test plan sets inspection points, methods and acceptance criteria
Your checkpoint
A complete mock project quality dossier index with one filled NCR and one ITP extract
Health, safety and environmental protection & Quality management, QA/QC and documentation
Identify welding fume, gas, radiation, noise and fire hazards and match each to a control measure
Explain ventilation and extraction principles and when respiratory protection is required
Interpret exposure limits conceptually and describe how monitoring supports compliance
Describe environmental controls for waste, consumable disposal and fume emission
Link safety controls into the inspection and test plan so safety checks become hold points
Your checkpoint
A hazard-to-control register for a welding workshop with at least ten hazards and an integrated safety hold-point list
Welding inspection practice and reporting & Inspection and testing (NDT and destructive testing) & Construction and design
Run a full timed mock inspection from drawing review through report issue
Apply acceptance criteria consistently across NDT, destructive and visual evidence
Write a final inspection report with a clear, defensible disposition and traceable references
Review and close knowledge gaps identified in earlier weeks using a personal error log
Explain the inspector's role and limits of authority in the quality chain
Your checkpoint
One full timed mock inspection with issued report, scored against a self-built checklist, plus a closed gap log
Milestones
Week 2: Can classify any listed discontinuity and name the most suitable NDT method plus one alternative, in under two minutes per case
Week 4: Can justify a preheat and interpass decision from carbon equivalent and section thickness without reference material
Week 6: Can trace a fabricated joint from contract review to final dossier and name every intervening document
Week 8: Completes a timed mock inspection and issues a report with correct dispositions on at least 80 percent of indications