Matching a Low Bid on a 60-Square Re-Roof

IL Roofing Contractor · Put your knowledge to work in context.

All case studies

Matching a Low Bid on a 60-Square Re-Roof

You are bidding a 60-square, 6:12 architectural shingle replacement on a 1978 two-story colonial in a northern Illinois suburb. Your takeoff includes tear-off of two layers, synthetic underlayment, ice-dam protection at all eaves, new drip edge, ridge and soffit ventilation, and the permit. Your price is $31,400. The homeowner shares a competitor's written proposal at $22,900: no ice-dam protection, underlayment type and fastener schedule unstated, ventilation listed as 'existing,' and a note that 'permits, if required, are the homeowner's responsibility.' From the attic you noticed no soffit intake path and 3/8-inch plywood sheathing with two soft spots near a valley. The homeowner likes your company and asks you to 'meet the other number.'

1. Explain the $8,500 gap and state what you will and will not do to close it.

Read the worked answer

Itemize the difference in writing rather than defending a lump sum.

What the other bid actually deletes:

  • Ice-dam protection is required by IRC R905.1.2 for roof coverings where winter design conditions warrant it, and northern Illinois municipalities enforce it at the eave. Deleting it is not a discount - it transfers a foreseeable ice-dam claim to the homeowner, and it can void the shingle manufacturer's warranty.
  • Underlayment and fastening are code and manufacturer requirements, not options. An unstated fastener schedule usually means the minimum, which is a liability on a 6:12 in a wind zone.
  • 'Ventilation: existing' on a house with no intake path is a no-op; the exhaust you are adding needs intake to work.
  • 'Permits are the homeowner's responsibility' does not transfer the exposure. Whoever installs unpermitted work absorbs the stop-work order, the re-inspection, and the removal cost.

What you can legitimately do: offer a good/better/best written proposal, a compliant but lower-tier shingle, or a phased scope. What you must not do is meet the number by deleting code-required scope - you would own the resulting failure.

2. The homeowner asks for 'value engineering' options. What alternatives are defensible?

Read the worked answer

Value engineering is legitimate only when it changes the product or the schedule, never the code minimum.

  • Product tier: a compliant entry-level architectural shingle with a shorter warranty instead of the premium line - same underlayment, ice barrier, and fastening.
  • A measured ventilation upgrade priced as a separate line, with the net free area math shown (roughly 1/150 of the attic floor area, reducible to about 1/300 where a ceiling vapor retarder exists and intake and exhaust are balanced - verify against the locally adopted code).
  • Phasing or a maintenance agreement to spread cost without reducing scope.
  • Owner-performed work that carries no code or warranty consequence (e.g., landscaping protection, removing satellite dishes).

Show the homeowner her real comparison: the $22,900 bid plus the ice barrier, permit, and ventilation she will pay for anyway - or pay for later, at emergency prices, from inside a stained ceiling.

3. How do you price and control the questionable 3/8-inch sheathing and the two soft spots?

Read the worked answer

Handle it as a priced contingency, not a guess.

  • Verify first: check panel thickness and span rating against the code's sheathing table and the shingle manufacturer's minimum deck requirements. Where panels are under-spanned, delaminated, or deflecting visibly, they must be replaced - overlay or shimming is not a remedy.
  • Put a unit price in the contract (per sheet of matching thickness, installed), so the discovery has an agreed value.
  • Scope the investigation: soft spots near a valley usually mean a long-standing leak. Probe the area, inspect the rafter for rot, and report in writing within the contract's notice period before covering anything.
  • Document with photos before and after, and obtain a signed change order.

Expect roughly a few sheets, not two - but quote the unit rate so the number is never in dispute.