Coastal Pole Foundations with Groundwater and a Leaning Pole

IMSA Roadway Lighting I · Put your knowledge to work in context.

All case studies

Coastal Pole Foundations with Groundwater and a Leaning Pole

A contractor is installing ten 9 m galvanized steel roadway lighting poles along a coastal boulevard. The geotechnical report notes loose sandy fill to 3 m, seasonal high groundwater at 0.6 m, and soil resistivity of 1,500 ohm-cm. The specified foundation is 0.75 m diameter by 2.1 m deep reinforced concrete with 19 mm anchor bolts, a 100 mm grout pad, and a handhole 450 mm above grade. During inspection, the contractor presents 1.2 m deep by 0.9 m diameter concrete cylinders with anchor bolts set directly in concrete; there is no rebar cage and no inspection record. The bottom of one excavation is wet with standing water. One pole is leaning 20 mm after a minor storm. The contractor says galvanizing is enough corrosion protection and requests acceptance so paving can proceed.

1. Should the engineer accept the foundation work? Evaluate the specific risks.

Read the worked answer

Do not accept. The installed foundations do not match the specified geometry or reinforcement: 1.2 m deep by 0.9 m diameter versus 2.1 m by 0.75 m, no rebar cage, and anchor bolts set directly in concrete without inspection. In loose sandy fill with groundwater at 0.6 m, the foundation's overturning and uplift resistance and anchorage are uncertain. The 20 mm lean after a minor storm is evidence of movement, not a cosmetic issue. Standing water in the excavation increases the risk of concrete defects, corrosion, and long-term settlement. Galvanizing helps the pole but does not compensate for inadequate foundation embedment or anchorage. The handhole elevation and grout pad also need verification. Acceptance should stop until a licensed engineer reviews the as-built conditions and the geotechnical assumptions.

2. What verification, testing, and records should be required before any remediation or acceptance?

Read the worked answer

Require excavation and foundation inspection records; concrete mix design, strength tests, and placement records; rebar size, cover, and cage details; anchor-bolt grade, embedment, projection, and torque; foundation elevation and plumbness survey; soil verification against the geotechnical report; groundwater observation and dewatering records; and corrosion assessment including pH, chlorides, sulfates, and resistivity, not resistivity alone. For the leaning pole, survey movement and check anchor bolts for elongation or cracks. If records are missing, nondestructive testing or load testing may be needed. The engineer of record must approve any remediation.

3. Outline a safe remediation sequence and the inspection hold points.

Read the worked answer

Likely remediation is to excavate and replace deficient foundations with engineered reinforced foundations, dewater and backfill properly, and reinstall poles; or underpin and strengthen them if analysis permits. Verify anchor-bolt torque and grout after curing, correct handhole orientation and elevation, and restore drainage. Add inspection hold points before concrete placement. For coastal corrosion, use the specified galvanizing and coating system and inspect for damage; repair galvanizing by an approved method. Do not pave over or conceal the work until the engineer accepts the foundations. Document all deviations and corrective actions.