Plan Sheet

A scaled drawing in the contract plans showing the location, dimensions, and details of signal work-poles, conduit runs, cabinets, and signal heads-that the contractor uses to lay out and build the installation.

Related: Special Provisions, Shop Drawing, Stationing
Standard Specifications

The contract book of general requirements covering materials, construction methods, and measurement and payment for each item of work, applied unless the plans or special provisions state otherwise.

Related: Special Provisions, Plan Sheet
Special Provisions

Project-specific written requirements that modify, add to, or delete portions of the standard specifications for a particular contract; they govern wherever they conflict with the general specifications.

Related: Standard Specifications, Plan Sheet
Shop Drawing

A detailed drawing submitted by the contractor showing how equipment or structures will be fabricated and assembled-dimensions, materials, bolts, and connections-so the engineer can verify compliance with the contract before construction.

Related: Plan Sheet, Anchor Bolt Template
Stationing

Distance measured along a baseline or roadway centerline and written in stations, usually 100-foot units, used to locate poles, cabinets, conduit, and other plan features on the ground.

Related: Offset Stake, Benchmark
Corner Radius

The curved edge connecting two intersecting curbs or pavement edges; it controls turning paths, the length and placement of crosswalks, and where pedestrian push buttons and poles may be installed.

Related: Clear Zone, Sight Distance
Clear Zone

The unobstructed roadside area measured from the edge of the traveled way that should stay free of fixed objects; poles, cabinets, and foundations must sit outside it or be protected by an approved barrier.

Related: Corner Radius, Sight Distance
Sight Distance

The length of roadway a driver must be able to see to stop or react safely; signal heads, poles, signs, and vegetation are placed and maintained so this view is not blocked.

Related: Clear Zone, Signal Face
Benchmark

A fixed point of known elevation, such as a marked disk or hub, from which all vertical measurements on the project are referenced; it must be protected and rechecked before foundations are set.

Related: Offset Stake, Stationing
Offset Stake

A stake set a measured distance away from the actual construction point and marked with the offset and cut or fill, allowing the point to be re-established after excavation destroys the original mark.

Related: Benchmark, Stationing
Anchor Bolt Template

A rigid jig, often plywood or steel, that holds anchor bolts at the correct spacing, bolt-circle diameter, and projection while foundation concrete is placed so the pole or cabinet base will fit.

Related: Pier Foundation, Shop Drawing
Pier Foundation

A drilled or excavated concrete column, typically reinforced and fitted with anchor bolts, that supports a signal pole or mast arm and resists overturning, uplift, and torsion from wind and wire loads.

Related: Anchor Bolt Template, Benchmark
Trench Bedding

A layer of sand, select granular material, or controlled low-strength material placed in the trench bottom to support conduit evenly and protect it from rock, debris, and point loading before backfill.

Related: Minimum Cover, Tracer Wire
Pull Box

An accessible buried or flush enclosure in a conduit run where cables can be pulled, spliced, or redirected; required where runs are long or contain enough bends to exceed pulling limits.

Related: Trench Bedding, Cable Schedule
Tracer Wire

A durable, usually insulated conductor laid alongside nonmetallic conduit or direct-buried cable so the buried route can be located later with a locating instrument, reducing damage during future excavation.

Related: Minimum Cover, Pull Box
Minimum Cover

The least depth of soil, base, or pavement required above the top of a conduit or duct, set by the specifications to protect it from traffic loads and routine excavation.

Related: Trench Bedding, Tracer Wire
Mast Arm

A horizontal or slightly arched structural arm attached to a pole that carries signal heads and signs out over the roadway, designed for wind, ice, and dead loads.

Related: Span Wire, Strain Pole
Span Wire

A tensioned wire suspended between two poles or structures from which signal heads and signs hang; the poles, guys, and anchors must be sized for the combined wire and equipment loads.

Related: Strain Pole, Guy Anchor, Mast Arm
Strain Pole

A pole sized and founded specifically to resist the one-directional pull of span wires or guys, usually with a heavier foundation or an anchor installed opposite the wire load.

Related: Guy Anchor, Span Wire
Guy Anchor

A buried device-screw anchor, plate, or concrete deadman-connected to a pole by a guy wire to resist lateral or unbalanced loads and keep the pole plumb.

Related: Strain Pole, Span Wire
Conductor Color Code

The standard, project-specified assignment of colors or tracers to conductors in a cable so each circuit can be identified and terminated at the same point at both ends.

Related: Cable Schedule, Home Run
Cable Schedule

A plan table listing each cable by tag number, size, conductor count, routing from and to, and length, used to pull, label, and terminate conductors correctly.

Related: Conductor Color Code, Home Run, Pull Box
Home Run

A cable run from a field device straight back to the controller cabinet with no intermediate splices or junction points, which simplifies testing and troubleshooting.

Related: Cable Schedule, Controller Cabinet
Bend Radius

The minimum radius to which a cable or conduit may be bent without damaging conductors or insulation; conduit bends must also be large enough to keep cable pulling within its own limit.

Related: Pull Box, Home Run
Signal Face

One complete set of signal indications-typically red, yellow, and green-aimed at a single approach or lane group; a signal head may contain one or more faces.

Related: Backplate, Visor, Phantom Indication
Backplate

A contrasting, usually black, panel mounted behind a signal face to make the indications stand out against bright or cluttered backgrounds such as sky, signs, or buildings.

Related: Signal Face, Phantom Indication
Visor

A hood projecting from the front of a signal lens that shields it from sunlight, reducing phantom indications and improving contrast; cutaway visors are used where drivers stop close to the head.

Related: Signal Face, Phantom Indication
Phantom Indication

A false signal appearance, most often caused by sunlight reflecting off a lens or by a signal face aimed toward traffic it does not control; visors, backplates, and proper aiming reduce it.

Related: Visor, Backplate
Accessible Pedestrian Signal (APS)

A pedestrian signal that supplements the visual display with audible and tactile information-locator tones, speech messages, and a vibrating arrow-so pedestrians with vision impairments can cross safely.

Related: Signal Face, Functional Test
Controller Cabinet

The weatherproof enclosure, usually aluminum or stainless steel, that houses the signal controller, power distribution, detector units, conflict monitoring, and terminal facilities for the intersection.

Related: Malfunction Management Unit, Detector Amplifier, Ground Rod
Malfunction Management Unit (MMU)

A monitoring device that watches signal outputs for conflicts, shorts, or field failures and, when a fault is detected, forces the intersection into flashing operation until the problem is corrected.

Related: Controller Cabinet, Functional Test
Inductive Loop Detector

A loop of wire embedded in the pavement and connected to an amplifier in the cabinet; passing vehicles change the loop's inductance and generate a call for the controller.

Related: Detector Amplifier, Controller Cabinet
Detector Amplifier

The cabinet card that energizes a loop or other sensor, tunes it to a stable operating point, and converts detected vehicle presence into calls the controller can process.

Related: Inductive Loop Detector, Controller Cabinet
Ground Rod

A copper-clad or galvanized rod driven into the earth and bonded to cabinet, pole, and equipment grounds to provide a low-resistance path for fault current and surge energy.

Related: Controller Cabinet, Insulation Resistance Test
Insulation Resistance Test

A test in which a megohmmeter applies high direct voltage between conductors and from conductors to ground to confirm insulation is intact and dry before equipment is connected.

Related: Ground Rod, Functional Test
Functional Test

Operating every signal indication, pedestrian display, detector, and auxiliary device from the controller to verify the installed system performs as designed before the intersection is placed in service.

Related: Turn-On, Detector Amplifier
Turn-On

The coordinated procedure for placing a new or rebuilt signal in service, usually beginning in flashing mode and followed by stop-and-go operation with the engineer and agency present.

Related: Functional Test, Traffic Control Plan (TCP)
Traffic Control Plan (TCP)

A drawing and written description of how traffic, pedestrians, and workers will be protected through a work zone, including signs, channelizing devices, tapers, and flagging.

Related: Turn-On