The 60:40 Split, Three Rain Days and a Muster Roll Dispute

Gujarat Gram Sevak · Put your knowledge to work in context.

All case studies

The 60:40 Split, Three Rain Days and a Muster Roll Dispute

Khetardi Gram Panchayat has a MGNREGA pond-deepening work sanctioned at Rs 9,60,000, with the statutory 60:40 wage-material split. The notified unskilled wage rate is Rs 250 per person-day. The mate's muster roll shows 96 workers engaged for 24 days each, and the GP has submitted a material claim of Rs 3,95,000 for pipe, cement and earth-moving hire. During verification the Gram Sevak finds that on three days heavy rain stopped work at 11:00, yet the muster roll marks all 96 workers present for the full day, and there is no measurement book entry for those three days. A group of workers complains that 14 of them were paid for only 21 days although the muster shows 24. The Sarpanch says the material claim should be cleared 'because the money is anyway within the sanctioned amount'.

1. Compute the maximum permissible wage and material components and decide whether Rs 3,95,000 of material is admissible. Show the percentage check.

Read the worked answer

Ceiling under the 60:40 condition (applied to the sanctioned amount of Rs 9,60,000):

  • Wage component, maximum = 60% × 9,60,000 = Rs 5,76,000
  • Material component, maximum = 40% × 9,60,000 = Rs 3,84,000

Check on the claim: 3,95,000 − 3,84,000 = Rs 11,000 in excess.

Cross-check by proportion: 3,95,000 ÷ 9,60,000 = 41.1%, above the 40% ceiling.

Cross-check against actual expenditure: if wages of Rs 5,76,000 and material of Rs 3,95,000 were both paid, the total would be Rs 9,71,000 - Rs 11,000 more than the sanction itself, and material would be 3,95,000 ÷ 9,71,000 = 40.7%, still impermissible.

The claim is therefore not admissible in full. The material component must be restricted to Rs 3,84,000 unless a revised sanction enhancing the project cost is obtained from the Programme Officer on recorded reasons. Restricting material automatically caps the wage side at Rs 5,76,000, i.e. 2,304 person-days at Rs 250 - which is exactly what the muster claims, so any further cut on the wage side will pull the total project cost below the sanction.

2. Compute the wage amount affected by the three rain days, and state what must be done to the muster roll and to the 14 workers' payments.

Read the worked answer

Rain days: 96 workers × 3 days = 288 person-days. At Rs 250 per person-day the excess is 288 × 250 = Rs 72,000.

No work was executed after 11:00 on those days and there is no measurement book entry, so the person-days are not verifiable. They cannot stand on the muster merely because the muster was signed. Wages under MGNREGA are paid against actual attendance and measurable work, and marking present without work is a muster falsification that the Gram Sevak is duty-bound not to certify.

Action on the muster: do not certify the three days; record the reason (rain, work stopped at 11:00) in the worksite register and the measurement book; raise a correction entry; if any amount has already been credited for those days, initiate recovery under the prescribed procedure and inform the Programme Officer. The mate's role should be examined separately, because the false marking originated at the worksite.

The 14 workers: 24 − 21 = 3 days each, so 14 × 3 = 42 person-days, i.e. 42 × 250 = Rs 10,500 short-paid. This is the opposite error and must be corrected on the same visit: verify their attendance against the worksite register, and if the muster is right, pay the shortfall through the wage payment system and record it. The Gram Sevak should not use one correction to bargain away the other - underpayment of workers and overpayment on the muster are separate liabilities.

3. How should the Gram Sevak answer the Sarpanch's argument that the claim is 'within the sanctioned amount'?

Read the worked answer

The argument confuses a ceiling with a permission. The sanction of Rs 9,60,000 sets the maximum the work may cost; it does not authorise any internal composition. The 60:40 wage-material ratio and the wage rate are conditions of the scheme, and a claim that breaches them is inadmissible even if the total stays under the sanction - indeed, on these figures it does not stay under the sanction once both components are paid.

A short, firm answer: 'The sanction is a limit on the total, not a licence on the components. Rs 3,95,000 is 41.1% material against a 40% cap, and paying it would take the total to Rs 9,71,000, beyond the sanction. I cannot certify it.'

What the Gram Sevak should then do:

  1. Return the material claim with the arithmetic shown in writing, so the reason is on record.
  2. Ask for vouchers and measurement book support for the material actually consumed; if the full Rs 3,95,000 has already been spent, seek a revised sanction prospectively rather than certifying it retrospectively.
  3. Place both the muster correction and the short-payment of the 14 workers before the Programme Officer in the same report, so that the record shows a balanced verification rather than a one-sided one.
  4. Avoid the informal compromise of adjusting the excess material against the short-paid wages; that would convert two separate irregularities into a single unaudited adjustment.