The End-of-Day Batch That Will Not Fit

IIBF Certified Information System Banker · Put your knowledge to work in context.

All case studies

The End-of-Day Batch That Will Not Fit

Vantage Commercial Bank (3.4 million deposit accounts, 1,100 branches) runs its core banking platform in a vendor-hosted data centre. The end-of-day batch was designed for a 3 hour 30 minute window; over eight months it has stretched to 6 hours 50 minutes. Salary credits missed the 09:00 customer commitment twice last month, ATM cash-position files now arrive after the 06:30 replenishment cut-off, and on Mondays 14 of 60 interfaces fail with 'file not found'. Transaction volumes grew 41% in 18 months after mobile onboarding went live; the ledger table holds 2.9 billion rows; three new interfaces were added in the last year with no batch-scheduling review. The vendor proposes two additional application nodes at ₹2.4 crore a year plus 'database tuning'. The CTO supports this. The COO wants to start the batch at 22:00 instead of 00:30. The regulator requires end-of-day balances by 10:00, and a change freeze begins in five weeks.

1. Rank the plausible root causes of the batch overrun and state what evidence would confirm or eliminate each, before any capacity spend is approved.

Read the worked answer

Do not buy capacity until the wait/run split is known. The proposal assumes a compute bottleneck; the symptoms do not yet support that.

  1. Interface arrival delays (highest probability). The 14 Monday 'file not found' failures point to upstream file delivery, not CPU. Evidence: per-interface arrival timestamps for the last 90 days compared with the job's scheduled start; count of jobs that start on time but wait on a dependency.
  2. Critical-path serialization. A batch can run long with idle CPUs if job B cannot start until job A finishes. Evidence: a Gantt chart of job start and end times; compute the longest dependency chain and compare it with total elapsed time.
  3. Data growth without archiving. 2.9 billion ledger rows and 41% volume growth will slow full-table scans and index rebuilds. Evidence: top 20 SQL statements by elapsed time, rows examined per execution, index fragmentation, and the time-per-1,000-transactions trend over 12 months.
  4. Inefficient new interfaces. Three interfaces added without scheduling review may run unindexed queries or contend in parallel. Evidence: execution plans, lock waits, deadlock graphs.
  5. Infrastructure contention. Evidence: CPU, IOPS and IO latency sampled every minute across the window. If CPU sits below 50% while elapsed time grows, nodes will not help.

A two-week instrumented baseline costs far less than ₹2.4 crore a year and prevents a multi-year lock-in to the wrong fix.

2. Evaluate the CTO's node purchase and the COO's 22:00 batch start. Recommend a decision with conditions and an interim control set.

Read the worked answer

The 22:00 start is a buffer, not a fix. Batch duration is 6h50m; moving the start earlier by 2h30m restores the 09:00 output only by consuming the online window and colliding with branch close, vendor file windows and the 22:00-00:30 maintenance slot. It also hides the defect, so the next volume increase re-breaks the SLA. It is acceptable only as a dated interim measure with a written expiry.

The node purchase is premature and poorly framed. ₹2.4 crore a year, presumably on a multi-year term, buys capacity the evidence may not justify. Ask the vendor for a benchmark showing the batch is CPU-bound, a per-node throughput commitment, and a termination right if the SLA is not met.

Recommendation:

  • Approve a 60-day remediation: archive or purge closed accounts, add the missing indexes, re-sequence the critical path, move the ATM cash file to a 05:00 cut-off, pre-stage interface files.
  • Set a decision gate: if the batch is not under 4h30m at day 60, approve nodes.
  • Use the change freeze exception only for risk-reducing batch changes, with CAB approval and rollback.
  • Escalate the vendor's refusal to provide execution statistics as a contract-performance issue.

The COO's option and the CTO's option are not the only two; a measured remediation with a gate is cheaper and produces evidence either way.

3. What would you report to the IT steering committee and the regulator, and what would you refuse to sign?

Read the worked answer

To the IT steering committee, report: batch elapsed time against the 3h30m design and the 09:00 commitment for each of the last 90 days; root-cause status; customer-impacting incidents (two salary-credit misses, ATM replenishment); remediation plan with owners and gate dates; vendor SLA performance; and the ₹2.4 crore proposal with the evidence gap stated.

To the regulator, report: any breach of the end-of-day balance commitment and the customer-impacting salary-credit delay, under the incident-reporting requirement, with cause, containment and remediation. Do not wait for the fix; late reporting is a separate violation.

What I would refuse to sign:

  • A statement that 'the capacity upgrade resolves the batch overrun' before the wait/run analysis exists.
  • A certification that there is no customer impact, because salary credits were late twice.
  • An approval that treats the 22:00 start as permanent without an expiry date.

The test is whether a reader six months later can see what was known, what was decided and what remained open.