Northgate Developments: Piling, Contamination and Delay in Start-Up

III IC-45 ยท Put your knowledge to work in context.

All case studies

Northgate Developments: Piling, Contamination and Delay in Start-Up

Northgate Developments is building a 12-storey office block on a brownfield city-centre site. The contract value is $85m, the build period is 24 months, and a 12-month defects liability period applies. Neighbouring buildings are within 5m, including a listed facade. Piling will be bored to 30m through known groundwater. The contractor has not previously installed piles deeper than 18m, and the piling subcontractor has not yet been selected. The site was formerly a gasworks, and contamination is confirmed. The contractor requests a construction all-risks policy with a $50m limit, a $100,000 deductible, and 12 months' delay in start-up (DSU) cover at $15m. The underwriter's survey notes that vibration and settlement are the main concerns, and that the DSU limit was based on the developer's rough estimate rather than a cash-flow model. The policy is due to incept in five days.

1. Evaluate the adequacy of the $50m limit and $100k deductible for this project.

Read the worked answer

The $50m limit is only about 59% of the $85m contract value. A major loss involving collapse, removal of debris, shoring of the listed facade or reconstruction could exceed the contract value, so $50m is inadequate. I would require at least $85m, and preferably $100m, including demolition and professional fees. The $100,000 deductible is low for deep piling next to a listed building; vibration or settlement claims could be frequent. Increase the deductible to $250,000-$500,000 and add a separate sub-limit for vibration and settlement damage to neighbouring property. These terms reflect the concentration and third-party exposure, not just the build cost.

2. Recommend conditions and exclusions for the piling, groundwater and contamination.

Read the worked answer

Require a piling method statement, a pre-construction condition survey of all neighbouring buildings, vibration and settlement monitoring with agreed trigger limits, and groundwater monitoring. Approve the piling subcontractor before work starts, including evidence of 30m bored-pile experience. For contamination, impose a discovery-period exclusion or a modest sub-limit for sudden and accidental pollution, and require a remediation plan. Exclude known contamination and gradual pollution, but do not leave the insured without cover for a sudden escape. Add a defects exclusion and a maintenance-period endorsement. These conditions make the piling risk inspectable and give the insurer a trigger for stopping work if monitoring limits are breached.

3. Explain how the DSU limit should be set and what information is needed.

Read the worked answer

The $15m DSU limit appears to be a rough estimate. DSU should be based on the maximum indemnity period and the projected cash flow: lost rent, debt service, additional costs and any contractual penalties. For a 12-storey office, 12 months may be too short if lease-up is slow after a major delay. I would request the development appraisal, rent roll, financing agreements, lease-up assumptions and the construction programme. The limit should reflect the worst credible delay and the financing structure, not simply a round number. The underwriter should also check whether the DSU period runs from the intended completion date and whether it dovetails with the 12-month defects liability period.