Maharashtra SSC Power Consumer Energy Meter Pre-Voc/NSQF study materials
Maharashtra SSC Power Consumer Energy Meter Pre-Voc/NSQF study resources

Maharashtra SSC Power Consumer Energy Meter Pre-Voc/NSQF flashcards

Maharashtra SSC Power Consumer Energy Meter Pre-Voc/NSQF · Build recall with a focused review session.

32 cards. Read the term and the definition here. The deck at the top of this page is optional.

Ohm's law
For a resistive circuit, voltage equals current multiplied by resistance (V = I × R). Power equals voltage times current, or current squared times resistance.
One kWh unit
One kilowatt-hour equals 3.6 million joules and is the unit shown on a consumer bill. A 1000 W load running one hour consumes exactly one unit.
Power factor
Ratio of real power in kW to apparent power in kVA, equal to cosine of the phase angle. Low power factor raises current for the same kW and increases losses.
Meter constant
Number of disc revolutions per kWh on an induction meter, or pulses per kWh on an electronic meter. Energy equals pulses counted divided by the constant.
Accuracy class
Maximum permissible percentage error of a meter under reference conditions. Class 1.0 allows plus or minus one percent; class 0.5 is twice as tight.
Creep test
Test with rated voltage applied and zero current. The disc must make less than one revolution, and an electronic meter must emit no energy pulse.
Starting current
Lowest current at which the meter begins to rotate continuously. Induction meters must start at 0.5 percent of basic current at unity power factor.
Induction energy meter
Electromechanical meter with voltage and current electromagnets driving an aluminium disc. A permanent magnet brakes the disc so speed is proportional to power.
Static energy meter
Electronic meter with no moving parts. Voltage and current signals are multiplied by a metering chip and integrated into kWh registers stored in memory.
Prepaid meter
Meter that supplies energy only while purchased credit remains. A built-in relay disconnects the load at zero balance and reconnects after recharge.
Smart meter
Electronic meter with two-way communication, remote reading, time-of-day registers, and tamper event logging. It supports remote connect and disconnect commands.
Braking magnet
Permanent magnet in an induction meter that produces braking torque proportional to disc speed. Moving it radially changes the full-load error adjustment.
Shading coil
Copper ring on part of a voltage magnet pole that shifts flux phase. It creates the torque angle needed for correct registration at unity power factor.
Light-load compensation
Small adjustable copper loop or vane near the voltage magnet that adds slight driving torque to overcome bearing and register friction at very low currents.
Meter terminal block
Insulated block carrying incoming and outgoing phase and neutral conductors. Screws are tightened to the maker's torque to prevent heating and contact resistance.
Meter mounting height
Meters are fixed vertically on a rigid dry surface roughly 1.5 to 1.8 metres above floor level, so the display and terminal cover are accessible.
CT secondary open circuit
Opening a current transformer secondary while primary current flows produces dangerous high voltage. Short the secondary at the test block before removing the meter.
CT burden
Total volt-ampere load on a current transformer secondary, including meter and leads. Exceeding rated burden causes ratio and phase errors in metering.
Multiplying factor
CT ratio multiplied by PT ratio. Primary energy equals the meter reading difference multiplied by this factor, used for all transformer-operated metering.
Pointer dial reading
Read pointer dials from the lowest-value dial upward. When a pointer lies between two numbers, record the lower number, then apply the multiplying factor.
Maximum demand register
Records the highest average kVA or kW over the demand interval, usually thirty minutes, during the billing cycle. It is reset after each billing.
Percentage error formula
Error equals meter energy minus standard energy, divided by standard energy, multiplied by one hundred. Positive means fast, negative means slow.
Disc revolution timing
Time for N revolutions equals N times 3600, divided by meter constant in rev/kWh times applied kW. Compare measured time with this calculated value.
Calibration traceability
Reference standards used for meter testing must have valid calibration certificates linked to a national laboratory, so measured errors are legally defensible.
Hot terminal symptom
Discoloured or warm terminal block indicates loose screw or overload. Isolate supply, clean or replace the block, and retighten to specified torque.
Jewel bearing wear
Worn disc bearings cause slow registration or rubbing. Replacing the bearing restores accuracy, and the meter must be recalibrated afterwards.
Meter not registering
With load on, check supply at meter terminals, meter fuse, voltage coil or input, and loose connections. A failed voltage circuit gives zero registration.
Wrong CT ratio setting
If the ratio programmed in the meter differs from the installed CT, all readings scale wrongly. Verify the setting against the CT nameplate.
Two-part tariff
Consumer charge made of a fixed or demand charge based on connected load or contract demand, plus an energy charge per kWh actually consumed.
Slab tariff
Per-unit rate increases in consumption bands. Each band's rate applies only to units falling in that band, not to the whole consumption.
Prove dead
After isolation, test the conductors with a proven voltage tester before touching them. Treat every conductor as live until this test confirms otherwise.
Clamp meter use
Measures current by clamping around one conductor without breaking the circuit. Clamping around both phase and neutral cancels the field and reads near zero.