- Ohm's law
- For a resistive circuit, voltage equals current multiplied by resistance (V = I × R). Power equals voltage times current, or current squared times resistance.
- One kWh unit
- One kilowatt-hour equals 3.6 million joules and is the unit shown on a consumer bill. A 1000 W load running one hour consumes exactly one unit.
- Power factor
- Ratio of real power in kW to apparent power in kVA, equal to cosine of the phase angle. Low power factor raises current for the same kW and increases losses.
- Meter constant
- Number of disc revolutions per kWh on an induction meter, or pulses per kWh on an electronic meter. Energy equals pulses counted divided by the constant.
- Accuracy class
- Maximum permissible percentage error of a meter under reference conditions. Class 1.0 allows plus or minus one percent; class 0.5 is twice as tight.
- Creep test
- Test with rated voltage applied and zero current. The disc must make less than one revolution, and an electronic meter must emit no energy pulse.
- Starting current
- Lowest current at which the meter begins to rotate continuously. Induction meters must start at 0.5 percent of basic current at unity power factor.
- Induction energy meter
- Electromechanical meter with voltage and current electromagnets driving an aluminium disc. A permanent magnet brakes the disc so speed is proportional to power.
- Static energy meter
- Electronic meter with no moving parts. Voltage and current signals are multiplied by a metering chip and integrated into kWh registers stored in memory.
- Prepaid meter
- Meter that supplies energy only while purchased credit remains. A built-in relay disconnects the load at zero balance and reconnects after recharge.
- Smart meter
- Electronic meter with two-way communication, remote reading, time-of-day registers, and tamper event logging. It supports remote connect and disconnect commands.
- Braking magnet
- Permanent magnet in an induction meter that produces braking torque proportional to disc speed. Moving it radially changes the full-load error adjustment.
- Shading coil
- Copper ring on part of a voltage magnet pole that shifts flux phase. It creates the torque angle needed for correct registration at unity power factor.
- Light-load compensation
- Small adjustable copper loop or vane near the voltage magnet that adds slight driving torque to overcome bearing and register friction at very low currents.
- Meter terminal block
- Insulated block carrying incoming and outgoing phase and neutral conductors. Screws are tightened to the maker's torque to prevent heating and contact resistance.
- Meter mounting height
- Meters are fixed vertically on a rigid dry surface roughly 1.5 to 1.8 metres above floor level, so the display and terminal cover are accessible.
- CT secondary open circuit
- Opening a current transformer secondary while primary current flows produces dangerous high voltage. Short the secondary at the test block before removing the meter.
- CT burden
- Total volt-ampere load on a current transformer secondary, including meter and leads. Exceeding rated burden causes ratio and phase errors in metering.
- Multiplying factor
- CT ratio multiplied by PT ratio. Primary energy equals the meter reading difference multiplied by this factor, used for all transformer-operated metering.
- Pointer dial reading
- Read pointer dials from the lowest-value dial upward. When a pointer lies between two numbers, record the lower number, then apply the multiplying factor.
- Maximum demand register
- Records the highest average kVA or kW over the demand interval, usually thirty minutes, during the billing cycle. It is reset after each billing.
- Percentage error formula
- Error equals meter energy minus standard energy, divided by standard energy, multiplied by one hundred. Positive means fast, negative means slow.
- Disc revolution timing
- Time for N revolutions equals N times 3600, divided by meter constant in rev/kWh times applied kW. Compare measured time with this calculated value.
- Calibration traceability
- Reference standards used for meter testing must have valid calibration certificates linked to a national laboratory, so measured errors are legally defensible.
- Hot terminal symptom
- Discoloured or warm terminal block indicates loose screw or overload. Isolate supply, clean or replace the block, and retighten to specified torque.
- Jewel bearing wear
- Worn disc bearings cause slow registration or rubbing. Replacing the bearing restores accuracy, and the meter must be recalibrated afterwards.
- Meter not registering
- With load on, check supply at meter terminals, meter fuse, voltage coil or input, and loose connections. A failed voltage circuit gives zero registration.
- Wrong CT ratio setting
- If the ratio programmed in the meter differs from the installed CT, all readings scale wrongly. Verify the setting against the CT nameplate.
- Two-part tariff
- Consumer charge made of a fixed or demand charge based on connected load or contract demand, plus an energy charge per kWh actually consumed.
- Slab tariff
- Per-unit rate increases in consumption bands. Each band's rate applies only to units falling in that band, not to the whole consumption.
- Prove dead
- After isolation, test the conductors with a proven voltage tester before touching them. Treat every conductor as live until this test confirms otherwise.
- Clamp meter use
- Measures current by clamping around one conductor without breaking the circuit. Clamping around both phase and neutral cancels the field and reads near zero.