A 2.4 m Trench Beside a Footpath

RBSE Sec Voc Construction · Put your knowledge to work in context.

All case studies

A 2.4 m Trench Beside a Footpath

An 18 m long, 1.2 m wide trench, 2.4 m deep, is being dug in sandy silt for a boundary wall footing along a school boundary. Spoil is heaped 1.5 m high with its toe about 0.4 m from the trench edge. Overnight rain has left about 150 mm of seepage in the bottom, and workers are bailing it with buckets. The only access is by climbing down the trench side using the footing reinforcement; a loose wooden plank across the trench is being used by masons as a shortcut. There is no barricade or warning light, although a public footpath runs 1.5 m from the edge and children use it. The supervisor intends to send two workers into the trench to trim the bed, and a tractor-trolley of bricks is expected in the afternoon.

1. List the hazards in the order you would act on them, and explain the failure mechanism for the two most serious.

Read the worked answer

Order of action:

  1. Side-wall collapse under surcharge and seepage.
  2. Falls of persons and materials into an unbarricaded trench beside a footpath used by children.
  3. No safe means of access and egress.
  4. Water accumulation and softening of the trench bottom.
  5. Vehicle loading and vibration from the brick trolley.
  6. Impalement and struck-by hazards from projecting reinforcement.
  7. Housekeeping - the plank across the trench.

Mechanism 1 - collapse. Sandy silt has little cohesion when wet, and the seepage has already reduced the shear strength of the lower face. The spoil heap sits 0.4 m from the crest at 1.5 m high; that is roughly 2 tonnes per square metre of surcharge applied within the critical wedge behind the face, which is precisely the mass that resists sliding. The face therefore fails along a shallow slip plane, and 2.4 m of sand arrives in the trench within a second or two. A person cannot outrun it and cannot breathe in it.

Mechanism 2 - falls. An unbarricaded trench 2.4 m deep and 1.2 m wide is a trap for anyone walking along the footpath, particularly a child. A fall of 2.4 m onto reinforcement, formwork or a concrete bed causes head and spinal injury even without any collapse.

2. State the controls that must be in place before anyone enters the trench, and who should certify it.

Read the worked answer

Before entry, all of the following:

  • Either batter the sides back to a safe slope in this sandy silt - roughly 45 degrees, which for 2.4 m depth means about 2.4 m of horizontal set-back each side - or shore the trench with timber or steel sheeting and props designed for the depth, with the struts at not more than 1.2 m vertical spacing and checked daily and after every rain.
  • Remove the surcharge: spoil heaped at least 1 m from the crest, preferably 1.5 m, and reduced in height. No spoil, bricks, or materials at the edge.
  • Divert surface water away with a catch drain, and dewater with a pump rather than buckets so the bottom is not continuously softened. Never allow a worker to stand in water at the base of an unshored face to bail.
  • Provide a proper ladder, secured and extending at least 1 m above ground, within 7.5 m of every worker, and prohibit climbing the reinforcement.
  • Hard barricade at least 1 m high, set back about 1.5 m from the edge, with warning lights at night and a designated crossing point with a properly supported walkway.
  • Protect or cut back projecting reinforcement with caps.
  • Keep the tractor-trolley at least 3 m from the trench edge, with stop blocks, and stop all vehicle movement while workers are inside.
  • Helmets, safety shoes, gloves, and a lookout at the top with a rope.

Certification. A competent person - a supervisor trained and authorised for excavation work - must inspect and sign off the trench before first entry, at each shift start, and after rain or any ground movement. No sign-off, no entry.

3. Which statutory and documentary requirements apply, and what would you do about the afternoon brick delivery?

Read the worked answer

Statutory framework. Because this is building and other construction work, the Building and Other Construction Workers (Regulation of Employment and Conditions of Service) Act and the state rules apply: a safety officer or safety representative depending on worker numbers, a register of workers, welfare facilities, first aid, PPE, and competent supervision for excavation. IS 3764, the code of practice for excavation work, gives the technical requirements for shoring, set-back, access and inspection. If the work falls within factory premises, the Factories Act provisions on excavations also apply. Report any accident under the applicable rules.

Documents to have in place:

  • A written excavation safety checklist signed by the competent person for each inspection.
  • A simple permit-to-enter for the trench, with depth, support type, dewatering, access and sign-off.
  • The shoring design or a tabulated standard for the depth and soil type.
  • Worker induction records, PPE issue records, and an emergency plan with a rescue method, a stretcher, and a first-aid trained person on site.
  • A barricade and lighting inspection entry.

The brick delivery. Do not allow the trolley to approach while anyone is in the trench. Route it to a stacking area at least 3 m clear of the crest, use stop blocks, unload there, and carry bricks to the work face by hand or barrow after the trench has been checked and cleared. Vibration and wheel loading from a loaded trolley near the edge can trigger exactly the failure the shoring is meant to prevent.