RBSE Sec Voc Construction · Give each week a clear focus.

8 weeks · About 7 hours per week

Week 1

Construction Materials and Their Properties

  • Classify the main construction materials (bricks, stones, cement, aggregates, timber, steel, lime, mortar, concrete) by source, use and basic composition

  • State and explain the key properties of each material: strength, durability, porosity, water absorption, thermal conductivity and workability

  • Describe the standard tests used to judge quality (compressive strength, water absorption, soundness, fineness, bulking of sand) and the acceptance values you can recall

  • Build a one-page material-property comparison table from memory and mark every value you are unsure of for review

Your checkpoint

A handwritten or typed 2-page material property and test summary table covering at least 8 materials, with self-flagged uncertain entries

Week 2

Construction Materials and Their Properties & Building Construction Methods and Components

  • Explain cement types, grades and storage precautions, and the meaning of setting time and soundness

  • Describe concrete grades, nominal mixes, water-cement ratio effects and curing methods with typical durations

  • Identify the parts of a load-bearing and framed structure: foundation, plinth, wall, column, beam, slab, lintel, roof

  • Sketch a labelled section through a simple framed building showing each component and its function

Your checkpoint

A labelled cross-section sketch of a two-storey framed building naming at least 10 components with a one-line function for each

Week 3

Building Construction Methods and Components

  • Compare shallow and deep foundations and state when each is chosen, including soil bearing capacity basics

  • Describe brick masonry bonds (English, Flemish, stretcher, header) and the rules for mortar joints and bonding

  • Explain damp-proofing, plastering, pointing and flooring methods and where each is applied

  • Outline doors, windows, stairs and roof types with the terminology used in drawings and site talk

Your checkpoint

A set of four hand sketches: English bond corner, a stair with rise/tread labelled, a damp-proof course detail, and a simple roof truss

Week 4

Construction Drawing, Estimation and Costing

  • Read a simple plan, elevation and section and extract dimensions, levels and material notes correctly

  • Apply the standard measurement rules for earthwork, brickwork, concrete and plaster to a small single-room plan

  • Prepare a quantity sheet and a rate-based abstract of cost for that room

  • Identify common estimation errors such as double counting, wrong units and ignored wastage

Your checkpoint

A complete estimate for a single 3 m x 4 m room: quantity sheet plus abstract of cost with assumed rates, totalled and checked

Week 5

Surveying and Site Setting Out & Construction Tools, Equipment and Workshop Practice

  • Explain the principles and uses of chain/tape, compass and level surveying, and the difference between plane and geodetic surveying

  • Perform and record a simple level booking with rise-and-fall and height-of-instrument methods, including arithmetic checks

  • Describe setting out of a building line using the 3-4-5 method and offsets from a baseline

  • List the hand tools and equipment for masonry, carpentry, plumbing and concreting, and state the care and maintenance of each

Your checkpoint

A worked level-book page for a 6-station run with both reduction methods, arithmetic checks shown, and a sketch of a rectangular building set out by the 3-4-5 method

Week 6

Occupational Safety, Health and Environment & Construction Tools, Equipment and Workshop Practice

  • Identify site hazards and the correct control for each: excavation collapse, falls from height, scaffolding, electrical, manual handling and silica dust

  • State the purpose and correct use of PPE and the meaning of common safety signage categories

  • Describe first aid, fire extinguisher classes and emergency response steps on a construction site

  • Explain environmental controls for dust, noise, waste segregation and water runoff, and the workshop safety rules for hand and power tools

Your checkpoint

A one-page site hazard register listing 12 hazards with risk rating, control measure and responsible person

Week 7

Entrepreneurship, Employability and Trade Management

  • Explain the steps to start a small construction contracting business, including registration, licences and basic record keeping

  • Prepare a simple labour and material cost build-up for a small job and set a price that covers overhead and profit

  • Describe workplace rights, duties, communication and teamwork behaviours expected of a construction worker

  • Practise answering interview-style questions about your trade skills and safety habits aloud

Your checkpoint

A one-page business case for a small contracting job: cost build-up, quoted price, expected profit and a list of records to keep

Week 8

Practical Project Work and Viva & Construction Drawing, Estimation and Costing & Occupational Safety, Health and Environment

  • Rehearse the structure of a viva answer: state what you did, why, the tools used, the check applied and the result

  • Complete two timed mixed mock papers weighted to the domain percentages and score them honestly

  • Review every wrong answer and write the corrected fact in your own words

  • Prepare a project file summary covering methods, materials, measurements, safety and cost for your practical work

Your checkpoint

Two scored mock papers with an error log of at least 20 corrected items and a one-page project file summary

Milestones

Week 2: Score at least 70% on a self-made 25-question quiz on materials and building components, and produce the labelled building section without notes

Week 4: Complete the single-room estimate unaided in under 90 minutes with quantities within 10% of a recheck and correct units throughout

Week 6: Reduce a 6-station level run with both methods and passing arithmetic checks, and explain 10 hazard controls from the register without notes

Week 8: Average at least 65% across the two timed mock papers with no domain below 50%, and deliver a 5-minute viva rehearsal covering project, safety and cost