WBPSC AE Civil study plan
WBPSC AE Civil · Give each week a clear focus.
8 weeks · About 6 hours per week
Engineering Mechanics and Strength of Materials & Concrete and Steel Design (RCC and Steel Structures)
Derive and apply the equations for shear force and bending moment diagrams for simply supported, cantilever, and overhanging beams under point loads, UDL, and UVL, solving at least 10 numerical problems.
Compute principal stresses and maximum shear stress using Mohr's circle and analytical methods for combined loading, solving 5 problems.
Calculate deflection of beams using Macaulay's method and moment-area theorems for at least 4 standard cases.
Explain the limit state method of design for RCC beams in flexure, including partial safety factors and stress-strain curves, and solve 5 singly reinforced beam design problems.
Memorize key IS 456 clauses for minimum reinforcement, cover, and development length, and apply them to 3 design checks.
Your checkpoint
A handwritten formula sheet covering shear force, bending moment, deflection, and principal stress; plus a solved problem set of 25 numericals from domains 1 and 3 with step-by-step solutions.
Structural Analysis & Concrete and Steel Design (RCC and Steel Structures)
Analyze statically determinate trusses using method of joints and method of sections, determining member forces for 5 different truss configurations.
Compute slope and deflection of beams and frames using energy methods (unit load method) and solve 4 problems.
Design reinforced concrete columns (short and slender) under axial load and biaxial bending using IS 456 provisions, solving 4 problems.
Design a simply supported RCC slab and a cantilever slab according to IS 456, detailing reinforcement as per SP 34.
Explain the design of steel tension members and compression members as per IS 800:2007, including effective length and buckling class, and solve 3 problems each.
Your checkpoint
A design report for a one-way slab and a short column, including reinforcement detailing sketches and checks; plus a truss analysis problem set with 5 solved trusses.
Fluid Mechanics and Hydraulics & Geotechnical Engineering and Foundation Engineering
Apply Bernoulli's equation and continuity equation to solve 8 problems on pipe flow, venturimeter, and orifices.
Calculate friction loss in pipes using Darcy-Weisbach and Hazen-Williams equations, and design a simple pipe network for 3 cases.
Determine flow profiles in open channels using Manning's and Chezy's equations for rectangular, trapezoidal, and circular sections, solving 8 problems.
Classify soils using IS classification and compute effective stress, permeability, and seepage using Darcy's law and flow nets, solving 6 problems.
Compute consolidation settlement and time rate of consolidation using Terzaghi's 1D theory for 4 cases.
Your checkpoint
A solved problem portfolio containing 20 numericals from fluid mechanics and geotechnical engineering, with a summary sheet of key equations and assumptions.
Geotechnical Engineering and Foundation Engineering & Transportation Engineering (Highways, Bridges, Traffic)
Determine shear strength parameters from direct shear and triaxial tests, and compute bearing capacity using Terzaghi and IS methods for 5 foundation cases.
Design a shallow foundation (isolated footing) for a given load and soil profile, including settlement checks, and produce a sketch.
Calculate lateral earth pressure using Rankine's and Coulomb's theories for retaining walls, solving 4 problems.
Design flexible pavement using IRC:37 method for a given traffic and subgrade CBR, and compute stresses using Boussinesq's equations for 3 cases.
Explain the geometric design elements of highways (superelevation, transition curve, sight distance) as per IRC guidelines and solve 5 numericals.
Your checkpoint
A foundation design sheet for an isolated footing and a pavement thickness design calculation as per IRC:37, each with a neat sketch and all checks.
Hydrology and Water Resources Engineering & Environmental Engineering (Water Supply, Sanitary, Public Health)
Compute runoff using the rational method and SCS curve number method for 5 catchments, and estimate peak discharge using the unit hydrograph method.
Perform flood frequency analysis using Gumbel's distribution for a given annual peak data set of 20 years.
Design a water treatment plant unit: calculate coagulant dose, flocculation basin volume, and filter area for a given flow rate and water quality.
Design a septic tank and a soak pit for a rural household, and compute the BOD removal efficiency of a trickling filter for 3 cases.
Explain the working of an activated sludge process and compute F/M ratio, MCRT, and sludge volume index for a given set of parameters.
Your checkpoint
A water treatment plant flow diagram with sizing calculations for each unit (coagulation, flocculation, sedimentation, filtration, disinfection) for a 10 MLD plant.
Transportation Engineering (Highways, Bridges, Traffic) & Surveying and Geomatics
Compute earthwork quantities for road construction using the prismoidal formula and mass haul diagram for a 2 km stretch.
Design a flexible pavement overlay using Benkelman beam deflection data for 5 sections.
Solve 10 problems on curve setting using Rankine's and transition curves, and compute superelevation and extra widening.
Adjust a leveling traverse using the rise and fall method and the height of instrument method, and compute missing data for 5 cases.
Compute areas and volumes from contour maps using the trapezoidal and Simpson's rules for 4 cases.
Your checkpoint
A surveying field book extract with reduced levels for a 500 m profile, including a mass haul diagram and earthwork calculation table.
Construction Materials, Planning, Estimation and Management & Irrigation Engineering and Hydraulic Structures
Prepare a detailed estimate for a two-room residential building using the center line method and the long wall-short wall method, including a bill of quantities.
Compute the rate analysis for at least 5 items of work (earthwork, PCC, RCC, brickwork, plastering) as per current WBPWD schedule.
Design a gravity dam for stability (overturning, sliding, stress) for a given profile and seismic coefficient, and check with 3 load combinations.
Design a canal fall using the Bligh's creep theory and Khosla's theory for a given discharge and drop, and sketch the hydraulic jump profile.
Explain the construction planning techniques (CPM and PERT) and solve a network problem to determine critical path and project duration.
Your checkpoint
A complete estimate and rate analysis report for a small building, including a bar bending schedule for the RCC slab and beam.
General Studies, Aptitude and Engineering Ethics/Professional Practice
Review and summarize key provisions of engineering ethics, professional practice, and codes of conduct for civil engineers in India.
Solve 20 previous years' questions from general studies and aptitude sections, focusing on logical reasoning and quantitative aptitude.
Memorize important current affairs and static general knowledge topics relevant to West Bengal (dams, bridges, infrastructure projects).
Take a full-length mock test under timed conditions and analyze performance to identify weak areas for final revision.
Create a one-page quick revision sheet for each domain, highlighting formulas and key concepts.
Your checkpoint
A set of 12 one-page revision sheets (one per domain) and a mock test score report with an improvement plan.
Milestones
Week 2: Successfully solve at least 80% of the problems in a self-made test covering domains 1, 2, and 3, and score at least 60% in a 30-question quiz.
Week 4: Complete the foundation design and pavement design deliverables with all checks, and pass a 20-question quiz on domains 4 and 7 with 70% accuracy.
Week 6: Submit the surveying field book extract and earthwork calculation, and achieve at least 65% in a 50-question mixed test covering domains 1-9.
Week 8: Score at least 70% in a full-length mock test (100 questions) and complete all 12 revision sheets.