An ice storm has generated about 300 service requests in 48 hours. Six locations have downed power lines in trees, 18 streets are blocked by fallen trees, 12 trees or large limbs are on houses, and 40 hanging limbs are over sidewalks. Two houses have occupants with medical needs. The city has four in-house crews trained in arboriculture and two contract crews without line-clearance qualifications. The utility has its own line crews but is prioritizing substations. The city has a traffic control contractor available and a GIS work-order system. The mayor wants visible progress on residential streets, and the public is calling about debris pickup. The city must also document costs for possible federal reimbursement.

1. Establish a triage framework for the first 48 hours and rank the work categories. Justify the order.

Read the worked answer

Triage by life safety first, then access, then property, then debris. First priority: downed lines in trees. Treat all conductors as energized, establish a minimum 10 m exclusion zone, and request utility line crews; city crews must not perform line clearance. Second: trees on houses with occupants, especially the two medical-needs households; coordinate evacuation or shelter-in-place and stabilize only after utility clearance. Third: hanging limbs over sidewalks and streets with active traffic or pedestrian use. Fourth: streets blocked by fallen trees that are not involving conductors, prioritizing emergency routes and access for medical and fire services. Fifth: debris pickup and residential visual progress. This order is defensible because it addresses imminent injury and emergency access before aesthetics.

2. Assign the in-house and contract crews appropriately, including safety and traffic control.

Read the worked answer

In-house arboriculture crews should handle complex tree work near structures, hanging limbs, and trees that may involve concealed utilities after utility clearance is confirmed. Contract crews without line-clearance qualifications should not work within the utility exclusion zone; assign them to debris removal, chipping, and non-electrical street clearing under city supervision. The traffic control contractor should set closures and detours before any work begins. All crews need PPE, chainsaw protection, high-visibility clothing, and a tailboard briefing. Use the GIS system to dispatch by priority and to record addresses, hazards, crew hours, equipment, and disposal volumes. If a crew encounters a downed line, stop work, move upwind and uphill if possible, and call the utility.

3. What communication and documentation steps are needed during the response?

Read the worked answer

Public communication should state the priority order, warn residents to stay away from downed lines and hanging limbs, provide a debris-placement schedule, and give a realistic timeline. Use 311 scripts, social media, and door hangers for the medical-needs households. Tell residents not to approach crews working near conductors. Documentation for reimbursement should include work orders with date, time, location, hazard type, crew and equipment hours, photographs before and after, disposal tickets, and a daily cost summary linked to GIS. Record which work was emergency protective measures versus debris removal. Keep a decision log showing why resources were assigned to life-safety calls first; this supports both public accountability and eligibility review.