- Calibration versus adjustment
- Calibration documents an instrument's deviation from a traceable standard without changing it; adjustment physically alters the instrument to reduce that deviation. A calibration certificate reports as-found and as-left data.
- Span error formula
- Percent span error equals (indicated value minus true value) divided by calibrated span, times 100. A 0.5 mA error on a 16 mA span equals 3.1% span error.
- 4-20 mA percentage
- In a 4-20 mA loop, 4 mA is 0%, 12 mA is 50%, and 20 mA is 100% of span. Each 1 mA equals 6.25% of span.
- HART multidrop current
- HART multidrop mode fixes each transmitter's analog output near 4 mA and polls devices digitally by unique address. Only one device may be point-to-point with a live 4-20 mA signal.
- Four-wire RTD advantage
- A four-wire RTD connection uses separate current and voltage leads, canceling lead resistance. It provides the most accurate measurement, especially for low-resistance sensors or long cable runs.
- Thermocouple cold junction compensation
- Thermocouples measure the difference between hot and reference junctions, so the instrument must compensate for ambient terminal temperature. Without CJC, readings shift by the ambient temperature error.
- NAMUR NE43 fault levels
- NAMUR NE43 recommends signaling transmitter failure with output below 3.6 mA or above 21 mA. Normal operating range is 3.8 to 20.5 mA, leaving margin for fault detection.
- Valve bench set
- Bench set is the air pressure range that moves a spring-return actuator from closed to open without process force. It is set on the bench and verified during stroke testing.
- Two-wire loop power check
- With the transmitter disconnected, a 24 VDC loop supply should read about 24 V open-circuit. A low reading indicates a short, excessive load, or failed supply; infinite indicates an open.
- Loop divide-and-conquer
- Troubleshoot by splitting the loop at accessible points, such as the DCS terminal or junction box, and injecting a known mA signal to determine which side is faulty.
- Proportional band definition
- Proportional band is the error span, in percent of measurement range, that drives controller output through 100%. It equals 100 divided by proportional gain.
- Integral action eliminates offset
- Integral action accumulates error over time and moves output until error reaches zero. Too much integral gain causes overshoot and oscillation; integral windup occurs when output saturates.
- Derivative action noise
- Derivative acts on rate of change and anticipates future error, but it amplifies measurement noise. It is normally avoided on noisy flow loops and often applied only to temperature.
- Ziegler-Nichols PID settings
- From ultimate gain Ku and ultimate period Pu, Ziegler-Nichols PID gives Kc = 0.6 Ku, Ti = Pu/2, and Td = Pu/8, producing quarter-amplitude decay.
- Cascade control rule
- In cascade control the master controller's output becomes the slave's setpoint. The slave loop must be at least three to five times faster than the master loop for stable benefit.
- Dead time and controllability
- Dead time is transport delay between a controller output change and measured response. Large dead time relative to the process time constant makes a loop difficult to control with PID.
- Bumpless transfer
- Bumpless transfer prevents an output jump when switching between manual and automatic. The controller initializes its integral term so the computed output matches the current output.
- Equal percentage valve characteristic
- An equal-percentage valve changes flow by a constant percentage per unit of stem travel. It compensates for installed characteristics that otherwise become linear at high pressure drop.
- Loop check purpose
- A loop check verifies the complete path from field instrument through wiring, I/O, controller, and final element. It confirms tag, polarity, scaling, alarms, and valve stroke.
- Cold versus hot loop check
- A cold loop check uses simulated signals with process equipment de-energized. A hot loop check repeats verification with live process or energized equipment before handover.
- PSSR requirement
- A pre-startup safety review confirms construction matches design, procedures are ready, training is complete, and safety systems function before introducing hazardous chemicals under OSHA PSM.
- Factory acceptance test
- A factory acceptance test runs the control system at the vendor's facility against approved specifications. It verifies hardware, software, graphics, alarms, and I/O before shipment.
- Punch list classification
- Punch list items are categorized by severity: A items block start-up, B items must be fixed before acceptance, and C items are minor and can be closed later.
- Cause and effect testing
- Cause and effect testing injects each input condition and verifies every specified output action, including trips, alarms, and interlocks, against the approved cause and effect matrix.
- Instrument air commissioning
- Before instrument air is used, verify dew point, oil content, and pressure at the header. Blow down lines and confirm filter regulators and airsets are installed and set.
- Cost performance index
- CPI equals earned value divided by actual cost. A CPI below 1.0 means the project is over budget; above 1.0 means under budget for work performed.
- Schedule performance index
- SPI equals earned value divided by planned value. An SPI below 1.0 indicates the project is behind schedule; above 1.0 indicates ahead of schedule.
- Management of change
- MOC is a documented review of proposed changes to process, equipment, or procedures to assess safety, environmental, and operational impacts before implementation and update documentation.
- LOTO six-step procedure
- Lockout/tagout requires preparation, notification, shutdown, isolation, lock and tag application, release of stored energy, verification, and restoration. It protects workers from unexpected energization.
- ISA-84 safety lifecycle
- ISA-84 and IEC 61511 define a safety instrumented system lifecycle: hazard assessment, SIL determination, design, installation, validation, operation, maintenance, and decommissioning.
- Calibration traceability
- Traceability links an instrument's calibration to national or international standards through an unbroken chain of documented comparisons, each with stated uncertainty.
- Span of control
- Span of control is the number of subordinates reporting directly to one supervisor. It affects communication, supervision quality, and organizational layers.