ISSMP study materials
ISSMP study resources

ISSMP cheat sheet

ISSMP · Keep the key ideas within reach.

Quick reference

Leadership and Business Management

  • Governance roles: the board sets risk appetite, executive management sets risk tolerance, and the security manager implements controls; material variance is escalated to the board.

  • Security budget formulas: ALE = SLE × ARO; ROI = (benefit − control cost) ÷ control cost.

  • RACI rule: exactly one role is accountable per activity; responsibility may be shared, consultation occurs before the decision, and informing occurs after.

  • Risk indicator thresholds: green = within appetite, amber = approaching tolerance, red = exceeds tolerance and requires escalation.

  • Business case components: problem, options, cost, benefit, risk, and recommendation; approve only when benefit exceeds cost and residual risk is within appetite.

  • Steering committee: cross-functional membership; owns policy approval, investment prioritization, and conflict resolution; meets at a defined cadence.

  • Due care is reasonable protection; due diligence is ongoing verification; absence of either increases negligence exposure.

  • Span of control: narrow spans fit complex or high-risk work; wide spans fit standardized, low-variability tasks.

Quick reference

Systems Lifecycle Management

  • Lifecycle phases: requirements, design, build, test, deploy, operate, retire; each phase has entry and exit criteria.

  • Security gate rule: production deployment requires documented security acceptance; unresolved critical findings block release.

  • Traceability matrix maps requirements to design, controls, and tests; an unmapped requirement is unverified.

  • Change control: normal changes require approval; emergency changes require retrospective review and documentation.

  • Separation of duties: developers do not hold production write access; the person who writes code does not approve its release.

  • Configuration baseline is the approved state; drift is any difference between actual and baseline and is handled through change management.

  • Secure disposal: sanitize media according to data classification before reuse or retirement; retain a destruction record.

  • Authorization to operate: the authorizing official accepts residual risk based on assessment evidence; continuous monitoring supports maintenance.

Quick reference

Security Compliance Management

  • Compliance hierarchy: law and regulation, then standard, then policy, then procedure, then guideline; lower levels cannot weaken higher levels.

  • Policy exception: documented, time-bound, risk-accepted by the owner, with a review or remediation date; permanent exceptions are not valid.

  • Control testing: design effectiveness asks whether the control could work; operating effectiveness asks whether it actually worked over the period.

  • Sample size rises with population size, required confidence, and lower tolerable error rate.

  • Audit finding structure: condition, criteria, cause, effect, recommendation; each element is needed for a defensible finding.

  • Evidence retention: follow legal and regulatory schedules; evidence must be dated, attributable, and protected from alteration.

  • Gap analysis compares current controls with required obligations; prioritize by legal exposure and risk.

  • Third-party review: right-to-audit clause, independent report review, and reassessment frequency based on data sensitivity and access.

Quick reference

Risk Management

  • Risk score = likelihood × impact; scales must be defined so ratings are consistent across assessors.

  • SLE = asset value × exposure factor; ALE = SLE × ARO.

  • Treatment options: mitigate, transfer, avoid, accept; residual risk must be within risk appetite.

  • Risk register fields: asset, threat, vulnerability, likelihood, impact, score, owner, treatment, due date.

  • Risk appetite is the broad willingness to take risk; risk tolerance is the acceptable variation around a specific objective.

  • Control cost is justified when annual control cost is less than the reduction in ALE.

  • Monte Carlo analysis models ranges and correlations to produce a loss distribution; it is preferred when single-point estimates hide uncertainty.

  • Third-party tiering uses data sensitivity, system access, and business criticality; higher tiers require deeper due diligence.

Quick reference

Threat Intelligence and Incident Management

  • Intelligence cycle: requirements, collection, processing, analysis, dissemination, feedback; feedback restarts the cycle.

  • IoCs are atomic and perishable; TTPs are behavioral and durable; detection engineering prioritizes TTPs.

  • Pyramid of Pain order: hash, IP address, domain, network artifact, tool, TTP; higher levels are harder for adversaries to change.

  • Incident response phases: preparation, detection and analysis, containment, eradication, recovery, lessons learned.

  • Severity = impact × urgency; escalation triggers include confirmed data exfiltration, ransomware, and critical service outage.

  • Chain of custody records who handled evidence, when, where, and why; hash evidence and preserve the original.

  • Containment decision: isolate affected hosts while preserving evidence; avoid destructive actions before capture.

  • Metrics include MTTD and MTTR; post-incident corrective actions are tracked to closure.

Quick reference

Contingency Management

  • BIA identifies critical processes, dependencies, and downtime impact; it establishes RTO, RPO, and MTD before strategy selection.

  • RTO is maximum acceptable downtime; RPO is maximum acceptable data loss; MTD is maximum tolerable disruption; RTO must be less than MTD.

  • Recovery site options: hot, warm, cold, reciprocal, and cloud failover; selection depends on RTO, RPO, and cost.

  • Backup rule 3-2-1: three copies, two media types, one offsite; restore testing proves recoverability.

  • Test types: tabletop, walkthrough, simulation, full failover; realism increases with process criticality.

  • Disaster declaration requires an authorized role and predefined criteria; the declaration starts plan activation and communications.

  • Crisis communications: predefined spokespeople, contact lists, and status templates; public statements avoid speculation.

  • Plan maintenance: review at least annually and after major change; use version control and role-based distribution.