Wireline Operations

Wireline Operations tests well control for slickline, electric line, and braided line. The exam expects correct lubricator sizing, BOP and grease-injection practice, and recognition that the wire is not a barrier.

Core rules

  • The lubricator must be pressure-rated for the maximum expected surface pressure and long enough to contain the complete toolstring plus a safe allowance.
  • The wireline BOP stack usually provides pipe rams, shear/seal rams, and a grease-injection head or stuffing box. Test before running in.
  • For braided or electric line, grease injection maintains a seal around the moving wire; monitor injection pressure and return flow.
  • The well must be shut in and pressure equalized before the lubricator is opened.
  • Depth control depends on measured toolstring length and wire depth; do not rely on guesswork.

Worked example

A toolstring measures 8.4 m. The available lubricator is 7.5 m from the wireline BOP to the top connection. It cannot be used. The minimum lubricator length should be at least toolstring length plus about 0.5 m for the rope socket and clearance, so a 9 m lubricator is required. If a longer lubricator is unavailable, break the toolstring into a shorter assembly or use a different deployment method; do not run with the toolstring protruding into the stuffing box.

Traps

  • Running a toolstring longer than the lubricator.
  • Opening the well before equalizing.
  • Losing grease injection and continuing to move wire.
  • Assuming the wire itself seals the well.
  • Shearing wire without confirming the shear ram and wire size.