The Kitchen Fire, the Penalty Clause and the 'Consultancy' Invoice

Tawjihi Business Field · Put your knowledge to work in context.

All case studies

The Kitchen Fire, the Penalty Clause and the 'Consultancy' Invoice

Faris Catering signed a six-month contract to supply a hotel with 300 meals a day at 4.50 dinars per meal. The contract states that any day on which deliveries are short or late incurs a penalty of 2% of that month's contract value per day, and it excuses liability for 'events beyond the supplier's reasonable control'. Monthly contract value is 40,500 dinars. In month three a fire destroyed Faris's kitchen and no meals were delivered for nine days. Investigators found the fire started in a gas cylinder that Faris had twice been warned to replace. The hotel bought replacement meals at 5.20 dinars each for those nine days and deducted 7,290 dinars from the next invoice. In the same week the hotel's purchasing manager asked Faris to issue a monthly invoice for 500 dinars of 'consultancy services' payable to the manager personally, hinting that renewal depends on it.

1. Will the force majeure wording excuse Faris for the nine missed days? Give your reasoning, including the effect of the prior warnings.

Read the worked answer

No - the clause is unlikely to protect him. Force majeure requires an event that is unforeseeable, outside the party's control, and unavoidable despite reasonable precautions. The fire fails at least two of these tests:

  1. Control and foreseeability. A gas cylinder is part of Faris's own equipment and premises. A known defect in his own plant is not an external event; it is an internal failure of maintenance.
  2. Prior warnings make it worse, not neutral. He was told twice to replace the cylinder. That establishes knowledge of the risk and a failure to mitigate, which is exactly the conduct the clause does not excuse. A court would read 'beyond reasonable control' as excluding self-inflicted harm through negligence.
  3. Causation is direct. The nine lost days flow from that cylinder, not from an unrelated disaster (flood, civil unrest, government closure) of the kind such clauses are written for.

Consequence: Faris is in breach for nine days and the hotel may claim its loss, whether through the penalty clause or as damages. His best argument is not that he is excused, but that the penalty is unenforceable or reducible - the next task. Practical lesson for the future: a genuine force majeure clause should list covered events, require notice within a set number of days, and be backed by insurance (business interruption cover) - none of which is mentioned here.

2. Quantify the hotel's actual loss for the nine days and assess whether the 7,290-dinar deduction is defensible.

Read the worked answer

The hotel's measurable loss - cost of cover

  • Contract price: 300 × 4.50 = 1,350 per day → 9 days = 12,150
  • Replacement cost: 300 × 5.20 = 1,560 per day → 9 days = 14,040
  • Extra cost = 14,040 − 12,150 = 1,890 dinars (equivalently 300 × 9 × 0.70)

The deduction

  • Penalty rate: 2% × 40,500 = 810 dinars per day → 9 × 810 = 7,290 dinars, i.e. 18% of a full month's contract value for missing nine days (30% of deliveries).
  • The deduction exceeds the proven loss by 7,290 − 1,890 = 5,400 dinars.

Is 7,290 defensible? As a liquidated-damages estimate, no. It is out of all proportion to the loss it is meant to pre-estimate, and a clause that applies regardless of whether one meal or all meals are missing cannot be a genuine forecast of harm. In many civil-law systems modelled on the Egyptian and Jordanian civil codes, a court may reduce an agreed penalty that is manifestly excessive to the level of the actual damage; in common-law systems a clause this punitive risks being struck down as a penalty rather than enforceable liquidated damages. Faris should not argue the clause is void in principle - he should argue the amount.

Position to take: accept 1,890 for cost of cover, invite the hotel to prove any further loss (cancelled functions, compensation to guests) with evidence, and request a credit note for the difference. A settlement around 1,890–2,500 protects the relationship better than litigating 5,400.

3. Advise Faris on the purchasing manager's request for a 500-dinar monthly 'consultancy' invoice. Cover legal exposure, the business consequences, and what he should do instead.

Read the worked answer

What this actually is. A payment to the counterparty's decision-maker, disguised as an invoice for services nobody will perform, in exchange for a contract award. That is commercial bribery, whatever the document is called. The label changes the paperwork, not the substance.

Legal exposure

  • Bribery/corruption: in most jurisdictions, offering or agreeing to give an advantage to an employee to influence a business decision is a criminal offence for both giver and taker; Faris would be a principal, not a victim.
  • False invoice: the 500 dinars has no underlying service, so the invoice misstates a transaction. That is a second, separate problem - tax and documentary fraud - and it would be booked in Faris's own accounts, leaving a permanent record.
  • Contract risk: a contract procured this way is voidable and unenforceable at the hotel's option; if the hotel later discovers it, Faris loses the contract, the revenue already earned and possibly the right to sue for unpaid invoices.
  • Personal exposure: the manager can end the arrangement at any time and threaten disclosure, converting a business relationship into ongoing blackmail.

Business consequences The 500 a month is not the cost. The real cost is that renewal now depends on one individual's private interest rather than on Faris's performance; if that manager leaves or is investigated, the contract leaves with him. It also sets a precedent: the next renewal request will be larger.

What Faris should do

  1. Refuse clearly and in writing, without accusing: 'We are not able to issue invoices for services not rendered; our pricing already covers all legitimate costs.'
  2. Document the request with dates and, where lawful, a contemporaneous note. Do not record private conversations in breach of local law.
  3. Escalate through a legitimate channel - the hotel's general manager or compliance function, or the tender owner - and ask for the contract to be awarded on published criteria. If no such channel exists, decline to bid rather than comply.
  4. Reinforce his own side: adopt a written policy that no employee may offer or accept gifts or payments to influence a decision, so the answer is the company's, not a personal judgement.
  5. Compete on value: the nine-day fire already exposed service risk, so the stronger counter to any renewal threat is an improved continuity plan and transparent pricing - evidence the hotel can defend internally.