CCI study materials
CCI study resources

CCI: Leadership, Implementation, and Change Management

CCI · Work through your exam, one topic at a time.

All guide sections

Leadership, Implementation, and Change Management

Leadership, implementation, and change management tests how informatics projects are governed, delivered, adopted, and sustained. Expect questions on charters, stakeholders, change models, go-live readiness, and benefits realization.

Governance and planning

  • A project charter states scope, sponsor, goals, success measures, and constraints. A steering committee resolves priorities and risks.
  • Stakeholder analysis maps influence and interest. A RACI matrix clarifies who is responsible, accountable, consulted, and informed.
  • The project plan includes risk register, communication plan, workflow validation, integration and regression testing, training, and cutover.

Change and adoption

  • Kotter's eight steps move from urgency to anchoring change. ADKAR focuses on awareness, desire, knowledge, ability, and reinforcement.
  • Rogers's diffusion curve describes innovators, early adopters, early majority, late majority, and laggards; tailor engagement accordingly.
  • Go-live requires a command center, super-users, at-the-elbow support, downtime procedures, and escalation paths. Optimization continues afterward.

Worked example

A CPOE go-live has 70% of physicians trained one week out. Reasoning: readiness criteria include validated workflows, approved order sets, device availability, and training thresholds. The team delays the go-live by two weeks, targets high-volume prescribers, and adds at-the-elbow support. It tracks adoption and order-entry safety events daily.

Traps

Treating go-live as the finish line; skipping stakeholder analysis; ignoring resisters; over-customizing; no benefits tracking.