ERA Cadre Civil Servant Exam · Put your knowledge to work in context.

All case studies

Eighteen Projects, Three Engineers

You head a district road office with 28 approved posts, 19 filled, and only three engineers. The annual plan lists 18 maintenance projects, but supervision capacity allows 11. Two staff members are frequently absent; one is the staff union representative. Community leaders are demanding a culvert on a school route that is not in the plan. A utility company has told you it will lay water pipes along a road you rehabilitated last year; the coordination meeting was missed because your office did not receive the invitation. The first-half budget release is 60% of the annual allocation, and staff morale is low because per diem claims from the previous quarter remain unpaid. The regional bureau wants a monthly performance report in two weeks.

1. How should you plan and allocate the 18 projects when only 11 can be supervised?

Read the worked answer

Rank all 18 projects by safety risk, traffic, condition and readiness. Group projects geographically so one engineer can supervise several nearby sites; use community-level supervision or a consultant for low-risk routine work; and set a written supervision plan with hold points. Do not start projects that cannot be supervised, because uncontrolled starts create quality and safety failures. Communicate the ranked list to staff and stakeholders. For the seven deferred projects, state the reason and the re-entry criteria.

The 60% budget release requires cash-flow planning: prioritize commitments that can be paid, avoid awarding contracts without funds, and request early release for critical items. The monthly report should show planned versus supervised projects and the rationale for deferrals.

2. How should you address absenteeism, low morale and the vacant posts?

Read the worked answer

Apply the HR policy consistently. Meet the two absent staff, document patterns, ask about causes such as health, transport or care responsibilities, and agree improvement plans. The union representative has the same obligations as others; handle the case through the supervisor and HR, not informally, to avoid a labour dispute. Morale: unpaid per diem is a legitimate grievance. Audit the claims, pay valid ones promptly, and explain any delay. Publish a simple status tracker. Recognize good work and involve staff in prioritization.

With three engineers, delegate routine inspections with training and checklists, but keep professional sign-off with the engineers. Escalate the vacant posts with a workload case rather than silently absorbing the gap.

3. How should you handle the utility company and the community culvert request?

Read the worked answer

Utility: Convene an urgent coordination meeting with the water company, the municipality and the contractor. Agree a joint trenching plan, reinstatement standards and a schedule before the road is resealed. Seek cost recovery for damage to the new pavement and a written undertaking. The missed meeting is a process failure; set up a standing coordination forum and a single point of contact.

Community culvert: Assess the request technically: catchment, flow, school-route safety and cost. If justified, add it to the next plan or seek a small-scale budget; if not, explain the criteria and offer an alternative. Do not promise what is not funded. The monthly report should include the deferral list, the utility agreement and the HR actions, so the regional bureau sees a managed process rather than a list of excuses.