Engineer Electric Work flashcards
Engineer Electric Work · Build recall with a focused review session.
33 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Ohm's law
- Voltage equals current times resistance (V = I·R). In AC circuits, RMS values and impedance replace resistance, so V = I·Z and phase angle matters.
- Three-phase power formula
- For a balanced three-phase load, active power P = √3·V_LL·I_L·cosφ, where V_LL is line-to-line voltage, I_L is line current, and cosφ is power factor.
- Resonant frequency
- A series or parallel LC circuit resonates at f_r = 1/(2π√(LC)). At resonance, inductive and capacitive reactances cancel, leaving only resistance in the series case.
- Power factor correction kvar
- Capacitor reactive power needed equals P·(tanφ1 − tanφ2), where P is active power and φ1, φ2 are the pre- and post-correction power factor angles.
- Per-unit impedance
- Per-unit impedance is actual impedance divided by base impedance, where Z_base = V_base²/S_base. Per-unit values stay continuous across ideal transformers, simplifying calculations.
- Heat rate
- Heat rate is fuel heat input per unit of net electrical output, often in kJ/kWh. It equals 3600 divided by overall thermal efficiency, so lower heat rate means better plant performance.
- Surge impedance loading
- SIL equals line-to-line voltage squared divided by surge impedance. A line loaded near SIL has a nearly flat voltage profile and minimal reactive power flow.
- Radial distribution system
- A radial system has a single supply path from source to load. It is inexpensive and simple but offers no alternate path, so any upstream fault interrupts all downstream customers.
- Short-circuit fault level
- Fault level at a bus approximates V²/Z_thévenin or S_base/Z_pu. Switchgear interrupting rating must exceed the calculated maximum fault current at its location.
- Induction motor slip
- Slip s = (n_s − n_r)/n_s, where n_s = 120f/p is synchronous speed and n_r is rotor speed. Rotor frequency equals s·f, and slip increases with load.
- Star-delta starting
- Star-delta starting connects the motor in star during run-up, reducing phase voltage and therefore starting current and torque to one-third of direct-on-line values.
- Transformer maximum efficiency
- A transformer reaches maximum efficiency when copper loss equals core loss. Core loss is constant with load, while copper loss varies with the square of load current.
- Synchronous speed
- Synchronous speed n_s = 120f/p, where f is supply frequency and p is the number of poles. It is the speed of the rotating magnetic field in AC machines.
- DC machine EMF
- Generated EMF E = (p·Φ·N·Z)/(60·a), where p is poles, Φ is flux per pole, N is speed in rpm, Z is conductors, and a is parallel paths.
- Differential protection
- Differential protection compares currents entering and leaving a protected zone. It trips on the difference current, giving fast, selective protection for transformers, generators, and busbars.
- Distance relay zones
- Distance relays measure impedance Z = V/I and set zones as percentages of line impedance. Zone 1 covers most of the line, while Zone 2 and 3 provide time-delayed backup.
- Symmetrical components
- Unbalanced three-phase quantities are resolved into positive, negative, and zero sequence networks. Zero-sequence current flows only where a ground return path exists.
- Coordination time interval
- The coordination time interval is the intentional time margin between downstream and upstream protective device trips, typically 0.2 to 0.4 seconds, ensuring selective operation.
- Critical clearing time
- Critical clearing time is the longest fault duration for which a power system remains transiently stable. Longer faults cause loss of synchronism between generators.
- Design current and cable capacity
- Installation design requires I_b ≤ I_n ≤ I_z: design current no greater than protective device rating, and device rating no greater than cable current-carrying capacity.
- Adiabatic equation
- The adiabatic equation S = √(I²t)/k checks that a protective conductor survives fault current I for time t, where k depends on conductor material and insulation.
- Disconnection condition
- Automatic disconnection of supply requires Z_s ≤ U_0/I_a, where Z_s is earth fault loop impedance, U_0 nominal voltage, and I_a the current tripping the device in time.
- Voltage drop limits
- Common design limits are 3 percent voltage drop for lighting and 5 percent for other loads, measured from the origin of the installation to the load.
- Cable derating factors
- Tabulated cable current capacity is reduced by factors for ambient temperature, grouping of circuits, thermal insulation, and installation method such as buried or in conduit.
- IEC 60364
- IEC 60364 is the international standard for low-voltage electrical installations. It covers protection, earthing, conductor sizing, and verification requirements for building electrical systems.
- Hazardous area zones
- IEC 60079 classifies gas atmospheres as Zone 0, 1, or 2 by likelihood of explosive mixture, and dust as Zone 20, 21, or 22, determining required equipment protection.
- Earthing system types
- IEC 60364 defines TN-S, TN-C, TN-C-S, TT, and IT systems by how neutral and protective conductors connect to earth, affecting protective device and RCD requirements.
- NFPA 70E
- NFPA 70E is the US standard for electrical safety in the workplace. It covers arc flash risk assessment, approach boundaries, PPE selection, and energized work permits.
- Lockout/tagout procedure
- LOTO requires isolating the energy source, applying locks and tags, verifying absence of voltage with a tested instrument, and applying temporary protective grounds before work.
- ISO 50001
- ISO 50001 is the international standard for energy management systems. It requires an energy baseline, energy performance indicators, and continual improvement of energy performance.
- SF6 greenhouse impact
- Sulfur hexafluoride is a potent greenhouse gas with a global warming potential around 23,500 times that of carbon dioxide, so recovery and leak reporting are regulated.
- Cost performance index
- CPI equals earned value divided by actual cost. A CPI below 1.0 means the project is spending more than the value earned, indicating a cost overrun.
- Critical path
- The critical path is the longest duration path through the project network. It has zero total float, so any delay on it delays the whole project.