Fixed-Fee Portal Engagement and the Late CIO Scope Demand

Certified Technical Consultant · Put your knowledge to work in context.

All case studies

Fixed-Fee Portal Engagement and the Late CIO Scope Demand

Northwind Freight, a 900-employee logistics provider, signed a fixed-fee engagement of USD 186,000 over 14 weeks to replace a legacy shipment-tracking portal. The statement of work names four deliverables: the portal, carrier API integration, a reporting pack, and cutover support. Your team is four consultants. In week 3 the client's IT sponsor resigned; in week 5 a new CIO joined. At the week-6 steering committee the CIO states that the portal "must also do EDI 856 advance ship notices and multi-currency invoicing" and that these are "obviously part of a shipment portal." Neither item appears in the SOW, and your estimate to add both is 240 person-hours plus a 3-week delay. Burn is 58% against 43% of deliverables accepted. The client has paid invoice 1 only. The account executive warns that Northwind is a reference account for a larger sister-company deal. The CIO asks you to confirm the additions will be absorbed at no extra cost by the end of the week.

1. What do you do in the next five business days, and what exactly do you say at the steering committee?

Read the worked answer

Do not accept or refuse in the room. Acknowledge the business need, then state that you cannot confirm commercial impact without an impact assessment and that you will bring one back within three business days. This is not evasion; it prevents an undocumented verbal commitment from becoming a de facto contract change.

Actions:

  • Re-read the SOW and proposal assumptions; confirm in writing that EDI 856 and multi-currency are not in scope and were not priced.
  • Have the delivery lead and architect size the work bottom-up; validate the 240-hour figure against the actual integration and FX requirements rather than reusing the earlier rough estimate.
  • Log the request in the decision log and RAID log the same day, with the CIO named as requester and the date.
  • Brief your engagement partner and the account executive before the next client contact so the relationship owner and delivery lead are not contradicting each other.
  • Ask the CIO to submit the request through the change-control form, and confirm that no EDI or multi-currency build work starts until it is signed.

At the steering committee, separate facts from interpretation: what the SOW covers, what has been accepted, current burn versus completion, and the quantified impact of the two items. Avoid framing it as the client's fault; frame it as protecting the go-live date and the quality of the four committed deliverables. Reference-account pressure is a commercial consideration for your firm, not a reason to absorb unpriced work silently.

2. The CIO refuses a change order and says the sister-company deal depends on Northwind being happy. What commercial options do you put to your engagement partner, and what do you recommend?

Read the worked answer

Present four options with explicit margin and risk consequences.

  1. Absorb at no cost. Rejects on economics: 240 unpriced hours against a 58% burn at 43% completion already threatens the fee. It also sets a precedent for the remaining eight weeks and trains the client that late requests are free.
  2. Full change order. Price the 240 hours and the 3-week extension, with a revised milestone and invoice schedule. Cleanest commercially, but risks the relationship and the reference.
  3. Scope trade. Keep the fee and date by removing or deferring something of comparable value, for example the reporting pack to phase 2 or reducing cutover support from four weeks to two. This preserves the relationship while protecting margin.
  4. Phased addition. Deliver EDI 856 before go-live only if the carrier mandates it; defer multi-currency to a post-go-live phase at a pre-agreed rate. This reduces the delay to roughly one week and caps exposure.

Recommend option 4 combined with option 3, with a not-to-exceed cap and a written assumption list. Rationale: it addresses the CIO's stated business driver, keeps the reference intact, and converts an open-ended demand into a bounded, priced commitment. Before proposing it, reforecast estimate-at-completion honestly; the 58% versus 43% gap suggests either an estimating error or unrecovered effort, and the partner needs that number to decide whether any absorption is even affordable. Whatever is chosen, the decision and its rationale belong in writing, signed by someone with budget authority.

3. What artifacts and stakeholder steps must exist by the end of week 7, and why does each matter?

Read the worked answer
  • Revised SOW or signed change order naming scope, fee, dates, and assumptions. This is the only artifact that changes the contractual baseline.
  • Impact assessment with hours by role, elapsed delay, and effect on each of the four deliverables. It converts a verbal demand into a decision the CIO can own.
  • Decision log entry recording the request, the options presented, the chosen option, the decision-maker, and the date. It is the defense if memories diverge at invoice time.
  • Re-baselined plan and milestone schedule, including the new configuration and UAT windows. A fee change without a date change usually just moves the overrun later.
  • Updated RAID log, adding the sponsor turnover as a realized risk and the new CIO's expectations as an assumption to validate.
  • Steering committee minutes issued within 48 hours, with an explicit "decisions required" section.
  • Invoice and cash plan aligned to acceptance, not elapsed time, given that only invoice 1 has been paid.
  • Internal escalation note to the engagement partner and finance, covering margin exposure and the reference-account consideration.

Stakeholder steps: map the new CIO's influencers, including the CFO who controls the budget and the operations lead who owns the carriers. Meet the CFO separately to explain the cost of the two additions in business terms, and confirm who besides the CIO can approve a change. Do not let the account executive negotiate scope informally; agree one channel for all change requests and restate it in the next steering pack.