- LSLBC license threshold
- Louisiana requires a State Licensing Board for Contractors license for projects of $50,000 or more in labor and materials, covering commercial, public, and residential work above that value.
- Qualifying party
- An individual who passes the LSLBC exam and is regularly employed by the firm to qualify its license; one person may qualify only one active license at a time.
- Major classification
- The broad category on an LSLBC license such as Building Construction, Highway, Street and Bridge, Heavy Construction, Municipal and Public Works, or Residential Construction that defines authorized scope.
- Residential contractor threshold
- Louisiana residential contractors must be licensed for residential projects of $75,000 or more; the Residential classification covers one- and two-family dwellings and related structures.
- Private Works Act lien deadline
- A claimant must record a Statement of Claim or Privilege within 60 days after the last day of the month in which the claimant last performed work or furnished materials.
- Notice of Contract
- A document the owner records before work begins that establishes the contract price and limits the owner's liability to the amount stated in that recorded notice.
- Public works bond claim notice
- On Louisiana public works, a claimant must give written notice to the contractor and the public entity within 45 days after the last day of the month in which the work was done.
- Retainage release timing
- On Louisiana public works, the owner generally withholds 5% of each progress payment and must release retainage within 45 days after substantial completion or acceptance.
- Residential written contract rule
- Louisiana requires a written contract for residential work over $7,500 that includes the license number and specific notices; violations can result in treble damages and license action.
- Contractor sales tax on materials
- A contractor is the consumer of materials incorporated into immovable property, so the contractor owes state and local sales/use tax and cannot claim a resale exemption for those materials.
- Unlicensed contracting penalty
- Performing work requiring an LSLBC license without one can result in fines, civil penalties, loss of lien rights, and an order to stop work or disgorge compensation.
- LSLBC exam format
- The Louisiana contractor exam is computer-based and multiple-choice, with a Business and Law portion plus a trade portion specific to the requested classification; confirm current bulletins for passing scores.
- Building Construction classification
- An LSLBC major classification authorizing construction of commercial, industrial, and institutional buildings, including structural, architectural, and related site work within the licensed scope.
- Highway, Street and Bridge
- An LSLBC classification covering roads, streets, bridges, drainage, paving, and related public infrastructure work; it does not authorize building construction outside that scope.
- Concrete 28-day strength
- Design compressive strength f'c is verified by cylinder breaks at 28 days; slump, air content, and temperature are field acceptance tests taken during placement.
- Concrete sampling frequency
- Strength specimens are typically taken at least once per 150 cubic yards of concrete placed and at least once per day of placement, per ACI sampling practice.
- Turn-of-nut method
- A high-strength bolt pretensioning method where the nut is rotated a specified fraction of a turn after snugging, with the amount depending on bolt length and diameter.
- Proctor compaction test
- A laboratory test that determines the maximum dry density and optimum moisture content of soil; field compaction is specified as a percentage of that maximum dry density.
- Nuclear density gauge
- A field device that measures in-place soil density and moisture by radiation attenuation, used to verify compaction against the Proctor maximum dry density.
- OSHA fall protection trigger
- Under OSHA construction standards, employees exposed to falls of 6 feet or more above a lower level must be protected by guardrails, safety nets, or personal fall-arrest systems.
- Ladder extension above landing
- A portable ladder used for access must extend at least 3 feet above the landing surface, and the top must be secured against displacement.
- Trench protective system
- Any trench 5 feet or deeper requires sloping, shoring, or shielding unless the excavation is entirely in stable rock; a competent person inspects daily.
- Spoil pile setback
- Excavated material and equipment must be kept at least 2 feet back from the edge of a trench to reduce surcharge loading and prevent cave-in.
- NEC conductor ampacity
- Conductor ampacity from NEC tables must be adjusted for ambient temperature and conduit fill, and overcurrent protection may not exceed the adjusted ampacity.
- Fixture unit sizing
- Plumbing drain, waste, and vent pipes are sized using fixture-unit tables, while water supply sizing uses fixture units combined with pressure-loss calculations.
- Gas pipe longest-length method
- Gas piping is sized using tables keyed to the longest run from meter to outlet, corrected for gas specific gravity and allowable pressure drop.
- Structural steel bolt inspection
- Inspection of pretensioned bolted joints verifies the specified minimum tension was achieved using the approved method and that correct bolt grade and grip length were used.
- Municipal and Public Works
- An LSLBC classification authorizing construction of public facilities and infrastructure such as water, sewer, and municipal improvements, subject to public bidding and bonding rules.
- Working outside classification
- Performing work outside the scope of the license's major classification or subclassification is a licensing violation that can result in fines, stop-work orders, and license suspension.
- Competent person
- An individual capable of identifying existing and predictable hazards and authorized to take prompt corrective measures, required for daily excavation inspections and fall protection planning.
- Louisiana public bid requirement
- Public entities must advertise for bids and award to the lowest responsible bidder; bids require a bid bond and the successful bidder must furnish performance and payment bonds.
- Substantial completion
- The stage when the work is sufficiently complete for its intended use, triggering retainage release timelines, warranty periods, and the start of lien claim deadlines.