LARE Section 1 flashcards
LARE Section 1 · Build recall with a focused review session.
32 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Critical path
- The longest sequence of dependent activities through a project network; it determines the shortest possible project duration, and any delay to an activity on it delays the project finish.
- Total float
- The amount of time an activity can be delayed without delaying the project finish date; calculated as late start minus early start or late finish minus early finish.
- Free float
- The time an activity can be delayed without delaying the early start of any successor activity; equals the successor's early start minus the activity's early finish.
- Cost variance
- Earned value minus actual cost; a negative value means the project is over budget for work performed, while a positive value indicates under budget.
- Schedule performance index
- Earned value divided by planned value; a value below 1.0 means less work has been completed than planned at that point in the schedule.
- Estimate at completion
- The projected total cost of the project; when current cost efficiency continues, EAC equals budget at completion divided by the cost performance index.
- Lump sum contract
- A contract in which the contractor agrees to a fixed price for a defined scope; the contractor bears the risk of quantity errors and cost overruns unless changes are authorized.
- Unit price contract
- A contract that pays the contractor a fixed price per unit of measured work; the owner bears quantity risk because final cost depends on actual quantities installed.
- Cost-plus contract
- A contract that reimburses allowable costs plus a fee; the owner bears most cost risk, so audits and cost controls are typically required.
- Retainage
- A percentage of each payment withheld by the owner to protect against incomplete work or defects; released at substantial or final completion per contract terms.
- Change order
- A written modification signed by owner and contractor that adjusts contract price, time, or scope; it becomes part of the contract after execution.
- Construction change directive
- A written owner-architect directive ordering a change before price and time are agreed; the contractor proceeds, and the adjustment is later formalized in a change order.
- AIA G702
- The application and certificate for payment form used to summarize the contract sum, completed work, retainage, and amount due; the architect certifies the payment amount.
- AIA G703
- The continuation sheet that itemizes scheduled values and work completed by line item; it supports the G702 payment application and documents stored materials.
- Conditional lien waiver
- A waiver that becomes effective only when the stated payment is actually received; it protects the contractor or sub who has not yet been paid.
- Unconditional lien waiver
- A waiver that is effective upon signing regardless of whether payment is received; signing it before funds clear can extinguish lien rights.
- Substantial completion
- The stage when the work is sufficiently complete for its intended use; it typically starts warranties, allows owner occupancy, and triggers retainage release less punch-list holdback.
- Punch list
- A list of minor incomplete or defective items identified at substantial completion; correction is required before final completion and final payment.
- A201 general conditions
- The AIA document defining rights and responsibilities of owner, contractor, and architect; it covers submittals, changes, payments, and dispute resolution.
- B101 owner-architect agreement
- The AIA standard form of agreement between owner and architect; it defines basic services, compensation, and the architect's scope of responsibility.
- A101 owner-contractor agreement
- The AIA stipulated-sum agreement between owner and contractor; it incorporates the general conditions and sets contract sum, date, and scope.
- Submittal review
- The architect's review of shop drawings, product data, and samples for conformance with design intent; review does not relieve the contractor of responsibility for dimensions and quantities.
- Request for information
- A formal written question from the contractor seeking clarification of contract documents; responses are logged and may lead to a change order if scope or cost is affected.
- Schedule of values
- A contractor-prepared breakdown of the contract sum allocated to work items; it is the basis for progress payments and must be reviewed and approved by the architect.
- Liquidated damages
- A pre-agreed amount per day of delay beyond the contract completion date; it must be a reasonable estimate of actual damages, not a penalty.
- Bid bond
- A surety instrument guaranteeing the bidder will enter the contract if awarded; failure can result in the owner claiming the difference up to the bond amount.
- Performance bond
- A surety bond protecting the owner if the contractor fails to perform; the surety may complete the work or pay the owner up to the bond amount.
- Payment bond
- A surety bond that protects subcontractors and suppliers from nonpayment on a project; it provides a claim path when the contractor fails to pay.
- Addendum
- A written modification issued during bidding to clarify or change the contract documents; bidders must acknowledge addenda in their bids.
- Allowance
- A stated amount in the contract for an item not yet fully defined; actual cost is reconciled against the allowance and adjusted by change order.
- Contingency
- A reserve of time or money set aside for identified but uncertain events; it is not a slush fund and should be drawn down only through documented authorization.
- Constructability review
- A review of design documents for buildability, sequencing, and coordination before construction; it reduces changes and claims during the construction phase.