Prioritizing a Neighborhood Park Program Under a Fixed Budget

LARE Section 2 ยท Put your knowledge to work in context.

All case studies

Prioritizing a Neighborhood Park Program Under a Fixed Budget

A 1.8-acre neighborhood park has a construction budget of $1.6 million. Residents have requested a dog park, splash pad, community garden, basketball court, playground, restroom, and parking. Existing conditions include mature shade trees, a 6-foot grade change between the street and the rear of the site, and only 80 feet of street frontage. Planning-level costs are: restroom $350,000, splash pad $450,000, dog park $150,000, playground $300,000, community garden $75,000, basketball court $120,000, and parking $100,000. Annual operations and maintenance are estimated at 4% of construction cost. The department wants a park that serves multiple age groups but cannot fund everything in one phase.

1. How would you structure a program matrix to compare requests and recommend a final program?

Read the worked answer

I would build a matrix with the requested uses as rows and evaluation criteria as columns: capital cost, annual operations, footprint, age and user group served, compatibility with existing trees and grade, adjacency needs, accessibility, and equity gap. Each criterion would get a simple high/medium/low score or a weighted 1โ€“5 score, and I would show the cost per user group rather than only total cost.

The matrix would likely reveal that the splash pad and restroom consume half the budget but serve overlapping peak summer users, while the playground and garden serve different daily patterns. The dog park and basketball court are lower-cost but have specific siting needs. I would recommend a core program that fits within $1.6 million and keeps a 15โ€“20% contingency: playground, restroom, garden, paths, shade, and stormwater. The splash pad and dog park would be Phase 2 candidates, with the basketball court considered only if a suitable flat area exists without major grading. The recommendation should explain what is deferred and why, not simply list what is cut.

2. Identify two significant adjacency conflicts in the requested program and propose layout responses.

Read the worked answer

The first conflict is dog park versus playground. Dogs, noise, and odor are incompatible with young children, and the dog park needs a double-gate entry and a buffer. I would place the dog park at the rear or side edge with a planted berm and a separate path, not between the street and the playground. The second conflict is basketball versus quiet garden or seating. Basketball generates noise and needs a hard, flat surface, while the garden needs sun and quiet. I would separate them by the grade change or a dense planting buffer, and place the basketball court away from residential property lines.

A third practical conflict is restroom visibility and access: it should be central to the playground and garden but not dominate the limited frontage. The 6-ft grade change can be used to bury service functions or create a terraced seating edge, reducing the need for retaining walls. Parking should be minimized and located at the frontage, with accessible routes to the core. The layout should show these separations on a diagram, not just in prose, so the community can see the tradeoffs.

3. Propose a phasing strategy that respects the budget and the site constraints.

Read the worked answer

Phase 1 should deliver a complete, usable park rather than isolated amenities. That means the playground, restroom, accessible paths, shade trees, seating, and stormwater management, plus the garden if the budget allows. These elements establish the park's identity, serve daily users, and avoid the problem of a restroom-less playground or a path to nowhere. Phase 2 would add the splash pad, which has high cost and high summer demand but also high water and maintenance requirements. Phase 3 would add the dog park and basketball court if additional funding is secured.

Phasing should also follow construction logic. Utilities and grading for future phases can be installed in Phase 1 only if the cost is justified; otherwise, avoid overbuilding infrastructure. The mature trees should be protected during all phases, and staging areas should be shown on the phasing plan. I would present the phasing with an operations budget for each phase, because a splash pad or restroom adds annual cost that the department must absorb. The final recommendation should state what triggers Phase 2-funding, attendance, or a maintenance assessment-so the plan is adaptive rather than aspirational.