LARE Section 3 flashcards
LARE Section 3 · Build recall with a focused review session.
32 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Design-bid-build delivery
- Owner contracts separately with a designer and a contractor. Design is complete before bidding. Lowest responsive bidder builds. Longest schedule, but clear division of design and construction responsibility.
- Design-build delivery
- One entity holds both design and construction contracts. Owner states performance criteria. Faster delivery and fewer owner change orders, but the owner has less control over design detail.
- CM at risk
- Construction manager holds a guaranteed maximum price and subcontracts the trade work. Owner gains early cost and schedule input, and the CM carries risk above the GMP.
- Agency CM
- Construction manager acts only as the owner's adviser, for a fee, with no construction risk and no GMP. The owner retains all cost-overrun risk.
- Retainage
- A percentage, commonly 5 to 10 percent, withheld from each progress payment until substantial completion or as the contract states. It reduces contractor cash flow and tends to raise bid prices.
- Critical path
- The longest continuous path through the schedule network. It has zero total float, so any delay on it delays project completion unless the schedule is compressed.
- Total float formula
- Total float equals late start minus early start, which also equals late finish minus early finish. Total float is shared along a path; free float is specific to one activity.
- Construction change directive
- A written order directing the contractor to proceed with work before price and time are agreed. It differs from a change order, which is a signed agreement on scope, price, and time.
- Slope percent formula
- Slope percent equals rise divided by run, times 100. A 2 percent slope drops 2 feet per 100 feet. A 4:1 ratio equals 25 percent; 3:1 equals 33 percent.
- Accessible route running slope
- Maximum running slope for an accessible route is 1:20, or 5 percent. Anything steeper is a ramp and must meet ramp requirements, including landings and handrails.
- Ramp slope and rise limits
- Accessible ramps have a maximum running slope of 1:12, or 8.33 percent, and a maximum rise of 30 inches per run. Landings at top and bottom are at least 60 inches long.
- Accessible route cross slope
- Maximum cross slope on an accessible route is 1:48, about 2 percent. Steeper cross slopes cause wheelchair drift and are a common compliance failure on site plans.
- Accessible passing space
- Where a route is narrower than 60 inches, provide a 60 by 60 inch passing space at intervals. Continuous clear width minimum is 36 inches.
- Minimum drainage slopes
- Paved surfaces drain at a minimum of 1 to 2 percent; turf at about 2 percent. Level spreaders convert concentrated flow into sheet flow to prevent erosion.
- Cut and fill balance
- Sum cut and fill volumes separately. Apply a shrinkage or swell factor, then the net difference gives haul-off or borrow volume needed to balance the site.
- Contour reading rule
- Contours run perpendicular to the fall line. Closely spaced contours mean steep grade; widely spaced mean gentle grade. Touching or crossing contours indicate an overhang or drawing error.
- Concrete water-cement ratio
- The water-cement ratio governs concrete strength and durability. Lower water-cement ratio gives higher strength. A common site mix is 1:2:3 cement to sand to aggregate by volume.
- Concrete curing requirements
- Keep concrete moist and above about 50 degrees Fahrenheit. Cure 7 days for normal cement, 3 days for high-early-strength. Cold weather slows strength gain.
- Asphalt pavement layers
- Place base course, then binder course, then surface course. Compact each lift. Apply a prime coat between the base and the asphalt layers.
- Segmental retaining wall geogrid
- Geogrid reinforcement length is typically 60 to 70 percent of wall height. Use granular drainage fill and a perforated drain at the base of the wall.
- Pressure-treated lumber fasteners
- Use stainless steel or hot-dip galvanized fasteners with pressure-treated lumber. Preservative salts corrode standard fasteners. Specify ground-contact rated lumber where it touches soil.
- MasterFormat divisions
- Division 01 general requirements, 02 existing conditions, 03 concrete, 31 earthwork, 32 exterior improvements, 33 utilities. Specifications are organized by these divisions.
- Shop drawings vs. submittals
- Shop drawings are contractor-prepared fabrication and installation details. Submittals is the broader category and also includes product data, samples, and mockups.
- Punch list
- A list of incomplete or defective work identified at substantial completion. The contractor corrects these items before final completion and final payment.
- Rational method formula
- Q equals C times i times A. Q is peak flow in cubic feet per second, C is the runoff coefficient, i is rainfall intensity in inches per hour, A is area in acres.
- Runoff coefficients
- Lawn 0.15 to 0.35, gravel about 0.35, asphalt 0.90 to 0.95, roofs 0.90 to 0.95. For mixed areas, compute a composite C weighted by area.
- Time of concentration
- The time for runoff from the most hydraulically remote point to reach the design point. It sets the rainfall intensity used in the rational method.
- Detention vs. retention
- Detention holds stormwater temporarily and releases it slowly. Retention holds it permanently through infiltration or a permanent pool. Detention is sized to limit peak discharge.
- Pre- and post-development flows
- Detention must be sized so post-development peak discharge does not exceed pre-development peak discharge for the design storm.
- Bioretention components
- Engineered soil media, surface ponding depth, an underdrain, and an overflow. Treat the water-quality volume first, then attenuate larger storms.
- Grass swale design
- Side slopes 3:1 or flatter, longitudinal slope of 1 to 4 percent, and check dams to slow flow and promote infiltration.
- Manning's equation
- V equals 1.486 over n, times R to the two-thirds power, times S to the one-half power. n is about 0.013 for concrete pipe and 0.03 to 0.04 for grass channels.