Sri Lanka NVQ L3 Carpenter · Give each week a clear focus.

8 weeks · About 6 hours per week

Week 1

Occupational Health, Safety and Environment on the Carpentry Site & Tools, Equipment and Machinery for Carpentry

  • List the personal protective equipment required for sawing, chiselling, planning and site handling tasks, and state when each item must be worn

  • Identify five site hazards common to carpentry workshops and building sites, and describe one control measure for each

  • Demonstrate the safe setup and use of a circular saw and a hand plane, including guard checks, blade condition and clamping of the workpiece

  • Describe the correct storage, labelling and disposal of timber preservatives, solvents, adhesives and sawdust in line with environmental requirements

  • Explain the emergency and first-aid response for a deep cut and for eye injury from flying chips

Your checkpoint

A two-page hazard-and-control checklist covering at least 10 carpentry hazards, each with its PPE and control measure, written in your own words and checked against your own workshop

Week 2

Tools, Equipment and Machinery for Carpentry & Materials, Timber Technology and Material Selection

  • Name the main hand tools and power tools used in carpentry and state the purpose of each in one sentence

  • Sharpen and set a hand saw and hone a chisel edge, then test the edge on end grain

  • Select timber for a given job by comparing species available locally on hardness, durability, shrinkage and cost

  • Distinguish between seasoning defects such as checks, shakes, warp and case hardening, and explain how each affects machining

  • Match three common sheet materials and two adhesives to appropriate interior and exterior applications

Your checkpoint

A tool-and-material reference sheet listing 15 tools with their purpose and maintenance point, plus a timber selection table for five species used in Sri Lankan carpentry

Week 3

Setting Out, Measurement and Working Drawings & Materials, Timber Technology and Material Selection

  • Read a simple floor plan and elevation and extract all dimensions needed for setting out

  • Set out a rectangular building outline on the ground using the 3-4-5 method and check the diagonals for squareness

  • Convert scaled drawing dimensions to full size and record measurements in a consistent unit

  • Produce a cutting list from a working drawing for a simple item such as a door frame

  • Identify common drawing symbols for doors, windows, levels and section markers

Your checkpoint

A marked-up working drawing with a full setting-out sketch and a cutting list of at least 10 components, with diagonal checks recorded

Week 4

Formwork and Shuttering for Concrete & Quantification, Estimation and Work Planning

  • Describe the components of formwork for a beam and a column, and explain how each part carries wet concrete load

  • Erect a small slab or beam formwork mock-up and check it for line, level, plumb and tightness at joints

  • Calculate the quantity of timber, plywood and props needed for a given slab area from a simple drawing

  • Explain stripping times and the sequence for safe removal of formwork

  • Prepare a two-day work plan for a formwork task showing labour, materials and sequence

Your checkpoint

A formwork take-off for one slab and one column, plus a photograph or sketch of your erected mock-up with a level and plumbness check recorded

Week 5

Roof Framing and Roof Construction & Quantification, Estimation and Work Planning

  • Name the parts of a pitched roof, including ridge, rafters, purlins, wall plate, collar and barge board, and state the function of each

  • Calculate rafter length for a given span and pitch using the rise-and-run method

  • Mark and cut common rafters and a ridge for a small practice frame, keeping birdsmouth seats consistent

  • Estimate the quantity of roofing sheets, battens and fixings for a stated roof area

  • Sequence a roof erection plan showing safe access, lifting and temporary bracing

Your checkpoint

A cut and assembled half-scale or full-size roof frame section with a written rafter calculation and a materials estimate for a stated roof area

Week 6

Doors, Windows, Fittings and Joinery & Flooring, Ceilings, Partitions and Interior Finishes

  • Set out and assemble a door frame and hang a door so that it swings freely with even gaps on all three sides

  • Fit a lock, hinges and a door closer correctly and test the operation of each

  • Describe the construction of a window frame and sash and identify the weatherproofing details

  • Install a partition frame, fix plasterboard or ceiling sheets, and finish joints ready for painting

  • Explain the sequence for laying a timber floor and for fixing a suspended ceiling grid

Your checkpoint

A hung door in its frame with fittings operating correctly, plus a written step-by-step procedure for the partition and ceiling task

Week 7

Communication, Teamwork and Workplace Conduct & Quantification, Estimation and Work Planning

  • Give a clear five-minute verbal briefing to a small team on a carpentry task, including safety points and sequence

  • Write a short site instruction or progress note that is unambiguous and correctly dated and referenced

  • Prepare a simple estimate for a small carpentry job covering labour, material, wastage and overhead

  • Build a one-week work programme that sequences three tasks and shows dependencies

  • Describe how to raise a concern about unsafe work or a material shortage with a supervisor and record the outcome

Your checkpoint

A one-page job estimate and one-week work programme for a small carpentry job, presented verbally in five minutes and checked against a peer's questions

Week 8

Occupational Health, Safety and Environment on the Carpentry Site & Setting Out, Measurement and Working Drawings & Formwork and Shuttering for Concrete & Roof Framing and Roof Construction & Doors, Windows, Fittings and Joinery & Flooring, Ceilings, Partitions and Interior Finishes

  • Revise all ten domains using a self-made summary sheet of key facts, formulas and safety rules

  • Complete a timed mock paper of at least 40 mixed questions and score it

  • Re-explain the three weakest topics aloud without notes

  • Re-check setting-out, rafter length and quantity calculations for errors under time pressure

  • Confirm your tools, PPE and calculation methods are ready for assessment conditions

Your checkpoint

A scored mock paper with a written list of your three weakest topics and a one-page correction plan for each

Milestones

Week 2: Can name 15 tools with purpose and maintenance point, and justify a timber choice for three different applications without notes

Week 4: Sets out a rectangle square within tolerance using the 3-4-5 method and produces a correct formwork take-off for a slab and column

Week 6: Hangs a door that swings freely with even gaps, and calculates rafter length correctly for two different pitches

Week 8: Scores at least 70 percent on the timed mock paper and can state the correct method for each previously weak topic