MA Fire Sprinkler flashcards
MA Fire Sprinkler · Build recall with a focused review session.
32 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Light hazard density
- NFPA 13 light hazard design density is 0.10 gpm/ft² over a 1,500 ft² design area for wet systems, with the area adjusted per density-area curves.
- Ordinary Group 1 density
- Ordinary Group 1 occupancies require 0.15 gpm/ft² over 1,500 ft² under NFPA 13 density-area design.
- Ordinary Group 2 density
- Ordinary Group 2 occupancies require 0.20 gpm/ft² over 1,500 ft² under NFPA 13 density-area design.
- Dry system design area
- NFPA 13 requires a 30% increase in the design area for dry pipe and preaction systems compared to wet systems.
- Minimum end-of-line pressure
- NFPA 13 requires at least 7 psi at a single sprinkler at the end of a line, or 15 psi where multiple sprinklers are at the end.
- Hazen-Williams C factor
- C=120 for black steel pipe and C=100 for galvanized or cement-lined pipe in NFPA 13 hydraulic calculations.
- Elevation pressure
- Each foot of elevation change equals 0.433 psi; add this to the demand when the system is above the supply.
- Flow test extrapolation
- Available pressure at the system demand is extrapolated from a hydrant flow test using the 1.85 power relationship between flow and pressure drop.
- Safety margin
- A margin, commonly 10-15 psi, is subtracted from the available supply curve to ensure the system demand is met.
- Domestic demand addition
- When sprinkler and domestic systems share a supply, the domestic demand must be added to the sprinkler demand in the calculation.
- 13R height limit
- NFPA 13R applies to residential occupancies up to and including four stories above grade; taller buildings require NFPA 13.
- 13D two-sprinkler rule
- NFPA 13D systems must be designed to supply at least two sprinklers simultaneously at the design pressure.
- 13R design density
- NFPA 13R requires 0.05 gpm/ft² over the room area with a minimum of two sprinklers, or the listed head flow if greater.
- 13D water supply duration
- NFPA 13D systems typically require a water supply capable of supplying the design demand for 7 minutes for a single-family dwelling.
- 13D omission areas
- NFPA 13D permits omission of sprinklers in closets, bathrooms, garages, and certain concealed spaces under defined conditions.
- Weekly wet system check
- NFPA 25 requires weekly inspection of wet system gauge readings and control valve positions.
- Quarterly alarm test
- NFPA 25 requires quarterly testing of waterflow alarm devices, valve supervisory switches, and main drain flow on wet systems.
- Annual dry valve trip
- NFPA 25 requires an annual partial trip test of dry pipe valves and a full-flow trip test every three years.
- Sprinkler head replacement
- Fast-response sprinkler heads must be replaced at 20 years and standard-response heads at 50 years, or per the manufacturer's listing.
- Gauge calibration interval
- NFPA 25 requires gauges to be replaced or recalibrated every 5 years.
- Impairment procedure
- When a system is impaired, notify the fire department and owner, post impairment tags, and implement a fire watch where required.
- Fire pump churn pressure
- Fire pump shutoff (churn) pressure is typically 100-140% of rated pressure and must not exceed the system component rating.
- Fire pump 150% flow
- At 150% of rated flow, a fire pump must produce not less than 65% of its rated pressure.
- Fire pump test header
- Fire pumps require a test header sized for 150% of rated flow and an annual flow test at churn, 100%, and 150%.
- Standpipe classes
- Class I provides 2½ in outlets for fire department use, Class II provides 1½ in outlets for occupants, and Class III provides both.
- Standpipe flow test
- NFPA 25 requires standpipe systems to be flow tested every 5 years and hydrostatically tested at 200 psi or 50 psi above static.
- Private main minimum size
- NFPA 24 requires private fire service mains to be sized for the required flow, typically 6 in for hydrant mains and 4 in for sprinkler-only mains.
- Working plan contents
- Working plans must show piping, sprinkler locations, hanger details, hydraulic calculations, and water supply data, signed by the responsible designer.
- Hydrostatic test
- NFPA 13 requires a hydrostatic test at 200 psi for 2 hours, or 50 psi above working pressure if higher.
- Sprinkler contractor license
- Massachusetts requires sprinkler contractors to hold a state license and employ licensed sprinkler fitters to perform installation work.
- Permit requirement
- A fire department permit is required before installing, altering, or repairing a sprinkler system in Massachusetts.
- Final acceptance
- A certificate of completion or final fire department inspection is required before a sprinkler system is placed in service.